Professional Documents
Culture Documents
Air Change in Hydraulic Concrete Due To Pumping
Air Change in Hydraulic Concrete Due To Pumping
DUE TO PUMPING
by
Fane R. Sellers, P.E.
MASTER OF SCIENCE
in
CIVIL ENGINEERING
Laramie, Wyoming
December 2002
CONTENTS
CONTENTS ..................................................................................................................... ii
LIST OF TABLES...............................................................................................................x
ACKNOWLEDGEMENT ................................................................................................. xi
CHAPTERS
1 INTRODUCTION ...................................................................................................1
ii
2.5.2 High pressure .................................................................................17
2.6.4 Others.............................................................................................20
4 DATA ANALYSIS................................................................................................36
iii
4.1.2.3 Improbable Influential Factors...........................................42
5.1 Conclusions................................................................................................69
5.2 Recommendations......................................................................................72
REFERENCES ..................................................................................................................74
iv
A.2 Photos from Phase II of the Study (Control Project) ......................................86
CONTROL PROJECT.........................................................................................115
v
LIST OF FIGURES
Figure 3.1 Form Used in the Data Collection of the Study ...............................................25
Figure 4.1 Air Content before Pumping verses Air Content after Pumping......................38
Figure 4.5 Statistical 95% Confidence Intervals by Collection Methods for Mean Air
Figure 4.6 Statistical 95% Confidence Intervals for Mean by Collection Methods Air
Figure 4.7 Measured Air Content after Pumping versus that before Pumping..................49
Figure 4.8 Air Loss versus Air Content before Pumping ..................................................49
Figure 4.9 Relative Air Loss versus Air Content before Pumping ....................................50
vi
Figure 4.14 Statistical 95% Confidence Intervals for Mean Air Loss by Configuration
Figure 4.15 Statistical 95% Confidence Intervals for Mean Air Loss by Position at 6.8%
Figure 4.16 Statistical 95% Confidence Intervals for ZNA Mean Air Loss by Position at
Figure 4.17 Measured Air Loss versus Air Loss Predicted Using Air Loss Model in
Figure 4.18 Measured Air Loss versus Air Loss Predicted Using Relative Air Loss Model
Figure 4.19 Slump after Pumping versus Slump before Pumping ....................................65
vii
LIST OF PHOTOS
Photo A.2 A-Frame Configuration Pumped from the Hill Down into the Foundation
Forms .....................................................................................................................79
Photo A.16 Concrete Sampling, Strip Layout and Single 90º Attachment........................88
Photo A.19 Double 90º Attached to the End of the Boom ................................................89
Photo A.20 Single 90º About to Be Attached to the End of the Boom .............................90
viii
Photo A.21 Single 90º in Use for Placing Concrete ..........................................................90
ix
LIST OF TABLES
Table 2.1 Survey Results on Testing Air Content of Pumped Concrete ...........................14
Table 4.1 Average Differences in Percent Air Content of Various Collection Methods ..45
Table 4.2 Average Differences in Percent Air Content of Various Testers and Pots........51
Table 4.3 Summaries of ANOVA Results on Air Loss and Relative Air Loss .................56
Table 4.4 Constants for Calculation of Air Loss and Relative Air Loss ...........................60
Table 4.5 Percent Air Losses for Various Configurations and Positions Using the Air
Table 4.6 Percent Air Losses for Various Configurations and Positions Using the Relative
x
CHAPTER 1
INTRODUCTION
include cement, fly ash, aggregate, trapped water, additives and air voids. As concrete is
subjected to freeze-thaw conditions, the trapped water within it expands and begins to
form ice. The volume of ice can be up to 9% larger than the same amount of water [1].
With 9% expansion, the freezing water would crack the concrete and cause it to
deteriorate over time. Deicing chemicals may accelerate the deteriorating process. Air
bubbles, trapped in hardened concrete, allow the freezing water to have a release without
breaking the concrete. Therefore, air content in concrete is very important to the
On the other hand, too much air in concrete can have detrimental effects to the
longevity of concrete. Concrete with too much air does not have sufficient binding of the
cement particles to hold up under repeated loadings. The required air content of a
concrete mixture depends upon the application of the concrete and the location of the
pour, whether the pour is in hot or cold climates. Concrete that will never go through
freeze-thaw cycles does not need as many air voids as concrete that will be subjected to
requires 4.0-7.0% air content in the “in place” concrete [2] for Quality Control and
Quality Assurance (QC/QA). Concrete can have up to 3.0% air voids just due to the
mixing process. An air entraining agent is added to the mix prior to mixing to increase
1
the air voids in the concrete. The air entraining agent causes more bubbles to form
during the mixing process which allows for more air voids during and after hardening.
Concrete has many uses and often has to be placed in locations that are impossible
to reach with the cumbersome concrete trucks. Historically, concrete has been placed
using wheel borrows and crane buckets when the trucks can not get close enough. The
invention of the hydraulic concrete pump has proven to be a time and energy saver. The
concrete pump allows for concrete to be placed in very tight locations by the use of a
come in various sizes which are measured in reference to the length of the boom.
In the process of concrete pumping, testing has shown that the air content changes
from before to after the pump. This change has caused questions to be raised on what to
do if the concrete falls outside the limits allowed in the specifications and who is
responsible for the problem. Many DOT’s have chosen to take tests and samples at the
point of placement because of the air change that occurs in the concrete placing
equipment, but this has become difficult and dangerous to employees that have to cross
The problem that has motivated this research study consists of the following:
particular, an amount of air above a base content is vital for concrete to resist
2
• Pumping of hydraulic concrete is one of the most common practices for placing
concrete. While the air content before pumping is relatively easy to control by
design, the change in air content during pumping has not been well understood.
• Testing at the point of discharge of the pump is costly and dangerous at some
between the air content before and after pumping to eliminate or reduce after-the-
This research study was performed in two phases. The data for Phase I was
collected in the summer of 2000, while those for Phase II was collected in the summer
2001. The study had several objectives, which evolved as the study progressed. In Phase
I, the objective was to obtain as much information about the air change across a concrete
pump as possible. As the research progressed, it was determined that projects with no
entrained air were not of interest to this study because all WYDOT projects are required
to have entrained air. It was also noted that projects with extra additives, such as
plasticizers, were beyond the scope of this research. On the other hand, sampling
methods were brought into question and were examined in Phase II.
• Gain an understanding of the factors that affect air content in pumped concrete.
• Provide guidelines for the data collection for Phase II of the study.
• Examine the effect of sampling methods before and after the pump on the change
• Quantify the magnitude and significance of the factors that affect the change in air
A literature review was performed to determine the base of knowledge that exists
about air change in hydraulic concrete due to pumping. The literature review is included
in Chapter 2. The data collection methods used in both Phase I and Phase II are
discussed in Chapter 3. After the data was collected, statistical analysis was performed
and the results summarized in Chapter 4. Conclusions and recommendations for the
WYDOT are presented in Chapter 5. References used throughout the report are included
at the end of the report. Appendices have been included showing many of the photos
(Appendix A) along with brief descriptions of the various parts of the research, copies of
the raw data (Appendices B and C for Phases I and II, respectively) collected in this
study, and results of statistical analysis of data from the control project (Appendix D).
4
CHAPTER 2
LITERATURE REVIEW
It has long been known that entrained air, the small bubbles of air added to
concrete during the mixing process, increases the resistance to scaling caused by freeze-
thaw cycles and deicing chemicals [3]. Increases in air content beyond a base level of
4.0% and up to 7.0% may yield 10% to 20% improvements in long-term durability for
the freeze-thaw effect alone [4]. The durability will be further improved when the
deicing chemicals are involved. Concrete in colder climates, such as that in Wyoming, is
often subjected to many of these freeze-thaw cycles and deicing chemicals during its
service life, therefore a certain level of air content is desired in the concrete. On the other
hand, excessive air content causes reduced strength and should also be avoided [5, 6].
The Wyoming Department of Transportation (WYDOT) requires the air content of “in
Recently, it has become a concern how placement processes affect the air content
been widely used in large projects due to the economy and convenience in construction
[5, 6]. A major concern is the effects of pumping on air content [7-19]. This is because
the air content of concrete before pumping is relatively easy to control. Once the effect
of pumping is understood, the air content in placed concrete can be better predicted.
The placement of most bridge decks is done with a pump, since it is easier to
access the large elevated area, rather than with other methods such as chute or crane and
bucket. When the pump is used to place concrete, air content may be changed; then the
5
effectiveness of the air entrainment is lost. In this case air content is particularly
important because one bad truckload may cause a whole bridge to be rebuilt after only a
few years of use. The expense that the state could incur because of improper air content
could be avoided by having better understanding of the effects of pumping on air content
Air content may help alleviate scaling of concrete by two mechanisms. First, air
entrainment helps to prevent scaling caused by freeze-thaw cycles. Concrete used for
pavement and structures in cold climates is often subjected to freezing at night and then
thawing during the day. Multiple daily cycles may occur due to solar heating and then
cooling under cloud cover. These cycles can occur numerous times during a winter
season. If these cycles occur while the concrete is saturated, scaling and severe
deterioration can occur. This deterioration is caused when water trapped in the concrete
walls of the pores in the concrete. When this pressure exceeds the strength of the
concrete, significant deterioration occurs [3]. Figure 2.1 shows the effects of freeze-thaw
on a concrete railing.
Second, air entrainment helps to prevent scaling caused by deicers. Deicers are
used to increase the friction on bridge decks during the time that ice is on the bridge.
Deicers can accelerate the deterioration of the concrete. This is due to the increased
osmotic and hydraulic pressures in excess of the normal hydraulic pressures that occur in
the saturated concrete when deicers are used on the concrete [1]. These increased
6
pressures can cause an already frozen and stressed piece of concrete to exceed its
strength. Once the strength of the concrete has been exceeded, it ruptures and portions of
concrete spall off leaving a substantial crater. When this occurs multiple times, the
surface of the concrete slab may become so covered with craters that there is no surface
left. At that point, there is no way to fix the slab and it can only be replaced.
For the past 50 years, air has been incorporated into concrete [3]. Air is added in
order to minimize or prevent the effects of freeze-thaw cycles and deicing chemicals.
Since 1938, the Portland Cement Association has been experimenting with admixtures
that are used to produce a stable system of air voids, termed “entrained air” [3]. These
bubbles are usually very small but densely grouped, about one million in one cubic inch
7
of properly entrained concrete [3]. This air is different from the large air voids that are
Vibration causes large air voids to rise to the surface allowing the concrete to settle into
the forms.
Entrained air increases the freeze-thaw resistance by providing spaces within the
concrete that act as reservoirs for freezing water moving within the structure. This
relieves the pressure that the freezing water exerts on the concrete as it expands. The
spacing and size of the air voids affect the amount these air voids are able to prevent
scaling. This is because air voids that are not big enough or spaced too far apart will not
be able to hold the water when it freezes. When this occurs, the benefits that are obtained
by adding the air to the concrete are lost. The following guidelines regarding air voids
cement paste to the edge of the nearest air void) – less then 0.008 inch.
2. Specific surface, α (surface area of the air voids) – 600 square inches per cubic
3. Number of voids per linear inch of traverse, n, – at least one and a half to two
times greater than the numerical value of the percentage of air in the concrete.
Air entrainment can be accomplished in one of two ways. The first is by adding
8
material, fatty and resinous acids and their salts, alkylbenzene sulfonates, and salts of
sulfonated hydrocarbons [1]. Entrained air is added to concrete during the mixing
process by adding an air-entraining admixture to the mix. Air-entraining agents are made
up of molecules that are attracted to water at one end and air at the other [3].
Some common air-entraining agents being used today include: Daravair, Daravair
1000, Master Builders Microair and Master Builders MBVR. They are mostly a soapy
substance. They work by stabilizing the bubbles that are normally formed during mixing
in two ways. First, by reducing surface tension of the mixing water, allowing for the
bubbles to form more easily. Second, by stabilizing the air bubbles by attaching to the
cement grains contained within the mortar of the concrete. After the air voids have been
established, they are left behind when the concrete hardens [3].
The second but less common method used to entrain air in concrete is by using an
air-entraining cement. An air-entraining cement is one that has air added to it during its
production. This is accomplished by using air-entraining additions that are ground with
samples must be taken at regular intervals. There are two methods for testing these
samples. The first method is the Air Void Characteristics of Hardened Concrete,
governed by (American Society for Testing and Materials) ASTM C 457. It is used to
determine the void spacing factor, specific surface of entrained air, and number of voids
per inch of traverse [1]. The second method used in determining air content involves
9
freshly mixed concrete. There are four tests that are used to determine air content in
freshly mixed concrete [1]. These are listed below along with their ease of testing.
