Professional Documents
Culture Documents
Overview of Microwave
Overview of Microwave
Overview of Microwave
SECTION – C
OVERVIEW
OF
MICROWAVE
1.0 The following Digital Microwave schemes are working in DOT Network.
1.1 13 GHz 34 Mbps Microwave System is used for junction working and in this
system, each RF channel can carry 480 Telephone channels.
1.2 7 GHz 34 Mbps system is used for thin route applications and each RF
channel can carry 480 Telephone channels.
1.3 6 GHz 140 Mbps Digital Microwave System is used for trunk route
applications and in this system each RF channel can carry 1920 Telephone
channels. The present capacity of the system is 3 plus 1 radio channels and
ultimate capacity is 7 plus 1 radio channels. But we will be able to utilize (5+1)
chls only because chls 1 and 8 have been reserved for satellite working. The
system operates in upper 6 GHz band (6430 MHz 7110 MHz) and employs
16 QAM modulation. The equipment is supplied by M/s Fujitsu and is installed
and commissioned on the following routes.
(The route line diagram is shown in Fig.1 for all the routes).
Fig. 1
Route Line Diagram
fo : 6770 MHz
lower half of band : fn = fo–350+40n
upper half of band : fn' = fo–10+40n
n = 1, 2, 3, 4, 5, 6, 7 or 8
Fig. 2(a)
Radio Frequency Channel Arrangement
Fig.2(b)
Radio Frequency Channel Arrangement
(U6 GHz, CCIR Rec. 384–3, 6, 4 to 7.1 GHz)
The radio frequency channels assignment for Bombay Panjim route is shown
in Fig.3 as an example. Polarisation employed (V/H) at various stations is also
depicted in the figure.
4. Frequency Bands
The Frequency bands and the capacities which are proposed to be used by
digital microwave and UHF systems in the country are given below :
– The ability to regenerate at each repeater with the result that circuit
performance becomes essentially independent of length.
– The plentiful capacity for data traffic and the ability to support an IDN
and subsequent potential involvement into an Integrated Services
Digital Networks (ISDN).
Associated with the use of higher frequencies for digital radio are reductions
in spectrum congestion and equipment size making such equipment easy to
transport and install.
Most of the disadvantages of high capacity DRRS are being eliminated with
the second generation of equipment coming onto the market. Major power drain
reduction has occurred, more powerful equalizers have been incorporated as a
standard part of the equipment and additional drop and insert capacity is being
introduced.
The salient characteristics for the analogue bearer are that the basic noise
and intermodulation noise from each hop are cumulative, the voice frequency (VF)
channel signal–to–noise (S/N) ratio depends on the received input signal level and
more particularly, on the carrier–to–noise (C/N) ratio and that co–channel carrier–to–
interference ratio of 30 dB makes the circuit quality unacceptable. The salient
characteristics of the digital bearer are that the performance is uniform over a wide
range of receive input levels and deteriorates rapidly over a small range of C/N ratios
near the threshold. In addition, the introduction of even a 30 db C/N ratio has only a
marginal effect in worsening performance near the threshold.
In view of the above, different definitions of the quality, the CCIR definitions
for the performance of hypothetical reference circuit (HRC) for analog system and
hypothetical reference digital path (HRDP) for digital system are as follows :
Analog System
Following noise figures are not to be exceeded for the time percentages
indicated :
Digital System
Following BERs not to be exceeded for the indicated time percentage as
given below :
–7
(a) 1 x 10 BER for more than 1% of any month.
–3
(b) 1 x 10 BER for more than 0.5% of any month.
For actual paths which differ from the HRDP in composition or are much
smaller in length the performance criterion under consideration by the CCIR is as
follows :
When a path is established over a link which is less than the HRDP (2500
kms), but greater than 280 kms and which differs in composition from the HRDP, the
allowable time percentage should be proportional to the link length L (kms) of the
link.
–7
(a) 1 x 10 BER for more than (L/2500) x 1% of any month.
–3
(b) 1 x 10 BER for more than (L/2500) x 0.05% of any month.
When a path is established over a link which is less than 250 kms, it is
proposed that BER not to be exceeded for the indicated time percentage as given
below :
–7
(a) 1 x 10 BER for more than (280/2500) x 1% of any month.
–3
(b) 1 x 10 BER for more than (280/2500) x 0.05% of any month.
Note : This takes into account fading, interference and all other sources of
–3
performance degradation. It does not include BER greater than 1 x 10 for periods
exceeding 10 consecutive seconds. This condition is included in the availability
criterion. The high BERs caused by switching operations are included in the above
criterion, but not the ones caused by scheduled switching for maintenance).
–3
Availability criterion is 1 x 10 BER (measured for 10s time interval) not
exceeding 0.3% of a year.
It is important to note that during the conditions of fades well above the
threshold margin, the system is almost perfect. In interpreting this statement, it
should be kept in mind that threshold margin does not necessarily imply flat fade
margin. This will be amplified further when the effects of propagation on digital
microwave systems are discussed.
SURVEY REPORT
(1) Clearance
(2) Preparation and Demand and Justification for the route and proposal
for the route.
(7) Placing of orders for tower materials, equipment, battery, power plant
and engine alternator, antenna, W.G., etc.
(9) Obtaining power supply to building and water supply where required.
Table 1
Before the survey is undertaken, the type of system, the terminals and
intermediate dropping stations are predecided. The possibility of utilizing any existing
Microwave tower is also studied. The various specific data to be calculated while
surveying and the input data for calculating them are listed in the Table below :
Table II
A good survey is one which takes into account not only the technical
requirements like line of sight, received signal level, interference, etc. but also the
cost economy. For instance, while locating the repeater station on a hill top, a cost
compromise should always be struck between the following :
height is normally limited to 100 metres. In view of the fact, that line of sight is the
prime consideration in route survey, in some hilly areas it may be necessary to
provide the tallest tower (100 M) on the hill top, in which case, a sacrifice has to be
made in cost in lieu of technical requirement. There are three types of towers
available in Indian Telecom. Dept., namely Light Weight (LW), Heavy Weight (HW)
and Special Heavy Weight (SW) towers. They are respectively used for light, medium
and heavy traffic routes depending upon the number of microwave systems (and
hence, the no. of antenna).
The Survey Division has to study the feasibility of the route and location of
Microwave routes in respect of the following points also in addition to the line of sight
requirement :
(ii) Suitability if soil for civil works like building and tower foundation.
(v) The local tie cable length required from the terminals and dropping
repeaters to the exchange building.
(vii) Addition of higher capacity system in the same route (without any
additional infrastructure) when traffic warrants at a later date.
The Survey Report furnishes the complete details of the proposed site like the
location with latitude and longitude, its survey no., ownership, altitude above MSL,
distance from a reference point, etc. It also furnishes all technical details as given in
Table II. The Survey Report for interstate routes whose cost does not exceed one
crore is approved by the concerned G.M. Projects. The other reports are approved by
the Directorate. The Survey Division also takes action for filing applications for
SACFA (Standing Advisory Committee on Frequency Allocation) Clearance. The
BRBRAITT / MAY-2002 228
J.T.O. (Phase I) : Fundamentals of Transmission
The Dept. of Telecom. has decided to go in for Digital Systems for all new
routes and also for the routes where the equipment has not been ordered. The path
loss and fade margin criteria for digital routes are stringent. The calculation of various
data for both analogue and digital routes are cumbersome and requires the use of a
computer for easy and speedy results. In fact, the Southern Telecom. Project is
already employing a mini–computer at its survey Division in Madras.
The main objective of the function of the SACFA Board is to investigate the
interference possibilities, etc. and allot the frequency and spectrum for new routes.
All types of Microwave routes should be cleared by this body as far as the frequency
to be used, the location, the height of tower are concerned. This body takes the
safety aspect from Aviation point of view (of civil as well as Defence flights) also.
Hence, while clearing the licence for a new route, this Body specifically mentions
whether night warning or both Day and Night warning are to be provided for the
Microwave towers. Night warning is by means of aircraft warning lamps and day
warning is by means of painting the tower with alternate bonds of international
orange and white. The SACFA Board also considers the distance of tower location
from the nearby Airports and ensures that the specified minimum distance is
maintained from the airport. The SACFA Board takes the individual clearance from
the member Departments, before clearing a particular Microwave route. In Project
In addition to the above, the Regional Boards liaison with local bodies like
Municipalities and Corporations to ensure that taller buildings are not permitted for
construction which may cause near end obstruction to the Microwave beams once
the route is commissioned. The user Department should complete the erection of
tower within the licensed period which is normally 3 years, otherwise, should intimate
the fact to SACFA and get the licence renewed. The user Departments should also
monitor whether any tall structure is raised in the path length of the MW route after
the route is commissioned and should immediately bring it through Regional Boards
to the notice of Municipality/Corporation for necessary action.
(1) Land
1.4.1 Land
The extent of land is decided on the basis of type of Microwave building, type
and height of tower, the soil bearing capacity of microwave site location, the
requirement of staff quarters, the extent of approach–road from the main public road,
etc. The probable cost of land is indicated in the Survey Report. Based on the cost of
land and the area of land required, the land cost is worked out.
1.4.2 Buildings
Table III below gives the type of building and where they are used. Since the
cost of foundation of the building depends upon the soil bearing capacity and number
of floors of building, these factors should be taken before the cost of construction is
arrived at. Table IV gives the standard for type and No. of quarters to be provided for
various types of microwave system. The cost provided under this item should include
compound wall/fencing, internal and external services, approach road and
electrification.
Table III
LW : Light Weight 60 M
Light Weight : 100 M
Table IV
Table V
Directorate has laid down that all transmission equipment shall be designed
to work off with 48V power supply. Hence, wherever, the earlier versions of
equipment working off with 36 and 24 V are available, suitable dropping (DC–DC
conversion) arrangements are to be made to make them to work off from a single
48V source.
As per the same explanation above, the batteries are to be 48V. But their
capacity is decided by the three factors : (1) Frequency of power failures, (2)
Duration of power failures, and (3) The connected load. The normal practice is to
provide two sets of batteries simultaneously on float. Suitable size of cable/copper
busbar is to be provided so that the total drop from battery terminal to load point for
full load current shall be less than IV.
Majority of the power plant supplied currently work off from 3–phase supply.
Hence, the engine–Alternator to be provided at the MW station has to cater for this
requirement. For UHF repeaters and terminals 12.5 KVA, 3–phase set is sufficient
whereas 35 KVA sets are provided for W/B stations and N/B terminals, where the
MW station is located in the existing telecom. Complex with more number of
equipments (Tml. and MUX) then a suitable higher capacity set is to be provided.
1.4.5 Equipment
This shall contain the cost of radio equipments including supervisory (this
may be imported to indigenous), antenna, waveguide, pressurisation equipments,
multiplexing and testing instruments.
1.4.6 Vehicles
Types of vehicles required for carrying out the installation works are to be
provided for. If full vehicle cost is not justified (for instance if UHF routes) then part of
the cost of vehicle is debited and remaining cost in other estimate could be shown.
The Project estimates up to one crore are sanctioned by G.M. (Projects) and
above that limit is forwarded to Directorate for sanction.
concerned Project Division. To identify the sites and pegmark them, a joint statement
is signed by both the parties for having correctly located the site selected by survey
division.
Afterwards, the Project division takes the initiation for procurement of the
required land for building, tower, staff quarters and approach road. The ownership of
the land can be broadly classified under :
(a) Private
(b) Govt. Promboke (the ownership rests with Revenue Department
(c) Endowments Land,
(d) Other Govt. Department's Land.
As far as the land under category (c) and (d) are concerned, it is not possible
to acquire them. It is possible to directly purchase the endowments land at the rate
fixed by Revenue authorities. If the other Govt. Department is willing to dispose their
land as surplus, it is possible to transfer them through Revenue Department, at the
rate fixed by them.
The Private land can be acquired whereas the Govt. land can be alienated. Of
all the above categories, the Govt. land (b) is the easiest one to get. Private land can
be acquired for MW purpose using urgency clause dispensing with Sec.5(A) of the
L.A. Act. In spite of this provision, the land acquisition proceedings are lengthy and
time consuming and takes minimum of a year or more to get the land from the date of
filing the L.A. Application. Provision is also available to get the land on advance
possession from the owner immediately subject to payment of interest on the land
value plus solatium, provided the land owner agrees to dispose this land at
acquisition rate. But this is a rare case and majority of the private land owners do not
agree since the market value of land is much more than the acquisition rate. If the
land owner is not willing to give his land on advance possession pending acquisition,
then it is possible for the District Collector (Revenue authorities) to give advance
possession till the award is passed. As per the amendment of LA Act in Oct. 1984,
the interest is fixed at 9% up to one year and 15% for the period more than one year.
