WET MIX MACADAM – 1ST & 2ND


LAYER WITH PAVER
SUBMIT
MATERIALS,
PROCEDURES AND
ITP FOR
APPROVAL.
ARE MATERIALS AND PROCEDURE APPROVED
YES

APPROVED GSB LAYER II


OR WMM 1ST CLEANED &
CONFINED.
NO

ARRANGEMENT OF
EQUIPMENTS &
LABOUR
SAFETY

SURVEY

FOLLOW WORK PROCEDURE

LAYING COMPACTION
& QC TEST OF WMM
REMEDIAL ACTIONS MIX.
INSTRUCTED BY PMC OR
CONCESSIONAIRE FIELD DENSITY

IS COMPACTION OK?
NO
YES

LEVEL &
CAMBER CHECK

IS LEVEL & CAMBER OK?


NO YES
RECTIFICATION OF APPROVAL
LEVEL & CAMBER. FOR NEXT
LAYER
END