500kV TRANSMISSION LINES INTERCONNECTION ARRANGEMENT FOR POWER EVACUATION FROM SUKI KINARI, KOHALA AND MAHL HYDROPOWER 

PROJECTS IN NORTHERN AREAS OF PAKISTAN
ASSIGNMENT – A: ENGINEERING DESIGN AND TENDERING
Suki Kinari to Maira 500kV DC T/L (approx. 170km)
WBS ID Task Name Baseline Dur. Start Finish 2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov D
A1 Line Segment (Suki Kinari ‐ Maira) 272 days Mon 10/29/18 Tue 9/10/19
A1.1 Commencement of Services 0 days Mon 10/29/18 Mon 10/29/18 Oct 29 '18
A1.1.1 Commencement of Services 0 days Mon 10/29/18 Mon 10/29/18 Oct 29 '18
A1.2 Review of existing information and data  26 days Thu 11/1/18 Fri 11/30/18
A1.2.1 Review of existing information and data  26 days Thu 11/1/18 Fri 11/30/18 Nov 1 '18 Nov 30 '18
A1.3 Transmission Line route alignment and detailed survey 116 days Thu 11/1/18 Fri 3/15/19

A1.3.1 Transmission Line route alignment and detailed survey 116 days Thu 11/1/18 Fri 3/15/19 Nov 1 '18 Mar 15 '19

A1.4 Geotechnical, geohazard and soil resistivity investigations 49 days Fri 2/1/19 Fri 3/29/19

A1.4.1 Geotechnical, geohazard and soil resistivity investigations 49 days Fri 2/1/19 Fri 3/29/19 Feb 1 '19 Mar 29 '19

A1.5 Transmission Line Plan and Profile and Structure List 63 days Fri 2/1/19 Mon 4/15/19

A1.5.1 Transmission Line Plan and Profile and Structure List 63 days Fri 2/1/19 Mon 4/15/19 Feb 1 '19 Apr 15 '19

A1.6 Conductor and Span Utilization 50 days Thu 11/1/18 Fri 12/28/18


A1.6.1 Conductor and Span Utilization 50 days Thu 11/1/18 Fri 12/28/18 Nov 1 '18 Dec 28 '18
A1.7 Preparation of Engineering Design 145 days Mon 10/29/18 Mon 4/15/19
A1.7.1 Collection of Data and Investigations 132 days Mon 10/29/18 Sat 3/30/19 Oct 29 '18 Mar 30 '19
A1.7.2 Insulation Coordination Study 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.3 Design of Hardware and Damping System 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.4 Design of Tower Family and Foundations 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.5 Preparation of Project Specifications 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.6 Preparation of BoQ and Costing 29 days Wed 3/13/19 Mon 4/15/19 Mar 13 '19 Apr 15 '19
A1.8 Preparation of Tender Documents 90 days Tue 1/1/19 Mon 4/15/19
A1.8.1 Preparation of Tender Documents 90 days Tue 1/1/19 Mon 4/15/19 Jan 1 '19 Apr 15 '19
A1.9 Tendering (Bidding Period) 60 days Tue 4/16/19 Fri 6/14/19
A1.9.1 Tendering (Bidding Period) 60 days Tue 4/16/19 Fri 6/14/19 Apr 16 '19 Jun 14 '19
A1.0 Evaluation and Award of Contract(s) 75 days Sat 6/15/19 Tue 9/10/19
A1.0.1 Evaluation and Award of Contract(s) 75 days Sat 6/15/19 Tue 9/10/19 Jun 15 '19 Sep 10 '19

Page 1 of 1 
NESPAK Revision No.: 00
National Engineering Services of Pakistan Dated: Wed 1/9/19