560-S28 - CORROSION PROTECTION AND REPAIR WORKS PRELIMINARY SCHEDULE 04-Oct-12 10:29

12500.00d 187500.00d

10000.00d 150000.00d

7500.00d 112500.00d

5000.00d 75000.00d

2500.00d 37500.00d

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Month
Labor Units Page 1 of 1 TASK filter: All Activities