Hence, it shall be clear that the land acquisition application shall be filed as early as
possible to avoid delay.
However, one does not wait for finalisation of layout and preparation of
Detailed Estimate till the land is actually made over to Project authorities. The
estimate preparation, layout finalisation are done side by side with land acquisition
proceedings so that no time is lost after getting the land to start the work.
The Directorate orders the tower materials on any of the above factories.
The order for all the above items are placed subsequent to project estimation
sanction and are processed at various levels. The DET, MW Project being the
ultimate consignee of the various stores, organises the godowns, watch and ward
etc. and keeps track of the materials despatched from various factories. Any loss or
damage of the stores are taken up with the appropriate transport/insurance agencies.
If the equipment is imported, the customs/port clearance is arranged, equipments
verified and any claim is raised before the expiry of the marine insurance period.
(ii) All the four legs of the tower foundation should maintain the same level with
reference to the bench mark. Any deviation in this will adversely affect the
verticality of the tower.
(iii) There should not be any rotational tilt of the stems. This means that all the
diagonals of the stem should fall on the diagonal of the tower base.
(iv) Correct size of template should be used for fixing the anchor bolts and the
correct size of anchor bolts for the specified tower (size and type) should be
used. Any mistake in this respect will result in irrepairable damage and the
rectification is possible only by dismantling the foundation work.
(v) Suitable type of foundation design based on the SBC of the soil and soil
analysis results should be adopted. The competent authority to decide the
tower foundation design is Civil Wing.
(vi) The settlement of Tower foundation allowed, to keep the verticality within
limits is 12 mm absolute and 16 mm differential. Foundation design should be
done taking this into account and for a maximum wind speed of 200 km/hr.
(iii) The type of electrical wiring whether surface pattern or concealed should be
decided before the starting of the building, so that suitable conduits scan be
burried, if necessary. It is also necessary to finalise the underground ducting
(piping) arrangements much in advance so that the pipes can be laid at the
appropriate time of execution of civil works. These ducts are necessary for
AC mains leading interconnection for dc leads between battery, power plant
and equipment earth wires, etc. These ducting arrangements have been
standardised for the various standard buildings like Z, Y, X, special Y and
special X buildings.
(iv) The type of floor for equipment room is Mosaic floor and for other rooms
cement concrete floor.
(v) The position and type of engine foundation should be decided and should be
completed before taking up flooring in engine room.
(vi) The position and number of exhaust fans in battery room should be decided
and suitable holes provided in the wall.
(vii) The location of fans should be decided and suitable fan hooks provided at the
time of roof cacting.
(x) Wherever, water supply is available easily, (from local body or through
borewell/open well) toilets are to be constructed with suitable external
services. Where water supply is scarce, the toilet room shall be used as a
store room and shall be constructed accordingly.
like vertical expansion, if any, internal and external services, if any, staff quarters
required, compound wall if required and internal approach road, etc. Simultaneously,
DET MWP coordinates with E.E. (Civil) concerned for assessment of SBC and site
survey particulars. These details are submitted to S.E. (Civil) and E.E. (Civil). The
SEC's office decides the type of foundation for tower and building and prepare the
preliminary estimate and submits to Director, MWP for according AA and ES, SE(c)'s
office prepares the tender schedule and sends it to EEC's office for floating tender.
EE(c) floats tender and after opening, forwards to SE(c) for approval. SE(c) confirms
the approval and issues the work order to the contractor whose tender is approved
and, thereafter, the work is commenced and EE(c) supervises the work and makes
payment of bills in his office. The procedure is similar for electrification work done by
the electrical wing of the Department.
However, when the Civil Wing executes the civil works DET MWP concerned
keeps liaison and coordinates at all levels so that the salient points, explained for
tower foundation and building. In the previous paragraphs are followed strictly. He
shall personally check up the anchor bolts fixing so that no mistakes are made at this
stage. After the completion of the work, the tower foundation, building including
electrification, staff quarters, if any, are made over to DET MWP for taking further
installation works.
States like Karnataka, charge different tariffs and so a separate single phase supply
for lights and fans of the MW building and a 3 phase supply for power plant have to
be obtained. A model calculation for required power supply is shown in table. The
State Electricity Boards of some states demand for payment of voluntary loan
contribution by the consumers to the extent of the estimated cost of providing electric
supply. In this connection, the survey division has to make careful study of availability
of LT power supply easily to the MW site chosen. Otherwise, the cost of providing
electric supply mounts from a few thousands to more than a lakh also and this
amount is to be deposited to the S.E.B. as advance (to be repaid to the Dept. of
Telecommunications after 5 years with nominal interest). The common mistakes
committed by Survey Division – In this respect is failure to identify the nearby electric
alignment as high tension or low tension. While it is possible to extend supply
through a transformer from the 22 KV line, the other extra HT lines like 110 KV, 220
KV and above are not available for direct distribution of supply to customers. Hence,
if there is no 22 KV distribution line within reasonable distance (say 1 or 2 Km >, then
Survey officials should study whether it is worth shifting the site. In this connection,
the paragraph under survey and feasibility report for MW routes may be referred to
where the cost economy study on various factors is explained. Wherever the factors
like line of site, availability of land, etc. force the location of MW site in a remote place
where electricity is not available in the nearby area, then there is no other way except
spending a little more in obtaining the electric supply. The Electricity Department
while preparing their estimate for cost of provision of electricity, takes into account
that they will get back their investment in 5 years time. This means that 1/5 th of the
estimated cost is fixed as minimum guarantee and the consumption of electricity per
annum in the MW stations. Concerned should be the differential amount to Electricity
Department towards minimum guarantee. This aspect also should be taken into
account while site selection and calculation of load particulars for the MW station.
The S.E.B. registers the application form and issues a serial No. in the waiting
list. Unless the building including electrical institution is ready by the time the turn for
the particular connection comes, then the priority lapses and the serial number will go
down in the waiting list. To avoid this perfect coordination between S.E.B. autorities
and the MW building construction, agency is required. The Telecom Department has
BRBRAITT / MAY-2002 243
J.T.O. (Phase I) : Fundamentals of Transmission
to pay Security Deposit and Service Connection Charges to S.E.B. before the actual
connection is effected.
The source of water supply may be of two categories namely, (1) Municipal
water supply, and (ii) well water. Wherever, the well water is potable, the same is
provided either by means of open well or borewell. If they are not potable, then
Municipal water supply can be arranged. Wherever the staff quarters are provided in
the MW compound itself, it is essential to arrange for Municipal water supply. The
attended MW buildings are provided with over head tank and running water facility for
the toilet. The repeaters (unattended) are not provided with running water facility,
though water supply facility is provided.
As for electricity supply, Municipal water supply also be to applied for with
local body well in advance before the completion of the building and pursued by
Project Organisation at DET's level. Open well/borewell facility can be done directly
by project or through civil wing as the case may be.
The tower materials for a given tower can be classified into three categories,
viz. (i) Materials for super structure, (ii) for ladder and waveguide racks, and (iii) for
antenna fixtures and platforms.
(i) After erection of base plates over the stem, the legs for the first panel
is fitted and bolted. Each panel is of 10 M height. Then the belt and
scissors members of first panel (0 to 10 M) is fitted and bolted. After
all the members of superstructure in first panel is fitted, all the nuts are
tightened.
(ii) Then the second panel members are fitted and after completion of
this, the first panel members bolts and nuts are fully tightened.
(iii) After the members of third panel is fitted and bolted, the second panel
is fully tightened. This process is continual till the superstructure is
completed. Afterwards, the ladder, waveguide rack and antenna
fixture and platforms are erected.
Wherever, the SACFA clearance specifies for Day and Night warnings, action
should be taken for painting the tower with international orange and white colours in
alternate bands. The night warning is by means of aviation lamps. The total number
of lights used depends upon the height of tower. It is always in odd numbers with top
position of tower fitted with single light, and in other levels in two numbers (one on
each diagonal legs). For 100 M tower, a maximum of 5 Nos. of aviation lights are
used (Please refer Table VII).
This will ensure a course orientation at the time of fixing the antenna itself. Any
further orientation at the time of fixing the antenna itself is done afterwards. Adequate
supports (stay rods) should be provided to the antenna after hoisting, to prevent
oscillation due to heavy wind force. The rear side of the feed horn should be sealed
temporarily till wave guide is terminated to avoid the entry of rain water or moisture.
After the physical mounting, the set is started on. After satisfying its
performance on no load, the load testing is done. An artificial load (variable), a
tachometer and a thermometer are required for this test. The over loading test, if any,
should done as per manufacturers instruction only.
