Professional Documents
Culture Documents
Gas Turbine Inspection Report PDF
Gas Turbine Inspection Report PDF
JOB NO #: JSS08/0294
TABLE OF CONTENETS
PAGE
JOB SUMMARY 5
INSPECTION SUMMARY 6
INLET SYSTEM 13
BEARINGS 14
COMBUSTION SECTION 26
COUPLINGS 33
COMPRESSOR SECTION 35
DEVICE SUMMARY 46
EXHAUST SYSTEM 47
TURBINE SECTION 49
JOB SUMMARY
Station: KAYAMKULAM
Unit No: 1
JOB SUMMARY
Name Responsibility
Name Responsibility
Mr.S.J.David Sr.Superintendent
Mr.Rajith Superintendent
Contractors:
Company Responsibility
JOB SUMMARY
This is a report on the first Major inspection of Gas Turbine and the Accessory Gear Box carried
out on Frame 9 E Gas Turbine unit # 1 (S/N GT# 297036) installed at National Thermal Power
Corporation, Kayamkulam. This unit had been commissioned by BHEL, Hyderabad in February
1999. This unit is being operated on HSD/Naphtha fuel and has accumulated the machine has
clocked 50510 fired hours at the time of Major Inspection. Prior to this inspection, Combustion
and Boroscope Inspection has been carried out on this unit in august 2007 and again Boroscope
inspection carried out prior to this inspection September 2008
The purpose of Major inspection is to examine all of the internal rotating and stationary
components from the inlet of the machine through the exhaust section of the machine. The work
scope involves inspection of all of the major flange-to-flange components of the gas turbine ,
which are subject to deterioration during normal turbine operation and also compressor rotor
The Major Inspection is a planned outage scheduled and commenced on 25th November 2008
and completed on 26th after completion of generator works the machine was put in barring gear
on 28th November 2008. The machine has achieved 116 MW at Base load on simple cycle and
combined cycle it was 110MW with WI and inlet temperature 30 deg C, all the parameters were
found normal.
BGGTS provided Technical Advisory Services along with the required skilled manpower with
tools and tackles to execute the job.
BGGTS shares the credit along with NTPC team for successful completion of the Major
Inspection.
INSPECTION SUMMARY
Bearing, Thrust
Combustion Cans
Combustion Liner
INSPECTION SUMMARY
Fuel Nozzle
Coupling, Load
Rotor, Compressor
Assembly 50510 Cleaned and Inspected Noticed with trail mark of compressor
blades.
Vane - IGV 50150 Removed & Inspected 3 no’s IGV replaced with new ones
Gear - Rack 50510 Removed & Inspected DP tested & found with no cracks.
Valves, Check
Liquid Fuel Check valve Flow Check Replaced with new ones
Water Injection Check Removed & Inspected found ok
Valve
Plenum, Exhaust
Assembly 50510 General Bucket Inspection replaced with new bucket kit
Casing, Turbine
Diffuser, Exhaust
Assembly 50510 Cleaned and Inspected replaced with new nozzle segments
Rotor, Turbine
Assembly 18530.8 Cleaned and Inspected replaced with refurbished set supplied
by others
INSPECTION SUMMARY
INLET SYSTEM
BEARINGS
Bearing, Thrust
Assembly
Both active and non active thrust bearings were cleaned and inspected observed with slight
scoring marks which were polished. Thrust pads were DP tested, checked and ultrasonic test was
carried out , found in good condition ,hence retained in service.
Bearings
COMBUSTION SECTION
Fuel Nozzle
Assembly
All fuel nozzles were removed from position and inspected found with carbon deposits, wear and
cracks were observed on 3 nozzles (3,7,&13). All fuel nozzles were replaced with refurbished
/calibrated set available with customer. The removed nozzles need to be sent to GE approved
workshop for repair / calibration and can be kept in stock.
Combustion Liner
Crossfire Tube
All male and female crossfire tubes were cleaned and DP checked. No cracks were revealed on
weld joints. However, wear & burnt marks were observed on male and female cross fire tubes.
As damages were not in acceptable limits, All the crossfire tubes were replaced with refurbished
set.
Combustion Liner
Retainer - Crossfire Tube
All the retainers were visually inspected, They were found worn & bent. For the better
operational reliability all the retainers were replaced with refurbished[Non-GE]
Combustion Section
COUPLINGS
Coupling, Load
Assembly
This component was disassembled and cleaned, and routine inspection was performed. No
problems were found. All coupling bolts were returned back to service & stretched to required
enlongation.
Couplings
COMPRESSOR SECTION
Rotor, Compressor
Assembly
Rotor;
Compressor rotor has sustained damages on R2 stage,for 4 blades trailing edge metal missing
was observed.
Stages 1 thru’ 17th stage have sustained minor tip rubs .
This existing rotor which was installed during HGPI in 2001 was replaced with original rotor
repaired at GE shop .To suit the change in technology of the compressor rotor, the inner barrel
was also changed with honey comb seals.
Following blades were repaired at GE shop.
Stage # 1: 12,13,14,15,19,23,
Stage # 3: 3,7,17
Stage # 4: 4,6,7,12,13,15,39
Stage # 5:
Stator:
The intial stages 1to 8th stage blade dovetail cracks and nicks and dents were observed , which
was replaced as a set, the remaining stages blades were observed with nicks, dents and tip rubs
in almost all the stages which were cleaned. The following stator blades were replaced during
assembly which have dents above the acceptable limits
Stage 9 : Nil
Stage 10 : Nil
Stage 11 : Nil
Stage 12 : 04 blades
Stage 13 : 18 blades
Stage 14 : 08 blades
Stage 15 : 12 blades
Stage 16 : 06 blades
Stage 17 : 06 blades
EGV 1 : 08 blades
JSS08/0294 National Thermal Power Corporation. Kayamkulam Page 35 of 58
Inspection Report
EGV 2 : 01 blade.
Casing, Compressor Discharge
Assembly
The unit was cleaned and visually inspected. Found casing out of roundness which was rectified
by jacking the casing and redowelling the body bound bolts. Heavy rubbing was observed, all the
high spots that could interface with the flow were smoothly polished to match the profile.
Compressor Section
Repaired rotor.
EXHAUST SYSTEM
Plenum, Exhaust
Assembly
This component was visually inspected. Damages were repaired by the customer , windows were
cut for the inspection of the insulation on the bottom plenum, which were found in good
condition..
Exhaust System
TURBINE SECTION
on two pins on ond of the diaphragm and all the others are found to be good, rubs and burnt were
not observed. Hence these were replaced along with nozzles.
Nozzle Arrangement, Stage 3
Assembly
All third stage nozzle segments were removed, cleaned and DP test was carried out. No
significant damages like cracks, erosion, corrosion and trailing edge bowing were noticed.
However light deposits were noticed on inner and outer walls. Diaphragm seals were visually
inspected in- situ and found in good condition.these nozzle segments along with diaphragm were
replaced with refurbished set supplied by BGGTS.
Rotor, Turbine
Assembly
The existing compressor rotor having part number 143D7324G007 has been replaced with
refurbished compressor rotor with part number 105E9371G010 available with NTPC-
Kayamkulum The rotor was thoroughly cleaned, journals were polished there were no significant
damages found. Dye penetrate test was carried on all the bucket wheel dovetails no cracks were
observed assembled with new/refurbished bucket kits and new hardware.
Shroud, Stage 1 Turbine
Assembly
All 1st stage shrouds were visual inspected. Light rubbing, nicks and burnt were observed on
some of the shrouds. Damages such as cracks were not seen. , hence the shrouds were replaced
with refurbished set available with customer supplied by others. These shrouds have clocked
18530.8 fired hours on liquid fuel firing.
Shroud, Stage 2 Turbine
Assembly
All 2nd stage shrouds were visual inspected , no significant damages like rubbing, missing metal,
cracks or burnt were noticed. However light deposits and corrosion marks were observed on
shrouds. These shrouds has crossed its recomended life, hence the shrouds were replaced with
new set supplied by BHEL.
These shrouds have clocked 50510 fired hours on liquid fuel firing.
