Professional Documents
Culture Documents
MS Project 2013 - Lesson 2 PDF
MS Project 2013 - Lesson 2 PDF
MS Project 2013 - Lesson 2 PDF
Lesson 02
Creating a Project Plan
The Project Manager needs to define basic project details at the commencement of a new project.
Project Calendar
A new project can be initiated in Microsoft® Project 2013 by creating a blank project and then adding project details
into it.
Ribbon
View
Gantt Chart
Zoom
Status Bar
Microsoft® Project 2013 has many pre-installed templates that can be used to create a new project.
Residential
Construction
If the project information is in Microsoft® Excel Workbook format, it can be imported into Microsoft® Project, without
losing the data or format.
If the development team is using SharePoint for a project, the Project Manager can synchronize the task list from
SharePoint without using the Project Web App.
• This will allow the team members to view the project schedule on SharePoint.
• Any updates on SharePoint will be reflected in the Microsoft® Project plan.
When planning a schedule, knowledge about working days and hours, down time, vacations, holidays, etc., are critical for a
project manager.
• These details allow the project manager to plan the project resourcefully.
• Hence, the project manager can set up a base calendar to plan his project in a better way.
Resource Allocation This helps in assigning the right resources for the project.
Resource Availability This helps in identifying the working time to determine when the resources are available to work in the project.
When the project team is spread across geographies, with each region having its own set of working and non-working
days, the Project Manager can create a new calendar for each geographical region.
1
Click Change Working
Time. Create New Base 3
Calendar window is
displayed.
2
Click Create New
Calendar…
The ‘Set Baseline’ command can be used to compare the status of the project with the original plan.
• Baseline records the project plan and the resource allocation.
• Microsoft® Project 2013 permits eleven benchmarks.
Microsoft® Project 2013 allows you to save the completed project plans as project templates.
• Strategies from past projects can be shared and can be applied to future projects.
3
1
a. Project Schedule
b. Base Calendar
c. Pre-Installed Templates
d. Project Information
a. Project Schedule
b. Base Calendar
c. Pre-Installed Templates
d. Project Information
Explanation: ‘Project Information’ option in Microsoft® Project 2013 provides the overall information of the
project to the user.
Which of the following provides option to create benchmarks to compare project performance?
Select the answer.
a. Gantt Charts
b. Project Schedule
c. Set Baseline
d. Standard Calendar
Which of the following provides option to create benchmarks to compare project performance?
Select the answer.
a. Gantt Charts
b. Project Schedule
c. Set Baseline
d. Standard Calendar
Explanation: ‘Set Baseline’ command is used to create a base point, which acts as a benchmark to compare
the project performance.
Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.
a. Base Calendar
b. Standard Calendar
c. Night Shift Calendar
d. 24-Hour Calendar
Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.
a. Base Calendar
b. Standard Calendar
c. Night Shift Calendar
d. 24-Hour Calendar
Explanation: ‘Standard Calendar’ is the type of calendar which is used from 8.00 AM to 5.00 PM.
a. 5
b. 7
c. 11
d. 15
a. 5
b. 7
c. 11
d. 15
Answer: c. 11
Which of the following can be used to synchronize the task list, without using the Project Web App?
Select the answer.
a. Existing Projects
b. Microsoft® SharePoint
c. Existing Templates
d. Microsoft® Excel Workbooks
Which of the following can be used to synchronize the task list, without using the Project Web App?
Select the answer.
a. Existing Projects
b. Microsoft® SharePoint
c. Existing Templates
d. Microsoft® Excel Workbooks
Explanation: You can synchronize the task list from the SharePoint without using the Project Web App.