2. Gravimetric method (ASTM C 138) – impractical for field testing but can be done
in laboratory.
3. Chace air indicator (AASHTO T 199) – easy way to test approximate air content.
4. Pressure method (ASTM C 231) – for field-testing of concrete that is not made
with highly porous and lightweight aggregates (This method was used in this
research study).
Originally, concrete was placed using a crane and bucket or wheelbarrow when
the ready-mix truck could not reach the placement site. With the advent of concrete
pumps, these placement jobs have been made easier [7]. This is because a concrete pump
can easily reach all areas of the job site. Additionally, a pump can continuously place
concrete while other placement techniques can not. These breaks in placement slow
down production and can create cold joints within the pour.
The concrete pump is able to place the concrete in a manner that is easier to finish
than other placement techniques also, the pump can deposit the concrete close to its final
position thus eliminating the need to move it while it is in the form. These benefits have
made pumping the preferred method for the placement of concrete in hard to reach
places.
10
2.3.1 Developments in pumping
During the first application of pumped concrete, the pumps were piston driven
with metal pipelines. These pipelines were hard to maneuver because sections had to be
removed and elbows added in order to change the discharge point. This process meant
that the pumping operations had to be stopped while changes were made. The changing
of pipes was also complicated by the fact that 6 to 8 inch diameter pipes had to be used to
pump concrete thus increasing the weight of the pipe sections and making them even
harder to move. These large pipes were required because a pumpable mix design had not
been developed [7]. Modern advances in mix design and pump design have resulted in
smaller pipes and more versatile configurations such as A-frame and Z-capable booms.
In order for concrete to be able to travel through a pump, it must first have a mix
that can be placed using this technique. A pumpable mix is dense, cohesive, and has
sufficient mortar [7]. Mortar requirements change as the pump type changes. Mortar
requirements may be as high as 57% by weight for a low-pressure pump with a 4-inch
diameter line or as low as 52% by weight for a high-pressure pump with a 5-inch line [7].
A cohesive mix is one that does not allow the aggregate to separate from the mortar as it
is being pumped. When this separation occurs, the aggregate becomes lodged in the line
and stops the pump from operating [7]. In order to prevent clogging, the mix design must
11
2.4 Current Practice of Testing Air Content of Pumped Concrete
Wyoming is not the only state that is interested in concrete pumping techniques.
In July 2000, the New Jersey Department of Transportation (NJDOT) conducted a survey
of the specifications governing concrete pumping in the United States and Canada [20].
The main objective of the survey was to determine how various states handled the testing
of freshly pumped concrete. The NJDOT shared the results of its survey with UW’s
A total of 22 states and one Canadian province replied to the survey. Of those
responding, 17 specify testing concrete at point of placement (after the pump). Only six
specified testing at the point of discharge of the concrete truck. Table 2.1 shows the
states that replied and where they test. Several of the states stated that, while testing at
the point of discharge of the pump is preferable, safety issues prevent testing after
pumping. Four agencies reported that a pump will be investigated for significant air loss,
rather than placing that burden on the concrete supplier. Two states, Connecticut and
Texas, allow for point of discharge of concrete pump testing if correlation tests have been
established. Five states (North Carolina, Michigan, Hawaii, Arizona, and Missouri) have
specifications for one side of the pump, but will test both points of discharge if a
significant problem dictates so. One state, New York, always tests both ends of the pump
and will reject the pump if there are significant problems with air content. Tennessee
specifies point of discharge of the pump testing, but also has a specification clause for
pumping concrete. The clause has three different methods, one of which must be used at
12
1. A metal loop consisting of four 90-degree elbows shall be placed in the line just
2. A minimum of 3 meters (10 feet) of line lying horizontally just prior to the
discharge point.
3. A rubber discharge hose configured into a "J" shape or loop, either of which
Many states have specifications in place to take care of the need of sampling in a
consistent manner to give them the results desired. Wyoming currently obtains samples
13
Table 2.1 Survey Results on Testing Air Content of Pumped Concrete
Georgia Alaska
Hawaii Arizona
Michigan Arkansas
Mississippi Connecticut
Missouri* Idaho
Maryland
Montana
North Carolina
Ohio
Oregon
Tennessee
Texas
Washington*
Wisconsin
Wyoming
* Indicates that a pump truck will be rejected if there are significant changes in air
14
2.5 Some Possible Causes of Air Change due to Pumping
apparent that air change does occur in pumped concrete. Several contributing factors
stood out. Each of them will be highlighted in the following sections and possible
There have been many theories as to how air is lost in concrete when it is
pumped. These are mostly based on the concrete being impacted against a hard surface,
causing the air bubbles in the concrete to pop and therefore losing a substantial amount of
air [8]. This type of hard hit is often caused when the concrete is allowed to fall
unimpeded from the high point in the pump to the placement site. Some possible fixes
1. Use a pump capable of Z configuration (Figure 2.2) can be used to slow down the
decent of the concrete in the pump. Instead of just allowing the concrete to free
fall the pumps boom can force the concrete to zigzag down the pipe. By making
the concrete zigzag it is not allowed to reach a speed that would cause the bubbles
2. Add a tremie. This should have the same effect that a Z-capable boom would
have in that it would not allow the concrete to gain enough speed to break the air
bubbles.
3. Limit the drop. This can be accomplished by configuring the pump in such a way
that the concrete does not get pumped any higher than necessary. In order for this
15
to happen, the pump may have to be parked farther from the placement site. This
placement will cause the pump to be stretched out instead of being bunched up
4. Introduce a kink in the hose. This can be accomplished by tying a cable to the
boom and the end of the pipe tight enough to keep a kink in the hose. It has been
suggested that this helps to decrease air change much in the same way that a Z-
boom or squeeze tube would in that it does not allow the concrete to move fast
enough to break the bubbles [10]. Also a 90o angle or two can replace the kink in
None of these methods have been tested, previous to this study, to see how
effective they may be. In this research study, some of these methods were tested. These
16
Figure 2.2 Example of a Z-Capable Pump
Pumped concrete can be subjected to high pressures [11]. When the air-entrained
concrete in the pump is exposed to this high pressure, it can cause the air bubbles to
dissolve into the mix water. When this happens, the bubbles may not reform once the
pressure is released, thus resulting in air change in the concrete. Results of previous
laboratory tests indicated that the value of spacing factor increases linearly with the
The best way to prevent this type of air change is to pump the concrete at as low a
pressure as possible. This can be accomplished by using a more pumpable mix, reducing
boom angles, slowing pump rate, and using pump aids to reduce friction.