Turbine Section
TNH 100.55% 100.55 99.9 100.09 100.08 100.27 100.64 100.3 99.73 99.17 98.09 98.46 98.21 98.32
TNH_RPM 3017 rpm 3016 2997 3002 3002 3008 3019 3010 2991 2976 2944 2954 2947 2950
DWATT 0 MW 0 15 30.8 15 49.8 60 74.5 90 115.7 106.9 108.5 109.2 110.4
FSR 13.19% 13.31 18.96 25.34 19.56 34.16 41.48 48.39 55.92 68.34 67.43 68.75 69.71 67.96
FQR 13.26% 18.96 25.53 19.34 34.72 41.64 48.76 56.78 68.87 66.55 68.75 69.73 67.96
CPD 6.19 bar 6.21 6.59 7.05 6.65 8.45 9.65 10.03 10.37 10.89 10.45 10.53 10.55 10.55
LTTH 47 DEGC 48 48 48 48 48 49 49 49 49 54 54 55
LTB1D 57 DEGC 57 57 58 58 58 59 59 59 60 64 64 65
LTB2D 68 DEGC 68 68 69 69 70 73 73 74 74 78 79 79
LTB3D 58 DEGC 59 59 59 60 60 61 61 61 62 69 69 70
thrst Active 57 DEGC 58 59 60 59 60 61 62 64 67 71 71 71
Thrst Active 58 DEGC 58 60 62 61 62 63 65 67 71 75 75 75
Thrst INActive 57 DEGC 58 58 58 58 58 59 58 58 58 62 62 63
Thrst INActive 59 DEGC 59 59 59 59 59 60 60 60 60 64 64 65
Brg 1 Metal 100 DEGC 100 100 100 100 101 102 102 102 102 105 105 106
Brg 1 Metal 96 DEGC 97 97 96 96 95 96 97 96 97 99 99 99
Brg 2 Metal 91 DEGC 91 91 93 93 94 96 96 97 99 101 101 101
Brg 2 Metal 89 DEGC 89 89 90 90 91 93 93 94 95 98 98 98
Brg 3 Metal 90 DEGC 92 92 88 87 88 89 87 85 85 98 98 99
Brg 3 Metal 78 DEGC 79 80 80 79 81 84 86 85 81 88 89 89
BB1 2 mm/sec 1.6 1.2 0.7 0.7 0.8 0.8 0.7 0.6 1.1 0.7 0.8 0.7
BB2 2.4 mm/sec 1.8 1.4 0.9 0.9 1.1 1.2 1 0.9 1.4 1 1 1
BB3 7 mm/sec 5.5 5 4.2 4 3.6 3.9 4 4.6 5.5 5.2 4.9 5
BB4 2.3 mm/sec 2.2 2.2 1.7 1.8 1.9 1.7 1.5 1.6 1.6 1.7 1.9 1.6
BB5 1.8 mm/sec 2.2 2.2 1.7 1.8 1.8 2.1 1.9 1.7 2.2 1.2 1.2 1.5
BB7 10.3 mm/sec 9.7 9.5 9.2 9.3 8.8 8.6 8.4 8.4 8.5 9 8.8 8.8
BB8 4.9 mm/sec 4.9 4.8 4.5 4.6 3.9 3.8 3.6 3.7 3.7 4.3 4.3 4.2
BB9 2.7 mm/sec 2.7 2.2 2 2.1 1.7 1.8 1.9 2.9 3 11.3 10.1 10.3
BB_MAX 10.3 mm/sec 9.7 9.5 9.2 9.3 8.8 8.6 8.2 8.6 8.5 11.3 10.1 10.3
CSGV 57 DGA 57 57 57 57 69.9 85 85 85 85 85 85 85
CTIF1 25 DEGC 24 24 24 24 23 24 23 22 22 28 28 28 29
CTIF2 25 DEGC 25 25 24 24 24 24 23 23 22 28 29 29 29
CTDA1 278 DEGC 278 285 294 286 316 335 339 343 352 355 357 358 360
CTDA2 279 DEGC 279 286 295 288 318 338 343 348 356 360 361 361 363
TTXM 251 DEGC 251 300 359 311 371 374 418 472 553 559 559 558 558
TTXSP1 4.2 DEGC 4.7 6.5 5.3 3 6.5 13.5 24 24.3 24.7 26.4 27 27 29.4
TTXSP2 3.6 DEGC 3.8 6 5.3 3 5.6 9.3 13.8 20.4 24.4 24.3 25.4 25.7 25
TTXSP3 3.1 DEGC 38 4 4.3 2.8 5.5 8.7 11.7 19.6 23.5 24.3 24 22.5 22.2
TTRXB 610 DEGC 610 610 610 610 610 571 565 561 553 559 559 559 558
TTRX 593 DEGC 593 593 590 593 593 571 565 561 553 559 559 559 558
TT-XD-1 251 DEGC 252 300 358 308 370 371 416 468 552 557 555
TT-XD-2 249 DEGC 250 297 358 307 370 372 418 473 551 557 556
TT-XD-3 250 DEGC 252 299 358 307 371 373 415 467 544 552 554
TT-XD-4 251 DEGC 252 300 359 308 370 373 419 473 554 565 551
TT-XD-5 250 DEGC 251 300 359 308 370 374 423 478 556 565 563
TT-XD-6 249 DEGC 250 300 360 308 369 374 422 470 548 558 561
TT-XD-7 250 DEGC 251 302 362 309 370 375 422 481 564 568 555
TT-XD-8 250 DEGC 251 301 362 309 370 372 414 464 558 563 566
Fuel Naphtha Naphtha Naphtha Naphtha HSD Naphtha Naphtha Naphtha Naphtha Naphtha Naphtha Naphtha Naphtha Naphtha
Combined Combined Combined Combined
Parameter
FSNL FSNL 15 MW 30 MW 15 MW 50 MW 60 MW 75 MW 90 MW BASE BASE BASE BASE BASE BASE BASE
