Professional Documents
Culture Documents
Week 4 Module 4 Project Cost Estimation
Week 4 Module 4 Project Cost Estimation
Week 4 Module 4 Project Cost Estimation
How much can budget affect a project? Have you ever been on a project that
was severely under budgeted? If so, how did that affect the project?
Module 4
Learning Objectives Do you recall the concepts from last
•Understand the types of estimates module on Critical Path Method? Write
and their accuracies your thoughts on how it can help in
deciding the timeline for the project.
•Describe the difference between
top down and bottoms up estimates
•Create parametric estimates
•Create and define a project budget
• Provide a cost baseline against which a project team can monitor the
Project
• Provide data for schedule and progress measurement
• Evaluate the cost impact of a change in the scope of facilities or services
• Provide the basis for bidding
• Establish a benchmark for evaluating a third party bid/proposal
Your Notes:
Scope Installation
Scope
Documents Labor
Quantified
Prepared Priced Assemble Conduct
External Estimate Reviews Transmit
Authorization Estimate Plan Material
Pricing for Final to Client
to Proceed Developed Pricing Benchmark Approval
Solicited
Various
Generate Price Home Components
Internal Office
Pricing Services
An estimate should be viewed as a Project within the Project and executed as such.
Your Notes:
Module 4
Preparing an Estimate Continued
Estimating Standards
• AACE International is a recognized source of recommended practices
(RPs) for estimating in multiple industries and geographies.
• AACE International have published Recommended Practices (RPs) on
earned value, risk management, contingency and other estimating
related areas.
• In the following sections, we will reference the AACE RPs as a basis for
estimates.
Estimate Classes
Your Notes:
Module 4
Estimate Bases
Basis of Estimate
Estimate Plan/Basis
All of the Baseline elements are part of
A typical estimate plan
the Basis of Estimate:
describes how the estimate
•Project Charter or Contract will be prepared and is later
including Business Case (Project converted to the basis which
Framework) then contains:
•Scope Baseline (Services and • Product/Services Scope
Product)
• Work Breakdown
•Project Management Plan
Structure / Cost Elements
•Cost Baseline
• Source and Values of
•Schedule Baseline
Pricing and Labor Costs
•Risk Register
• Drawings and
Red items are those cited by PMI as the Specifications
baseline
• Contractual Requirements
The Estimate does not make sense except
/ Labor Posture
in this context.
• Project Execution Plan /
Notes: Project Schedule
• Approach to Contingency
/ Escalation / Currency
• Approach to Allowances /
Exclusions / Qualifications
• Estimate Schedule and
Resource requirements
Your Notes:
Module 4
Types of Estimates
Analogous Estimates
• Based on a similar project or a
similar section of a project.
Analogous Parametric • Some adjustments are made to
account to know differences
Basic approach is:
“The last time we did something
similar it cost X; this time should be
Semi- about the same.”
Detailed
Detailed Relies on judgment and experience to
estimate the costs.
Parametric estimates
• Capacity Factored
• Equipment Based
Semi-Detailed Estimate
A semi-detailed estimate is one employing either capacity or
factor/modeling based techniques in estimating direct field costs for
some portions of the project with the balance of the direct field costs
estimated in a detailed manner using some method of quantification and
unit pricing. May employ frequency data and factors in the
determination of quantities
Detailed Estimate
A detailed estimate is one in which each component or group of
components has been quantitatively surveyed and priced, using the
most realistic unit prices available. Quantities are determined from
drawings or sketches and specifically identified
Estimate Reviews
Estimate reviews are the key to quality. There are several levels of
review.
1. Functional Peer Review
2. Discipline Review
3. Project Review
4. Project Sponsor Review
5. Customer Review
Your Notes:
Module 4
Cost Baseline
Cost Baseline
It is typically divided into WBS work packages and then time-phased using the
project schedule. Estimate contingency and risk contingency are time phased
per their related component.
Module Assignments:
❑Peer Review: Project Assignment
❑Discussion: Kaz and Tom weekly conclusion
❑Quiz: End of Module 4 Quiz
Summarize this Module and jot down how you will personally use this material: