Professional Documents
Culture Documents
Railway Construction PDF
Railway Construction PDF
Railway Construction PDF
FACULTY OF ENGINEERING
CIVIL ENGINEERING DEPARTMENT
RAILWAY CONSTRUCTION
-1-
1- Railway Construction - Introduction:
The positive system has long been in successful operation at all large
and important junctions. In such a situation the use of a stringent code is
manifestly conducive to the greatest degree of safety, as by the unavoidable
intersections of the lines of rails there are many chances of collision. The
positive system has been merged in what is known as the block system of
signaling,—that is to say, the positive system
has been on most railways extended to every
station on the lines in combination with
telegraphic signalling. The best, perhaps the
only, safeguard against error on the part of the
persons in charge of trains is to be found in the
adoption of the absolute block system, and of
means for enabling engine-drivers to observe
signals well in advance. Distant signals are
occasionally fixed at 1500 yards’ distance; but
beyond 800 yards their action is uncertain, and
it is checked by repeater—electric or
mechanical—by which, by way of confirmation,
the signal is returned to the signalman.
-4-
The standard project period as proposed here allows one to obtain a general
picture of a specific route’s overall project period, but as the construction
conditions for each route have not been determined, it may not be viewed as an
executable construction process.
The standard project period for each route is categorized into project preparation,
construction and completion periods. Standard periods for each type of work were
determined based on comparisons of theoretical estimations and the actual
construction periods of other similar projects.
A. Project Preparation Process: The general process for preparing for the
railway construction project goes as follows: after the basic plans are
established, base and actual designs are conducted, followed by the acquisition
of various approvals and certifications and discussions with related agencies
and organizations. Then, the land for facility construction sites is acquired, and
construction begins. The minimum time length for each stage is as shown
below:
-5-
Establishing Railway Construction Project Periods for Each Line:
To estimate the construction period for the railway, the team set the
preparation period as 2 years as shown above, and applied the time-limit
determining zones in each line as the standard for estimating the roadbed
construction period. Systems (electric, signal, communication), stations, and
tracks will be built when the roadbed work is about 50% complete. Also,
considering the possibility of building new railways, the construction period for
each line includes a test driving period of about six months
-6-
3- Step By Step Railway Construction Plan:
Among the lines planned for the national railway network plan, the short-
term routes of S-1 and S-3 which are connected to the existing narrow gauge
tracks, could be applied in the types of standard gauge and narrow gauge, and
the means of railway operation will be changed based on the gauge type.
-8-
For embankments aconventional fill materials are liable to excessive settlement
on railway embankments. The high strength-to-weight ratio of Fillmaster provides
a cost-effective solution to withstand the mechanical loads encountered in railway
construction.
Plat form characteristics: The most basic form of platform consists of an area at
the same level as the track, usually resulting in a fairly large height difference
between the 'platform' and the train floor. This would
often not be considered a true platform. The more
traditional platform is situated at an elevated level
relative to the track, but often lower than the train floor,
although ideally the platform should be at the same level
as the train floor. Occasionally the platform is at a higher
level than the train floor. This may be the case when a
train with a low floor level serves a station built for trains
with a higher floor level, for example at the Dutchstations
of the DB Regionalbahn Westfalen (see Enschede).
Likewise, on the London Underground some stations are
served by both District Line and Piccadilly Line trains,
and the Piccadilly trains have lower floors.
-9-
A tram stop is often in the middle of the street; usually it has as a platform a
refuge area of a similar height to that of the sidewalk (e.g. 10 cm), and sometimes
has no platform at all. The latter requires extra care for the boarding and
unboarding passengers and for the other traffic to avoid accidents.
Plat form facilities: Part of the station facilities are usually on the platforms.
Where the platforms are not situated within a station building, often some form of
shelter or waiting room is provided. The protection offered by such varies greatly –
some being little more than a roof with open sides, others being a closed room
with heating or air-conditioning.
Also there may be benches, lighting,garbage boxes and static timetables or
dynamic displays with information about the next train. There are
often loudspeakers as part of a public addresssystem. The PA system is often
found where dynamic timetables or electronic displays are not present. A variety
of information is presented, usually pertaining to departures, but often arrivals
also. This concerns destinations and, delays, cancellations, platform changes,
changes in routes and destinations, and supplemental fee or reservation
requirements.
Markings: Platforms usually have some form of warnings or measures to keep
passengers away from the tracks and moving trains. The simplest measure is
markings near the edge of the platform to demarcate the distance back from the
platform edge that passengers should remain. Often a special tiled surface is used
as well as a painted line, to help blind people using a walking aid, and aid in
preventing wheelchairs from accidentally rolling too near the platform edge.
- 11 -
Resources:
1- http://www.rff.fr/en/the-network/europe-on-rails/building-a-
europe-on-rails// railway construction steps.
2- http://en.wikipedia.org/wiki/Railway_signal.
3- http://en.wikipedia.org/wiki/Railway_platform.
4- http://www.valleymetro.org/images/uploads/lightrail_publicati
ons/Design_Criteria_Manual_FINAL_030207.pdf.
- 12 -