Gravity Sewers Spreadsheet: Unknown Sewer Project ETC 2/21/12
Gravity Sewers Spreadsheet: Unknown Sewer Project ETC 2/21/12
Project Name: Unknown Sewer Project Review Engineer: ETC Date: 2/21/12
Manhole Stations Δ Length of Pipe Check for Length Slope Invert Check for Slope*
Main or Line Slope (%)
From To (ft) ≤ 400 ft Elevation Out (ft) Elevation In (ft) Δ Elevation (ft) Slope (ft/ft) ≤ 0.004
Main A Ex MH A1 107.31 OK 457.77 450.15 7.62 0.0710 OK 7.10
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
OK OK
Gravity Sewers Spreadsheet
Project Name: Unknown Sewer Project Review Engineer: ETC Date: 2/21/12
Design average BOD5: 170.00 lbs BOD5/day = Predicted Population x 0.17 lbs BOD 5/day/capita
10 CSR 20-8.110(4)(C )5.C.(I)
Design average SS: 200.00 lbs SS/day = Predicted Population x 0.20 lbs SS/day/capita
10 CSR 20-8.110(4)(C )5.C.(I)