201 A Sub Base
201 A Sub Base
MANPOWER
Code Description No. Hours Rate Amount Rs.
1041 HELPER (SEMI-SKILLED) 2 8 143.00 2,288.00
1051 LABOUR (UN-SKILLED) 4 8 118.00 3,776.00
Total Manpower Charges Rs. 6,064.00
EQUIPMENT
Code Description No. Hours Rate Amount Rs.
3007 GRADER. 165 H.P. 2 6 5731.88 68,782.56
3015 COMBINATION ROLLER 18 T. 2 8 4468.25 71,492.00
3024 WATER TANK BOWSER TYPE 12000 LTR. 2 6 2067.26 24,807.12
MATERIAL
Code Description Unit Quantity Rate Amount Rs.
2017 GRANULAR SUB0BASE A CM 625.00 754.27 471,418.75
2065 WATER 1000 LIT 90.00 105.00 9,450.00
Total Material Charges Rs. 480,868.75