17
2.5.3 Pump configuration and attachment
There are different configurations of the pump when pumping hydraulic concrete.
In investigating the influence of pump pressure, previous research was found that the
characteristics of the pump set-up or configuration can have a significant effect on the air
content that is reflected by the value of the spacing factor after pumping [18]. The in-situ
test results suggest that the stirring of concrete, during and after pumping, contribute to
the reduction of the detrimental influence of pumping by subdividing the large air voids
into smaller ones. These results also suggested that the attachments to the pump have an
effect on the air content. In order to quantify the effects of pump configurations and
attachments that are commonly used, specially designed experiments should be carried
The concrete materials used have been suggested to be one possible cause of air
change in pumped Portland cement concrete [12]. The variability in the Portland cement,
for example, can cause air content changes. Some of the cement characteristics that can
affect air content include alkali content, fineness, cement content, and contaminants [3].
The exact effects of these variabilities are not known. Generally, it has been shown that
air content will decrease with increased cement content and with increased cement
fineness. Air content has been shown to increase with an increase in cement alkali
content. Contaminates can change air content in either direction. The best way to
prevent change due to contamination is to ensure the cement is transported and stored in
isolated containers. Other materials that may also affect the air change of concrete
18
include cementitious admixtures, chemical admixtures, and aggregates which will be
admixtures include fly ash, furnace slag, and silica fume. Each can have an effect on air
content, most often a decrease in air content in the concrete. The exact amount of change
in air content varies with the amount and fineness of the admixture used. Therefore,
when cement substitutes are used, tests should be performed to ascertain the effect of the
particular admixture.
Chemical admixtures can also affect the air content of concrete. Typical chemical
admixtures that may change air content include water reducers, retarders, and
accelerators. Water reducers and retarders, especially those with lignosulfonates, will
increase air in concrete. Accelerators will only slightly increase air content. Accelerators
2.6.3 Aggregates
Aggregates that are added to the Portland cement can also change the air content
of the cement. The characteristics of the aggregate that have been shown to change air
content include maximum size, sand to total aggregate ratio, and fine aggregate grading.
As the maximum size of aggregate increases the air content requirement decreases. The
19
sand to total aggregate ratio causes air content to increase as sand content increases, and
the middle fractions of the fine aggregate tend to promote air entrainment [13].
2.6.4 Others
Some other characteristics of cement that have been shown to affect air content
include water chemistry, water to cement ratio, and slump. The chemistry of the water
that is added to the cement can change the air content. This is especially true when the
water that is used contains organic material such as algae. Algae may cause the air
content to increase.
The presence of hard water usually does not affect air content if it is used in the
cement mix. However, hard water can cause a loss in air content if it is used to dilute air-
Water-cement ratio affects the air content of a cement mixture. High water-
cement ratio will cause the air content of the cement to increase. This occurs because
when there is a high water-cement ratio the air-entraining agent has more water to
Slump may be an indicator in the air content of the cement in that an increase in
air content. This increase is caused in the same way as the increase that is seen when
20
2.7 Summary
Air content in concrete is a very important aspect of its ability to withstand the
colder climates. The placement of concrete in colder climates must be closely monitored
to ensure the proper amount of entrained air has been added to the concrete in order to
admixtures, which provide spaces within the concrete for the expansion of water. The air
Concrete pumps have evolved technologically to the point that they are the only
economically feasible means of placing concrete in tight locations. Placing concrete via a
pump requires a pumpable mix and close monitoring of the air content of the concrete
mix after the pump. Since pumping is an easy way for concrete to be placed, it is
imperative to know how the pumping of air-entrained concrete can affect the air content
in concrete. Theories concerning air losses within the concrete mix during pumping
include: the large drop within the boom, high pressure within the pipes, pump
configurations and attachments and the materials used in the concrete mix.
21
CHAPTER 3
DATA COLLECTION
The data used in this study was collected in two phases. Thirty-one projects were
tested during Phase I of the study. In addition to bridge deck projects there were water
treatment plants, residential buildings, and business buildings. The main objectives of
Phase I was to determine which factors affected the change in air content in hydraulic
concrete. The findings from Phase I then drove the test methods and types of projects for
Phase II.
Phase II consisted of five projects. The five projects were divided into two
groups. Four of the projects were bridge decks used for looking into the effects of
sampling collection methods. The remaining project was a parking lot used for
The data collection for Phases I and II was conducted during the summer of 2000
and 2001, respectively. Appendix A to this report shows many of the photos, which were
The 31 projects were selected in Colorado, Nebraska and Wyoming. Table 3.1
shows the location, type of construction and testing date of each project. Table 3.2
22
Table 3.1 Projects for Phase I of the Study
23
Table 3.2 Types of Construction Projects for Phase I of the Study
Bridge Decks 8
Residential Walls 5
Internal Slabs 4
Business Walls 4
Residential Slabs 2
Outside Deck 1
Footer 1
Total Projects 31
All data was collected in accordance with ASTM specifications and all testers
were ACI (American Concrete Institute) certified. The following data was obtained at
every project: air content, slump, unit weight of concrete before and after the pump,
concrete temperature, ambient temperature, and pump pressure. The pump configuration
was drawn and photos were taken to obtain the slope of the boom and the approximate
height of the drop. Pump boom length and type of pump were also obtained for the
projects. Concrete mix design data was obtained where available. Figure 3.1 shows the
24
Revision Date: 5/23/2000
Testers: .
Location of Test: (Before/After the Pump) Truck ID Number: .
Date: Ambient Temperature: Weather: .
Air Pot:
Number: Tare Weight: lbs. Capacity: ft³
Concrete:
Final Weight: lbs. Unit Weight: lbs/ft³
Slump: in. Concrete Temperature: Air Content: %
Batch Number: Supplier: .
Phone Number: .
Fax Number: .
Water Added at the Site: gal.
Pump:
Brand: Type: .
Age: Owner: .
Configuration:
Diagram:
25
3.1.1 Testers
All the testers (operators) were trained and ACI certified in testing procedures. In
order to make the test results as consistent as possible, only five people were involved in
3.1.2 Samples
The general requirements outlined in ASTM C172 were followed in the sampling
process. Concrete samples obtained before the pump were placed in 5-gallon buckets to
bring them from the pump hopper to the test equipment. The concrete was lifted out of
Concrete samples obtained after the pump were placed in 5-gallon buckets to get
the sample from the construction site to the test equipment. Nevertheless, most samples
were obtained by placing the bucket near the outflow end of the pump and swinging the
pump over the bucket while it was flowing and filling the bucket. Stopping the pump and
swinging the boom and then starting the pump again to fill the containers was used to
3.1.3 Tests
accordance with ASTM C231 “Standard Test Method for Air Content of Freshly Mixed
Concrete by the Pressure Method” using Type B air meter [21]. Air content and weight
measurements were taken before and after the pump. Simultaneous testing was carried
out so that the concrete was as close to the same on each side of the pump as was
26
possible. In order to eliminate some of the errors associated with field testing of
concrete, the air meters were frequently calibrated. For testing in this study (both Phases
I and II), calibration was performed once a week. The calibration was accomplished in
Slump of concrete: The slump of concrete was taken using ASTM C143
“Standard Test Method for Slump of Hydraulic Cement Concrete”. Again, the slump
was taken before the pump and after the pump. The equipment used for testing was a
Unit weight of concrete: The weight of concrete was measured by weighing the
concrete while in an air pot with a given volume and a known empty weight. This
allowed the computation of the unit weight of the concrete. This test was accomplished
according to ASTM C138 “Standard Test Method for Density (Unit Weight), Yield, and
with ASTM C1064 “Standard Test Method for Temperature of Freshly Mixed Portland
Cement Concrete”. Temperatures were taken from before and after pumping samples.
The equipment used for this test was a thermometer capable of measuring the
temperature of the freshly mixed concrete to ±1°F and having a range of temperature
from 0° to 120°F.
Table 3.3 summarizes the test methods used in the data collection process.
27
Table 3.3 ASTM Test Methods Used in Data Collection
Five projects in Colorado, Nebraska and Wyoming were tested in Phase II of the
study. The test methods followed were the same as summarized in Table 3.3. The
1 (before pumping)
Sampling Methods
3 (after pumping)
Total Projects 5
28
3.2.1 Sampling methods
Four bridge deck projects were tested for the purpose of looking into the effects of
sampling collection methods. One project was used for testing air change due to
sampling methods of concrete before the pump. Three testers and three pots were used in
the testing. The sampling methods used were shovel to collection vessel, chute to
collection vessel (no drop), chute to collection vessel (2-foot drop) and chute to collection
vessel (5-foot drop). The descriptions of the methods of sampling before the pump are
shown below:
• Shovel to collection vessel: The concrete is scooped from the hopper with a
shovel and gently placed in the collection vessel one scoop at a time until the
• Chute to collection vessel (no drop): The collection vessel is placed directly
beneath the end of the chute and the concrete is allowed to flow directly into the
collection vessel.
• Chute to collection vessel (2-foot drop): The collection vessel is placed beneath
the end of the chute and the chute is raised until there is 2 feet between the end of
the chute and the top of the collection vessel. The concrete is then allowed to
flow into the collection vessel dropping 2 feet through open air.
• Chute to collection vessel (5-foot drop): The collection vessel is placed beneath
the end of the chute and then the chute is raised until there is 5 feet between the
end of the chute and the top of the collection vessel. The concrete is then allowed
to fill the collection vessel while falling 5 feet through open air into the vessel.
29
There were four collection methods used in the sampling of concrete after
pumping, which were tested for three projects. The four methods used in sampling
concrete after the pump were: swing pump, hose to collection vessel, and gently shovel
from placed concrete and slopped shovel from placed concrete. The following are
• Swing pump over: The collection vessel is placed on the ground and the outflow
end of the pump is swung over to the collection vessel, which is filled with
minimal drop.
• Hose to collection vessel: The collection vessel is placed directly under the end
• Gently, shovel from placed concrete: The collection vessel is placed on the
ground and the concrete is also placed on the ground. A shovel is then used to
pick up the concrete and place it gently into the collection vessel.
• Slopped, shovel from placed concrete: The collection vessel and the concrete
are placed on the ground. A shovel is then used to lift the concrete to the
collection vessel and then the concrete is slopped into the collection vessel with
some force.
In January 2001, a meeting was held between WYDOT and the University of
Wyoming Research Team. It was decided at the meeting that a control project should be
conducted. This control project would focus on the effects of the configurations and
were:
The control project was a parking lot located at St. Paul's Newman Center at 1800
E. Grand Avenue in Laramie, Wyoming. The parking lot was 106.4 feet wide along
Grand Avenue and 110.0 feet long with a slab thickness of about 4.0 inches. This project
was constructed on August 16-17, 2001. It was designed to have 15 strips that were
about 7.0 feet wide. Figure 3.2 shows the layout of the control project. Air content, as
well as slump, measurements were taken from three positions for each strip, totaling 45
locations, to get a full range of motion for each configuration and attachment. The
position represented the distance between the pump and the location where concrete was
placed, which indirectly reflected the extension or shape of the boom. The extensions of
the boom, the corresponding positions, and the estimated distances were:
Figure 3.3 schematically illustrates the extension and distance for each position.
31
Figure 3.2 Layout of the Control Project
32
Figure 3.3 Schematic Illustration of Boom Extension and Position
33
A total of seven testers were involved in the project, four from the UW Research
Team and three from WYDOT. Six of the testers (oval symbols in Figure 3.2) performed
air content and unit weight testing using six pots (rectangular symbols in Figure 3.2),
while the remaining tester performed slump testing. The testers were all ACI/WYDOT
certified and the pots were calibrated just prior to the control project in accordance with
ASTM calibration procedures. The testers and pots were switched with locations
regularly to reduce possible biases. Additional personnel were present for various
activities, from picture taking to equipment washing to make sure everyone was in the
The concrete used in this experiment met all WYDOT specifications for bridges.
The same mix was used in the whole experiment to eliminate the mix design as a factor.
