AIN TSILA DEVELOPMENT

Main EPC Contract


A-CNT-CON-000-00282

SUB-CONTRACTOR COMMENTS RESPONSE SHEET


PO NO :

Document Title : Isolation Areas and Crew Change Management Procedures Sub-Contractor Transmittal No. : Date :

PIUL Review Transmittal No. : Date :23 Aug 2020

PIUL Position
Sl. No. Document No. Rev PIUL COMMENT SUB-CONTRACTOR RESPONSE
( Open or Closed )
01 3.1 Arrangement of temporary 1: The containement is done in a professional way. The location Open
containment zones 1. Please provide details of where the containment location is, so depends on the number of the employee available. The containement
it can be reviewed by PIUL HSE? takes place at IRARA hassi massoud for 8 days. Then, worker took the
2. Please provide the contact details of the individual responsible test to check his situation. In case there are no places at IRARA,
for the containment team.
workers will be mobilized to TBRHO camp for 14 days in isolated rooms.
3. Please provide details of the Company doctor.
4. The cleaning team must wear full PPE at all times (Face mask, 2: We have a doctor the responsible of taking care them and measures
disposable gloves, safety glasses or face shield). temperature. A helper to delivery food wearing appropriate PPE to
avoid anything.
3: The doctor belongs to clinic IBEN Sinna
4: All workers are provided with full equipment & avoid personnel
interatio
02 3.2 Health prevention and protection 1. Our TBRHO HSSE is sending the monitoring register for new Open

measures:
1. Health monitoring will take place twice per day by the company comers.
Doctor and not once as stated in the document. Temperature 2. The reports is always sent to PIUL HSSE at AM & PM
checks should be taken AM and PM.
03 3.3. Transport arrangements for the 1. Social distancing rules are 2 meters not 1 meter. 1. Workers are always wearing masks and respect the distance. Open
2. There is no mention of your drivers conducting quarantine?
Crew Changes:
Will this happen? Please elaborate.

SUB-CONTRACTOR SIGN OFF


Prepared By: ___Sahli. Seyfeddine_____________________
COMPANY SIGN OFF
Date :
PIUL SIGN OFF
Signature: ___________________________
AIN TSILA DEVELOPMENT
Main EPC Contract
A-CNT-CON-000-00282

SUB-CONTRACTOR COMMENTS RESPONSE SHEET


PO NO :

Document Title : Isolation Areas and Crew Change Management Procedures Sub-Contractor Transmittal No. : Date :

PIUL Review Transmittal No. : Date :23 Aug 2020

PIUL Position
Sl. No. Document No. Rev PIUL COMMENT SUB-CONTRACTOR RESPONSE
( Open or Closed )
Date : Date :
Approved By: _________________________ Approved by : _________________________________ Approved by : _________________
Date :
Signature: _____________________________ Signature: ____________________________________ Signature: ____________________