3 The UGW shall produce and submit updated services drawings to the
Employer’s Representative within three (3) months from award of Contract
incorporating the result of the trial trenches. These services drawings shall be
updated every three (3) months thereafter to reflect the latest
details/changes on the route, location, position and depth, etc., of the
services based on the results of the trial trenches, cable detection, as-built
details of diverted services, etc. The UGW shall ensure the correctness and
accuracy of the updated services drawings at all times. Any cost arising from
damage to the existing services as a result of error(s) in the drawings shall be
borne by the UGW.
P15.8.2 In addition to the temporary diversion, there are also affected private drains,
authority drains, roadside drains and box culverts that may need to be
permanently diverted. These drains shall be constructed to their original
sizes. All permanent diverted drains shall be constructed in accordance to the
authorities standards and requirements.