ZXSDR BBU B8200 Offline Operation Test Procedure

ZXSDR BBU B8200 Offline Operation Test Procedure

and are registered trademarks of ZTE CORPORATION. ZTE’s company name, logo
and product names referenced herein are either trademarks or registered trademarks of ZTE
CORPORATION. Other product and company names mentioned herein may be trademarks or trade
names of their respective owners. Without the prior written consent of ZTE CORPORATION or the
third party owner thereof, anyone’s access to this document should not be construed as granting, by
implication, estopped or otherwise, any license or right to use any marks appearing in the document.

The design of this product complies with requirements of environmental protection and personal
security. This product shall be stored, used or discarded in accordance with product manual, relevant
contract or laws and regulations in relevant country (countries).

This document is provided “as is” and “as available”. Information contained in this document is
subject to continuous update without further notice due to improvement and update of ZTE
CORPORATION’s products and technologies.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 2


ZXSDR BBU B8200 Offline Operation Test Procedure

TABLE OF CONTENTS

TS01 Applying Power to ZTE BBU Delta Cabinet ........................................................... 4

TS01-1 Applying Power to ZTE BBU Delta Cabinet Connection ................................... 4

TS02 Testing of the BBU using ZTE Software ................................................................ 8

TS02-1 Testing of the BBU using ZTE Software............................................................. 8

TS03 Testing of the IPTRAN using ZTE Software ........................................................ 13

TS03-1 Testing of the IPTRAN ZXCTN 9000 using ZTE Software................................ 13

TS03-2 Testing of the IPTRAN ZXCTN 6120S using ZTE Software ............................. 18

TS04 Testing of the RRU using ZTE Software .............................................................. 24

TS04-1 Testing of the RRU using ZTE Software........................................................... 24

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 3


ZXSDR BBU B8200 Offline Operation Test Procedure

TS01 Applying Power to ZTE BBU Delta


Cabinet

TS01-1 Applying Power to ZTE BBU Delta Cabinet


Connection

Short Description To power on the ZTE BBU Delta Cabinet


Prerequisites It is assumed that the following BBU components has been
success successfully mounted and connected into the Delta
Cabinet:

TYPE1 BBU ZXSDR B8200 WITH ZXCTN 9000


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

TYPE2 BBU ZXSDR B8200 WITH ZXCTN 6120S


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 6120S Including INSTALLED CARD
Delta Cabinet Power Rectifier

BS software version has been saved in local hard disk.

MPO Cassette (Patch Panel) including INSTALLED CARDS


BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 4


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 1: Connect the 220V AC wires of power cable to the sockets provided on the right side of the ZTE
Cabinet. (See Pictures Below)

Step 2: After connecting the wires, switch on the circuit breaker also located at the right side of the
cabinet to start the operation.

Step 3: After switching on the circuit breaker of the power supply, power control indicator (see
highlighted the picture below) will start to initialize, wait until display comes up indicating that the parts
are ready to work.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 5


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 4: Switch on the Circuit Breaker Number 1 to power on the Cabinet Centralized Fan.

Step 5: Switch on the Circuit breaker number 3 to power on the BBU Module with cards. Wait for 10 to
15 minutes to make BBU fully initialized and accessible.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 6


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 6: Switch on the Circuit breaker Number 9 and 10 to power on the IPRAN. Also wait for 10-15
minutes to make the IPRAN fully initialized and accessible.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 7


ZXSDR BBU B8200 Offline Operation Test Procedure

TS02 Testing of the BBU using ZTE Software

TS02-1 Testing of the BBU using ZTE Software

Short Description To check the BBU functionality and output.


Prerequisites It is assumed that the following BBU components has been
success successfully mounted and connected into the Delta
Cabinet:

TYPE1 BBU ZXSDR B8200 WITH ZXCTN 9000


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

TYPE2 BBU ZXSDR B8200 WITH ZXCTN 6120S


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 6120S Including INSTALLED CARD
Delta Cabinet Power Rectifier

BS software version has been saved in local hard disk.

MPO Cassette (Patch Panel) including INSTALLED CARDS


BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 8


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 1: To check the BBU's functionality and output, connect the UTP Cable to BBU's
Debug/CAS/LMT UTP socket going to laptop.

Step 2: After connecting, go to the program open NetSetMan and set it to BBU. See image below.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 9


ZXSDR BBU B8200 Offline Operation Test Procedure

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 10


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 3: After setting up the program, open EOMS.jar program. Once EOMS program opens, click the
OK Button. (No username and password are required)

Step 4: After clicking the Ok button, EOMS program will start to connect on the BBU's system and a
window will be opened showing the details you need about the BBU, cards and controls.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 11


ZXSDR BBU B8200 Offline Operation Test Procedure

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 12


ZXSDR BBU B8200 Offline Operation Test Procedure

TS03 Testing of the IPTRAN using ZTE


Software

TS03-1 Testing of the IPTRAN ZXCTN 9000 using ZTE


Software

Short Description To check the IPTRAN functionality and output.


Prerequisites It is assumed that the following BBU components has been
success successfully mounted and connected into the Delta
Cabinet:

TYPE1 BBU ZXSDR B8200 WITH ZXCTN 9000


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

BS software version has been saved in local hard disk.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 13


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 1: To check the IPRAN functionality and output, connect first the RJ45 serial cable to 9000-2ER
IPRAN. Look for the module P90E-MCT-2D then connect to Console Socket.

Step 2: Change IP Address to 192.168.0.20 255.255.0.0, then TELNET 192.168.0.1. See figures
below

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 14


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 3: Go to the program open NetSetMan and set it to 9002E.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 15


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 4: After setting up the program, go to your computer device manager, check the list of ports.

Step 5: Open the PuTTY program, set to serial then the type of port available.

Username : who

Password: who

or

Username: ipran

Password : B3lLt3L

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 16


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 5: After clicking the Ok button, the program will start to connect on the IPRAN's system and a
window will be open showing the details you need about the IPRAN Module, cards and controls.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 17


ZXSDR BBU B8200 Offline Operation Test Procedure

TS03-2 Testing of the IPTRAN ZXCTN 6120S using ZTE


Software

Short Description To check the IPTRAN functionality and output.


Prerequisites It is assumed that the following BBU components has been
success successfully mounted and connected into the Delta
Cabinet:

TYPE2 BBU ZXSDR B8200 WITH ZXCTN 6120S


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 6120S Including INSTALLED CARD
Delta Cabinet Power Rectifier

BS software version has been saved in local hard disk.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 18


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 1: To check the IPRAN functionality and output, connect first the UTP Cable to SMDE Card LCT
socket.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 19


ZXSDR BBU B8200 Offline Operation Test Procedure

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 20


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 2: Change IP Address to 192.192.192.20 255.255.0.0, then TELNET 192.192.1.1

Step 3: Go to the program open NetSetMan and set it to 6120S.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 21


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 4: After setting up the program, go to your computer device manager, check the list of ports.

Step 4: Open the PuTTY program, select Telnet then type 192.192.192.11 then click open.

Username : who

Password: who

or

Username: ipran

Password : B3lLt3L

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 22


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 5: After clicking the Open button, the program will start to connect on the IPRAN's system, click
enter and a window will open showing the details you need about the IPRAN Module, cards and
controls.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 23


ZXSDR BBU B8200 Offline Operation Test Procedure

TS04 Testing of the RRU using ZTE Software

TS04-1 Testing of the RRU using ZTE Software

Short Description To check the RRU functionality and output.


Prerequisites It is assumed that the following BBU components has been
success successfully mounted and connected into the Delta
Cabinet:

TYPE1 BBU ZXSDR B8200 WITH ZXCTN 9000


MPO Cassette (Patch Panel)
MPO Cassette (Patch Panel) including INSTALLED CARDS
BBU ZXSDR B8200 including INSTALLED CARDS
IPTN / IP RAN
ZXCTN 9000-2E4 Including INSTALLED CARD
Delta Cabinet Power Rectifier

BS software version has been saved in local hard disk.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 24


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 1: For RRU Testing, get a power cable with 12 wires (6 wires with color coding then 6 wires
(black for ground). See image below.

Note: colored wires are not strictly in series.

Step 2: Connect one end of the power cable (colored) to 6 different circuit breakers of ZTE Cabinet
located as shown below then the other 6 blacks wires are for grounding to be attached on the metal
part above the breakers.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 25


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 3: After connecting the 12 wires on the circuit breakers and ground, open the control box of the
RRU modules and connect the other 12 end wires (6 blacks for ground in any order then 6 color
coding wires in proper order), please note the color black section is for ground and the color blue
section is for the wires with color code.

Step 4: When connecting the power wires on the RRU Control box, there is no color coding but we
recommend following the colors as indicated in the Control Box Cover. Please refer to the Manual
available on the Control box top cover.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 26


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 5: After connecting the power cables from Cabinet to RRU, get the Fiber Optics Cable (FO). On
one end having red and blue, connect the FO (red and blue) on the patch panel (a small like box
located at the top part of the BBU), blue for the left then red for the right. See the Image below.

Step 6: Connect the other ends of the FO Cable (7 color coded end of FO wires) and connect to the
RRU Control Box. Follow the color coding on the below image.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 27


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 6: After connecting the power wires and the FO cables, Power on the RRU on the BBU cabinet
and start accessing the RRU's information, function and controls by connecting the UTP Cable on the
RRU modules one by one going to the BBU's, normally it takes 20-30 minutes for each RRU modules
to fully initialized and accessible. See the figure below:

Step 7: Using EOMS program, access Manage NE-> Device->Device Group.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 28


ZXSDR BBU B8200 Offline Operation Test Procedure

Step 8: If the RRU Modules are still not ready or not completely initialize, the system will be on a
Normal Operational with Faulty running status, just wait until the modules are ready, refresh the
program, then all running status will be in normal and the red illustration will be Green after complete
initialization.

ZTE Confidential Proprietary © 2019 ZTE Corporation. All rights reserved. 29


ZXSDR BBU B8200 Offline Operation Test Procedure

Normally, it will just take another couple of minutes more and the modules will change its status to
Ready. Refresh the program so that all running status will be in normal and the red illustration will be
Green after complete initialization. See Figure below: