This document provides an estimate for waterproofing works at Station 1A2 in Riyadh, Saudi Arabia from January 1-30, 2018. It details the waterproofing materials needed, including horizontal and vertical applications of Proofex Engage membrane on base slabs and perimeter walls totaling over 1,700 square meters. It also includes over 300 square meters of double layer membrane and HDPE membrane for top slabs. Quantities to date and previous works are summarized. The estimate was prepared by Fel C. Gabinete and approved by Adeel Bashir.
This document provides an estimate for waterproofing works at Station 1A2 in Riyadh, Saudi Arabia from January 1-30, 2018. It details the waterproofing materials needed, including horizontal and vertical applications of Proofex Engage membrane on base slabs and perimeter walls totaling over 1,700 square meters. It also includes over 300 square meters of double layer membrane and HDPE membrane for top slabs. Quantities to date and previous works are summarized. The estimate was prepared by Fel C. Gabinete and approved by Adeel Bashir.
This document provides an estimate for waterproofing works at Station 1A2 in Riyadh, Saudi Arabia from January 1-30, 2018. It details the waterproofing materials needed, including horizontal and vertical applications of Proofex Engage membrane on base slabs and perimeter walls totaling over 1,700 square meters. It also includes over 300 square meters of double layer membrane and HDPE membrane for top slabs. Quantities to date and previous works are summarized. The estimate was prepared by Fel C. Gabinete and approved by Adeel Bashir.
SUBJECT : ESTIMATE OF WATERPROOFING WORKS CONTRACTOR : CRETEC - SAUDI CONCRETE TECHNIQUE CO. LTD. PERIOD COVERED : JANUARY 01, 2018 - JANUARY 30, 2018 DATE: JANUARY 30, 2018
Item Length Width Height Qty.
Work Description Total Unit No. (m) (m) (m) (pcs.) HORIZONTAL - BASE SLAB(Proofex Engage) 1 AT 1+800 TO 1+770 10.31 10.65 1 109.80 sqm
2 AT 1+760 TO 1+717.26 42.43 10.11 1 428.92 sqm
3 DROP AT SLAB -NEAR AT STA. 1+760 10.65 1.75 1 18.58 sqm
5 DROP AT SLAB -NEAR AT STA. 1+770 10.65 1.30 1 13.85 sqm
5.88 1.67 2 19.64 sqm
5 SUMP PIT 01 3.62 1.67 2 12.09 sqm
Sub-total 602.88 sqm
CUMULATIVE TOTAL AREA 602.88 sqm
PERIMETER WALL AREA - PROOFEX ENGAGE + GEOTEXTILE
WALL ALONG AXIS B&A - EAST SIDE
1 ZONE 7 9.15 6.100 1 55.80 sqm
2 ZONE 8 9.55 6.100 1 58.22 sqm 3 ZONE 9 6.66 8.100 1 53.95 sqm 4 ZONE 10 4.02 6.100 1 24.53 sqm 5 AT 1+800 TO 1+770 28.84 1.300 1 37.49 sqm 11.98 5.050 1 60.47 sqm 6 AT 1+770 TO 1+760 0.70 1.100 1 0.77 sqm 7 AT 1+760 TO 1+717.26 42.43 4.500 1 190.91 sqm
Sub-total 482.15 sqm
WALL ALONG AXIS H&J - WEST SIDE
1 ZONE 9 6.66 6.100 1 40.63 sqm 2 ZONE 10 11.30 6.100 1 68.93 sqm 3 AT 1+800 TO 1+770 28.84 1.300 1 37.49 sqm 11.98 5.050 1 60.47 sqm 4 AT 1+770 TO 1+760 0.70 1.100 1 0.77 sqm 5 AT 1+760 TO 1+717.26 42.43 4.500 1 190.91 sqm
Sub-total 399.20 sqm
WALL ALONG NORTH SIDE
17.90 7.25 1 129.74 sqm 1 North Wall at Axis 05 15.72 7.25 1 113.93 sqm 2 North Wall at Axis CC 10.11 1.00 1 10.11 sqm
Sub-total 253.78 sqm
CUMULATIVE TOTAL AREA 1135.14 sqm
HORIZONTAL - TOP SLAB (2 LAYER MEMBRANE + HDPE MEMBRANE)
5.81 2.88 1 16.74 sqm
5.81 1.91 1 11.09 sqm 1 1+800 to Near at 1+780 16.00 10.85 1 173.60 sqm 12.00 10.65 1 127.74 sqm 2 Upstand at Wall 10.25 1.10 1 11.28 sqm 6.06 1.40 1 8.48 sqm 3 Upstand at Opening Wall 5.80 1.40 2 16.24 sqm 4 Drop at Top Slab 10.85 0.30 1 3.26 sqm
Sub-total 368.42 sqm
CUMULATIVE TOTAL AREA 368.42 sqm
STATION 1A2 QUANTITY SUMMARY
Previous Present To Date Unit Proofex Engage Horizontal 5981.58 602.88 6584.46 sqm Proofex Engage Vertical 7778.45 1135.14 8913.58 sqm Total Proofex Engage 13760.03 1738.01 15498.04 sqm Total Geotextile 7778.45 1135.14 8913.58 sqm Total Drain Sheet 18.52 18.52 sqm Double Layer Membrane 368.42 368.42 sqm HDPE 368.42 368.42 sqm