TT-XD-9 250 DEGC 251 300 363 308 373 379 426 484 563 570 564
TT-XD-10 248 DEGC 249 298 362 308 371 377 427 484 561 570 570
TT-XD-11 250 DEGC 250 300 362 307 371 378 422 478 557 559 569
TT-XD-12 252 DEGC 253 302 363 305 373 378 424 477 566 570 555
TT-XD-13 252 DEGC 253 302 364 303 374 379 427 482 563 571 566
TT-XD-14 250 DEGC 251 301 362 304 372 375 420 471 560 560 570
TT-XD-15 249 DEGC 250 301 362 306 371 374 425 468 544 548 559
TT-XD-16 251 DEGC 251 303 365 306 374 376 417 467 552 558 551
TT-XD-17 252 DEGC 253 304 365 306 374 376 421 475 549 554 559
TT-XD-18 252 DEGC 251 301 362 304 371 377 417 462 541 548 551
TT-XD-19 250 DEGC 252 301 360 305 368 373 405 459 556 562 547
TT-XD-20 252 DEGC 51 301 360 305 369 366 418 466 543 548 560
TT-XD-21 252 DEGC 253 301 360 305 369 372 417 468 560 563 547
TT-XD-22 251 DEGC 252 301 359 305 369 372 418 466 540 544 560
TT-XD-23 252 DEGC 253 301 360 305 371 372 418 470 551 557 543
TT-XD-24 252 DEGC 252 301 360 305 371 373 421 470 546 553 557
TTWS1FI1 311 DEGC 315 318 324 325 334 368 371 376 383 389 392
TTWS1FI2 310 DEGC 315 318 324 325 334 367 371 376 383 388 391
TTWS1AO1 311 DEGC 313 331 358 345 376 419 431 445 457 480 484
TTWS1AO2 306 DEGC 308 322 342 334 358 396 406 418 436 448 452
TTWS2FO1 314 DEGC 316 332 354 344 369 401 410 419 426 437 441
TTWS2FO2 314 DEGC 317 333 351 344 366 402 410 417 427 439 442
TTWS2AO1 286 DEGC 295 301 310 311 323 352 357 364 375 385 388
TTWS2AO2 286 DEGC 295 301 310 311 320 353 358 365 374 383 387
TTWS3FO1 282 DEGC 294 302 314 317 323 362 370 384 407 416 419
TTWS3FO2 282 DEGC 295 303 315 318 324 364 370 386 413 420 423
TTWS3AO1 123 DEGC 138 147 156 159 166 188 196 210 234 297 299
TTWS3AO2 124 DEGC 140 149 161 169 170 193 202 217 229 298 300
BRG1 X 10 microm 10 5 5 5 5 5 5 5 5 10 10
BRG1 Y 50 microm 45 35 35 40 40 45 40 35 30 30 30
BRG2 X 25 microm 25 25 26 30 30 35 30 25 35 30 25
BRG2 Y 25 microm 25 30 30 30 25 35 35 30 40 35 30
BRG3 X 60 microm 50 40 40 45 50 50 50 55 55 55 55
BRG3 Y 75 microm 50 30 30 30 30 35 30 40 45 50 50
AXIAL 1 `+ 0.2 mm 0.2 0.2 0.28 0.28 0.28 0.28 0.3 0.33 0.4 0.38 0.38
AXIAL 2 0.2 mm 0.2 0.2 0.28 0.28 0.28 0.28 0.3 0.3 0.38 0.35 0.36
EXCITOR 50 65 60 65 70 70 65 65 80 95 140 135
Water Inj. Flow. 0 0 0 0 0 0 0 0 0 0 2.4 Kg/Sec 3.7 4.92 4.5
Lube Oil Pressure 1.68 bar 1.68 1.68 1.68 1.68 1.68 1.65 1.65 1.65 1.65 1.65 1.65 1.65 1.65
Hyd. Oil Pressure 100 bar 100 100 100 100 100 100 100 100 100 100 100 100 100
Trip Oil Pressure 4.8 bar 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8
INSPECTION REPORT
ASSEMBLYDRAWlNG:N"72K402B0
* Recommended spares
17 2 Lockplate 73co43c4
* Recommended spares
I I i I 1
ITEM NUMBER DESIGNATION DRAWING OBSERV
NUMBER OR I
I 1 NORMCODE 1
I
.~:~~:~~~~~~~~~~~~~i~~~~~~~~~~~~~_~~~~~~~~~~~~~.~~~~~~~.~~~_~~~~~~~~~~~~~.~~~~
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..~...._.....................................
l
411 1 Wheel 74A74dB2
* Recommended spares
* Recommended spares
Wheel 74A74202 *
456 1
457 1 74A717A4 *
Key
*
458 1 Coupling 76A15284
Nut 5/8 ”
r369 12 73C075A4 Pos3
22 I Ring R No 9 N38423 tt
201 1 Wheel shaft 74852082 *
202 1 Wheel 74A72582 l
a
366 1 Pinion shaft driver 74A182E2 *
367 1 Pinion shaft driven 74A183F2 l