RATE ANALYSIS FORMULA

Item No. 201 a


Providing and laying Granular sub base in approved
thickness as per profile and camber of road
Description:
including watering and compaction to 98% modified
AASHTO.
Assumed Daily (8 Hours) Progress: 480 CM
Resources for above progress

MANPOWER
Code Description No. Hours Rate Amount Rs.
1041 HELPER (SEMI-SKILLED) 2 8 143.00 2,288.00
1051 LABOUR (UN-SKILLED) 4 8 118.00 3,776.00
Total Manpower Charges Rs. 6,064.00

EQUIPMENT
Code Description No. Hours Rate Amount Rs.
3007 GRADER. 165 H.P. 2 6 5731.88 68,782.56
3015 COMBINATION ROLLER 18 T. 2 8 4468.25 71,492.00
3024 WATER TANK BOWSER TYPE 12000 LTR. 2 6 2067.26 24,807.12

3086 PUMP 4" DELIVERY (DIESEL) 1 6 566.75 3,400.50


Total Equipment Charges Rs. 168,482.18

MATERIAL
Code Description Unit Quantity Rate Amount Rs.
2017 GRANULAR SUB0BASE A CM 625.00 754.27 471,418.75
2065 WATER 1000 LIT 90.00 105.00 9,450.00
Total Material Charges Rs. 480,868.75

Total Charges for 480 CM 655,414.93


Charges per Unit (Rs.) 1,365.45
Add Over Head/Contingencies 4% 54.62
Add Contractor's & Profit 10% 136.54
Add Income Tax 8% 109.24
Rate per CM 1,665.85
Rate per CFT 47.17