Three air content measurements were made at each of the 45 locations, one before
pumping and two after pumping. (Positions T1, T2 and T3 in Figure 3.2 indicate
Positions 1, 2 and 3 where air content before pumping was taken.) Ambient temperature
and pump pressures were recorded to determine if they affect air changes in pumped
concrete. In addition, two slump measurements were made at each location, one before
pumping and the other after pumping. The test methods followed were the same as
summarized in Table 3.3. The sampling method for air content used for before the pump
was “shovel to collection vessel”. The sampling method used after the pump was “hose
to collection vessel”. The samples before and after were taken at the same time for each
location, which ensures that the concrete is the same for before and after testing.
34
3.3 Summary
Comprehensive data concerning air content of hydraulic concrete before and after
pumping was collected from a total of 36 construction projects in two phases. Additional
information that may relate to the change in air content of concrete, such as slump, unit
weight, and concrete temperature, was also collected for possible use in establishing the
correlation in the present study or in the future. All tests were performed in accordance
with ASTM standards to assure precision and accuracy of the data. The analysis of the
35
CHAPTER 4
DATA ANALYSIS
After the data was collected from Phases I and II, computerized data bases were
created. These data bases are summarized in Appendices B and C for Phases I and II,
Phase I of the research study was conducted in the summer of 2000. This phase
of the study was designed as a field evaluation. All testing was performed in the field at
actual construction sites. By using field evaluation, eventual application of the results to
obtained. One objective of Phase I was to narrow down the number of factors that affect
the air change in hydraulic concrete due to pumping. By narrowing down the number of
factors, cost in Phase II of the study can be decreased and the amount of useful data
increased.
Before any analysis could be accomplished, the data that was gathered for Phase I
was evaluated. Projects that were found to be a no air mix were eliminated from the
analysis since WYDOT requires air in all concrete mixtures. Also, one project, Project
19, was eliminated because air was being added to the mix after before-pumping testing.
36
Figure 4.1 shows the air content before pumping verses the air content after
pumping with an equality line X = Y. Data points above the reference line reflect
concrete that gained air through the pump while points below the line reflect concrete that
It can be seen, from Figure 4.1, that air is usually lost through the pumping
process, although occasionally the concrete may gain air. The average air change was
calculated to be a loss through the pumping process, although occasionally air can be
gained. Eleven of the fifty-nine tests shown in Figure 4.1 gained some air with an
average air gain of 0.69%. Nine of the eleven tests were outside the 4% to 7% required
by specifications. The estimated average loss of air for a site is 1.06%, which agreed
with a previous finding (1.0%) reported in the literature [5, 6]. A 95% confidence
interval for the mean loss is 0.62% to 1.48%. This confidence interval shows a rather
large spread for the average air change. The significant scatter of data points indicates
that other factors should be considered to statistically explain the air change in concrete
due to pumping in addition to the air content before pumping. Accompanied by the loss
of air is an average loss of slump of 0.6 inch, which is also in agreement with a finding
The scattering data in Figure 4.1 suggests that the air content before the pump is
not an adequate independent measure of air content after pumping. The air content after
cannot be accurately predicted by just knowing the air content before. There are other
37
10.0
Test Data
Equality
Air Content after Pumping (%) 8.0
6.0
4.0
2.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0
Air Content before Pumping (%)
Figure 4.1 Air Content before Pumping verses Air Content after Pumping
Further analysis was conducted to determine the factors affecting air change in
concrete due to pumping. Since WYDOT requires that air content in concrete be equal to
or greater than 4% [2], projects with air contents below this were not included in the
regression analysis. For further details, consult with “Evaluating the Air Content
Wyoming Department of Transportation, May 2000 [22]. The average air loss after
removing those less than 4.0% air content before pumping is 1.23%, which is a slight
38
increase compared to the overall 1.06%. With the 1.23% air loss, the average slump loss
The data that was used to perform the analysis were coded into Excel so that
discrete variables are converted to a usable format by coding these variables into a
number that can be plotted against air change. The air change is then plotted against each
of the variables that were included in this phase of the study. These plots were examined
to see if there was any discernable pattern. When a pattern was detected that variable
Factors affecting air change were classified into three categories. They were
probable, possible and improbable influential factors as obtained through the statistical
analysis [22].
1. Drop distance – the distance from the highest point of the boom in which the
2. Boom slope - the slope at which the boom angles off the back of the pump.
3. Length of boom – the length from the truck to the discharge end of the boom.
consistent basis. The first probable influential factor was drop distance. Usually, the
larger the drop distance is for the concrete, the more the amount of air loss. Another
39
factor is boom slope, which has values that ranged from zero to ninety degrees.
Typically, steep slopes showed a significant air loss and shallow slopes showed air gain
or very low air loss. Length of the boom (total boom length) is an additional factor when
considering air change due to pumping. However, length of boom may be more of an
influence on other factors, such as drop distance, than an independent factor itself.
concrete mix. It is difficult to ascertain the absoluteness of this effect, because it was
difficult to obtain all mix designs from all projects. The final probable influential factor
is collection method. It varied from having the bucket directly in the hopper gathering
concrete straight from the chute to a five-foot drop to the bucket from the chute. A drop
of more than two feet seemed to influence air to be lost from the concrete.
4.0
3.0
2.0
1.0
Air Change (%)
0.0
-1.0
-2.0
-3.0
-4.0
-5.0
-6.0
0 10 20 30 40 50 60 70 80 90
Drop Distance (ft)
40
Figure 4.2 shows one of the probable influential factors, drop distance from the
highest point of the boom to the point of concrete placement, plotted against percent air
change.
1. Precipitation.
3. Pump size.
Possible influential factors were factors that showed statistical significance and
thus had a definite effect on air change but were not quite as significant statistically as
the probable factors. The first possible influential factor is precipitation. A slight
relationship to air change was found when it was whether raining or sprinkling during a
given project. Another possible influential factor is the amount of water added at the
site. While it did not affect all projects the same, in a few instances it seems to have
had an effect on air content as shown in Figure 4.3 as an example. The last possible
influential factor is pump size. Once again, size may be more of an influence on other
41
4.0
3.0
2.0
1.0
Air Change (%)
0.0
-1.0
-2.0
-3.0
-4.0
-5.0
-6.0
0 2 4 6 8 10 12 14 16
Water Added (gal)
1. Slump.
2. Concrete temperature.
3. Water-cement ratio.
4. Gradations.
5. Specific gravity.
6. Pump age.
42
Improbable influential factors are factors that, from the collected data, statistically
have no effect on air change. The first improbable factor is slump. Slump change did not
correlate to any air change as shown in Figure 4.4. Another improbable factor is concrete
temperature. Change in temperature has no correlation on air change for the ranges of
temperatures observed in this study (40° F to 85° F). The next improbable factor is
water/ cement ratio. From the mix designs received, no relationship was found between
the water-cement (or cementitious material) ratio and any air loss incurred on the project.
Also, along the same lines as water/cement ratio, gradations and specific gravity were
found to be improbable correlations. The apparent lack of relationship between the mix
design and air change of a project could be a result of limited data or it could be the result
4.0
3.0
2.0
1.0
Air Change (%)
0.0
-1.0
-2.0
-3.0
-4.0
-5.0
-6.0
0 2 4 6 8 10 12
Slump (in)
Another improbable influential factor is pump age. While the national survey, discussed
in the literature review, indicated that certain states were concerned with a pump’s age,
43
the data from this summer did not indicate that pump age affected air change. A further
improbable influential factor is the number of pump segments. Pump segments along
with concrete flow were too constant to show and differences that would indicate they
The data for the examination of the effects of sampling methods on air content
was from four projects at different construction sites. Three testers were involved in the
project testing. In each project, three replicate tests were conducted for each method.
Four methods were used for before pumping and four methods were used for after
pumping.
44
Statistical analyses indicated that the sampling collection method slightly affect
the measured air content. Table 4.1 shows the differences on average in percent air
Methods
Shovel Shovel
Swing pump Hose
After (gentle) (slopped)
Pumping
0.20 0 -0.01 -0.18
The values in the table are the differences in percent air content relative to the
mean (so that the sum of the differences in each case is zero). For example, “shovel to
collection vessel” measures more air than does “chute to collection vessel 5-foot drop” by
0.6% in the case of the before, while “swing pump over” measures more than does
“slopped shovel from placed concrete” by nearly 0.4% air content in the case of the after.
Figures 4.5 and 4.6 show the 95% confidence intervals for mean air loss by collection
45
95% Confidence Intervals for Means by Collection Method
Before Pumping
7.0
Mean Air Content
6.5
6.0
Collection Method
Figure 4.5 Statistical 95% Confidence Intervals by Collection Methods for Mean Air
4.75
Mean Air Content
4.65
4.55
4.45
4.35
4.25
4.15
Figure 4.6 Statistical 95% Confidence Intervals for Mean by Collection Methods Air
46
4.2.2 Control project
The control project consisted of 15 strips. In each strip, three testing positions
were selected, totaling 45 locations. Three air content measurements were made at each
location, one for before pumping and two for after pumping. Ambient temperature and
pump pressures were recorded to determine if they affect air changes in pumped concrete.
In addition, two slump measurements were made at each location, one before pumping
Six ACI certified testers were involved and six calibrated air pots were used in the
project testing. The testers and pots were switched regularly with strips and positions, in
an attempt to look into the possibility of systematic errors that may be introduced by the
testers and pots and to reduce the errors introduced if they do exist.
The variables considered in this control project for the response of change in air
content are:
• Position: three levels, which reflects of the extension of the boom (1-3).
Figures 4.7 through 4.9 show all the measured data in different ways. Figure 4.7
is the air content before pumping versus the air content after pumping and Figure 4.8
presents the air content before pumping versus the air change (air content before minus
after pumping). Finally Figure 4.9 illustrates the air content before pumping versus the
relative air change (air loss divided by air content before pumping). Each before
measurement was used twice for the two measurements after pumping. These figures
indicate that the air content after pumping, as well as air loss and relative air loss, is a
function of the air content before pumping. The dispersion of the data is the effects of
various influencing factors in addition to the nature of the measurement. The average air
loss for the control project was 0.57%, which is about half of that for Phase I, 1.23%.
This reduction should be mainly attributed to the configurations and attachments that
were believed to produce less air loss and used in the control project for testing.
48
10.00
Test data
Position 1
8.00 Position 2
Position 3
Equality
4.00
2.00
0.00
0.00 2.00 4.00 6.00 8.00 10.00
Air Content before Pumping (%)
Figure 4.7 Measured Air Content after Pumping versus that before Pumping
4.00
Position 2 Position 3
2.00
Air Loss (%)
1.00
0.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
-1.00
-2.00
-3.00
Air Content before Pumping (%)
49
0.80
0.60
Position 2 Position 3
0.40
Relative Air Loss
0.20
0.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
-0.20
-0.40
Air Content before Pumping (%)
Figure 4.9 Relative Air Change versus Air Content before Pumping
evaluate the errors introduced by the testers and pots. Comparisons of tester and pot
scores against averages at each location were made. Figures 4.10 and 4.11 show the
It is seen from Figure 4.10 that, although the effects of testers and pots are
statistically discernible, the magnitudes of these effects are, as expected, minimal. The
variation exhibited by each tester was substantially greater than was the variation among
testers; the range of the six tester means was 0.22%, while the ranges for individual
testers varied between 0.55% and 0.90% air content. Similarly, as shown in Figure 4.11,
variation by each pot dominated variation between pot means; the range of the six pot
50
means was 0.24%, while the ranges for individual pots varied between 0.50% and 1.30%
air content.
Table 4.2 shows the average results for various testers and pots. The values in the
table are differences in percent air content relative to the average. For example, Tester 1
overestimates the air content with respect to the average by 0.09%. In other words,
−0.09% should be added to the reading to obtain the average that is believed to be closer
Table 4.2 Average Differences in Percent Air Content of Various Testers and Pots
Tester 1 2 3 4 5 6
Pot 1 2 3 4 5 6
51
Deviations for Testers: Square = Mean
0.5
Residual
0.0
-0.5
1 2 3 4 5 6
Tester
0.5
Residual
0.0
-0.5
1 2 3 4 5 6
Pot Number
52
In summary, individual testers and pots were substantially less consistent than
were the averages of testers or pots. Even though small differences between means are
statistically detectable, differences are not important from the standpoint of practice.
Tester training and pot calibration can effectively standardize results. Within the
Adjustments for pot and tester effects are very small and are inconsequential in
terms of subsequent analyses. In the following analyses, unadjusted data is used because
adjusted analyses are more complex yet give essentially identical results. All conclusions
the temperature data indicated that the changes in air content are not related in any way
with temperature within the range of temperatures and under the conditions where tests
were conducted. Figure 4.12 illustrates the air loss versus the temperature in which, no
In this project, three pump pressures were recorded. They were the minimum
pressures, the average pressures and maximum pressures. The average pressure
represents the pressure at normal operation of the pump, while the maximum and
minimum pressures are the irregularities around the average. Analyses of the pressure
measurements indicated that none of the three pressures has any significant relationship
with the air changes. Figure 4.13 is an example, in which the air loss shows little pattern
with respect to the average pump pressure contrary to one previous hypothesis.