The power plants are available in two categories depending upon the
capacity, namely (i) two–unit type, and (ii) 3–unit type. Power plants up to 200A
capacity are available in 2–units, comprising (a) float cum battery charger, and (b)
Auxiliary cubicle. Depending upon the type used, the layout is predetermined and the
physical installation is done. While doing so, it is essential to maintain their relative
physical positions since the interconnection cables/busbars are supplied by
manufacturers accordingly. Then the electrical connections on the input and output
sides are completed.
After the physical installation, it is essential to check the entire power plant for
any possible loose connection or disconnection during transport and handling. After
ensuring this, the input supply is switched on following the instructions given by
manufacturer on "installation and commissioning". The output voltages for various
modes of operations of the power plant are checked and if necessary adjusted. Its
regulation for variation in input voltages is tested using an auto transformer of
suitable capacity. The various alarm conditions are also tested.
Then the power plant is tested on load using artificial load. This can be made
of resistive coils or by means of water load. The power plant is tested for fractional
and full loads on the both equipment and charging terminals of the output, thus
ensuring its satisfactory performance for simultaneous loading of equipment and
battery charging. The alarm pertaining to loaded condition are also tested.
Only when the engine alternator set and power plant set gives satisfactory
performance of load conditions for continuous duration of 10 hrs or more, then the
charging of battery sets should be undertaken.
(b) The power plant should have been tested for full load and its
satisfactory performance ensured. All the HRC fuses used in power
plant should have been provided with spare. The spare control cards
of the power plant should be in good condition and is available readily.
(c) The engine alternator should have been tested for full load and its
satisfactory performance should be confirmed. Adequate stock of
correct quality of fuel oil for the set to run it for the entire period of
charging is to be provided. This is necessary to ensure, that there will
not be any interference of charging even if there be a total failure of
commercial mains.
The prepared acid should be cool enough before filling into the cells. The
cells should not be filled too early before the commencement of the charge. It is
preferable to fill up during day time and start the first charge during the immediate
night following so that the cells will not become excessively hot. It may be necessary
to use air circulators to keep the temperature of the acid while charging within the
limits specified by the manufacturer. The vent holes on the cap of the cells should be
clean and free from dust to let off the acid fumes freely without building pressure
inside the cell.
During charging the specific gravity of the acid, temperature and cell voltage
should be noted every hour. Normally after forty hours of charging, a little rest is
given before continuing the charging. But this depends on the manufacturers
instructions on first charging and this should be followed strictly. If there be a power
failure from commercial mains, immediately the engine generator set should be
started and charging should be maintained as per manufacturer's instructions. After
the first charge is completed, then a specified rest is given before the discharge
through artificial load is commenced. The discharge rate is limited to 10 hrs. and
during discharge also, the specific gravity and cell voltage are noted hourly.
Discharge should be stopped where the specified specific gravity or cell voltage is
reached.
This should be followed by recharging again and discharge. This cycle can be
repeated twice or more, till such time the specified capacity of battery is attained on
discharge. The battery should never be left in discharged condition for long. After the
final charge, the battery is ready for use and could be floated with the power plant
and load.
3. Pulleys.
4. Jute ropes to tie the waveguide with hoisting rope.
5. Flanging tool supplied by the waveguide with manufacturer.
6. Accessories like hacksaw knife, insulating tapes, scale, etc.
7. Petrol for cleaning during flanging.
(2) The details of building and tower foundations like foundation drawing,
the layout drawings, etc. with details whether building has provision for
further vertical expansion or not.
(3) The earthing details of various earths like tower earth, equipment
earth, AC earth, etc. This should be accompanied by drawings
showing the location, type and layout of different earths. The ring
earth position also should be indicated.
(5) Electrical layout drawings. The electrical circuit, drawings and drawing
showing the conduit positions if it is concealed wiring.
(6) Details of drawing showing the L.T. panel wiring including the loading
in arrangement of AC mains.
(11) Guarantee details for power plant, battery, engine set and for any part
of equipment like TWT and etc.
(12) Any other detail which is important from maintenance view point.
The above paragraphs does not mention about the staff quarters for Mtce
staff. It is worth mentioning here that the Project Organisation takes the responsibility
of providing the staff quarters to Mtce Staff, the details of land for staff quarters, the
staff quarters including its electrical and other inventories are also made over to
Mtce.
assumed that the Project work for a particular MW scheme is completed in all
respects.
Table