53
4
3
dAC (%)
2
Air Change
-1
-2
45 55 65 75
Temp (F)
Temperature
3
dAC (%)
2
Air Change
-1
-2
60 70 80 90 100 110 120
PPave
Average Pump Pressure (psi)
54
4.2.2.3 Effects of configuration and position
After eliminating the temperature and pump pressure factors, statistical analysis
was performed on the air content data to investigate the effects of configurations and
attachments of boom and position. The position factor reflected distance of the pump
from the location where concrete was placed, which indirectly reflects the extension or
shape (slope and drop distance from the highest point) of the boom relative to the site.
Position 1 in the project was the “fully extended”, Position 2 the “half-way extended”,
Results of the analysis indicated that both the configuration and position are
statistically significant in changes in air content due to pumping in addition to air content
before pumping. Table 4.3 present summaries of the results of analysis of variance
(ANOVA) using Generalized Linear Model (GLM) for responses of air loss and relative
air loss, respectively. The p-values are as low as from 0.000 to 0.002 for these factors
with respect to the responses, so that the conclusions are the same whether the response
air loss was used or whether the response relative air loss was used. Details of the
Less air loss is present when using HOG and D90 than when using ZNA or NAA.
Significantly more air is lost at Position 3 than is lost in earlier positions. There is no
discernible interaction between the configuration and position, that is, the change in air
loss measured between positions is judged to be the same on average, regardless which of
the five configurations is viewed. It is noticed in particular that use of the hose on the
ground resulted in ambient air mixing with the concrete, causing an average air gain
(seen in a negative percent loss). Figures 4.14 and 4.15 graphically display the air loss in
55
percentage for the five configurations and for the three positions with 95% confidence
intervals for means at 6.8% air content before pumping, which is the median of all
measurements, respectively.
Table 4.3 Summaries of ANOVA Results on Air Loss and Relative Air Loss
P-Value
Factor
Air Loss Relative Air Loss
1
Air Loss
Figure 4.14 Statistical 95% Confidence Intervals for Mean Air Loss by
56
95% Confidence of Mean Air Loss by Position
1.0
0.9
0.8
0.7
0.6
Air Loss
0.5
0.4
0.3
0.2
0.1
0.0
1 2 3
Position
Figure 4.15 Statistical 95% Confidence Intervals for Mean Air Loss by Position at
According to this criterion, it cannot be distinguished between HOG and D90, between
ZNA and NAA, or between S90 and any of the other values. It is, clear, however, that
HOG and D90 lose less air than do ZNA and NAA. Also based on Tukey's Honestly
Significant Difference, Positions 1 and 2 both experience less air loss than does Position
One observation from Figure 4.14 is that both ZNA (Z-boom No Attachments)
and NAA (No Attachments A-frame) produced highest air losses. The ZNA shows
slightly less air loss although the difference between the two configurations is statistically
insignificant. It was the attachments, D90 (Double 90°), S90 (Single 90°), and HOG
(Hose on Ground), that played key roles in reducing the air losses to various degrees.
57
Figure 4.16 shows the statistical 95% confidence intervals by position at 6.8%
initial air for mean air loss of ZNA only. Wider intervals and more overlapping among
the intervals can be observed, compared to those in Figure 4.15 in which data for all five
1.5
Air Change (%)
1.0
0.5
1 2 3
Position
Figure 4.16 Statistical 95% Confidence Intervals for ZNA Mean Air Loss by
58
4.2.2.4 Statistical Models for air change
Regression analyses gave the following statistical model for air loss as a function
where ∆AC = air loss (air content before minus air content after pumping) in %,
ac, ap = constants for configuration and position, respectively (Table 4.4), and
showing that the equation accounts for 76% of the air loss variation when adjustments for
air content before the pump, configuration and position are taken into account. The other
24% consists of other factors which could not be isolated or that were not analyzed in this
study in addition to any random effects present in the system. Equation [4.1] is a good
ac′, ap′ = constants for configuration and position, respectively (Table 4.4), and
Air loss can be calculated by ∆ACR from Equation [4.2] times ACbef.
showing that this equation also accounts for 76% of the variation. The equation for
59
relative air loss is equivalent to the direct measure of change in air content across the
pump.
Table 4.4 Constants for Calculation of Air Loss and Relative Air Loss
Configuration Position
ac′, ap′ -0.057 -0.014 -0.112 0.05 0.133 -0.037 -0.013 0.049
It is noticed that the differences in air loss can be up to 1.52% (HOG versus
NAA) due to differences in configurations and attachments of the boom. The maximum
difference in air loss is 0.56% (Position 1 versus Position 3) for the difference in position.
The air loss due to air content before pumping is 0.64% per percent on average
Figures 4.17 and 4.18 show the measured air loss versus air loss predicted using
the air loss and relative air loss models in Equations [4.1] and [4.2], respectively. There
are 89 valid measurements of air loss in control project. For air loss model in Equation
[4.1], 26 or 29.2% have residuals (measured minus predicted) that are outside ±0.5%; 5
or 5.6% have residuals that are outside ±1.0%. For the relative air loss model in Equation
[4.2], 26 or 29.2% have residuals (measured minus predicted) that are outside ±0.5%; 6
or 6.7% have residuals that are outside ±1.0%. The complexity introduced in the relative
60
air loss model does not result in a better prediction for the data available, making
Tables 4.5 and 4.6 show the air losses calculated using Equations [4.1] and [4.2],
respectively, at selected values of air content before pumping for various configurations
and positions. A negative air loss implies a gain of air content. The differences result
from the differences in the models. The results in the table include the extremes of
observation and thus reflect the greatest disagreements between models that will be seen
for data within the scope of inference. It is noted that the models in the equations are
valid in the range of air content before pumping, which is from 5.3% to 8.1%. Excessive
3.00
Data
Equality
2.00
Predicted Air Loss (%)
1.00
0.00
-1.00
-1.00 0.00 1.00 2.00 3.00
Measured Air Loss (%)
Figure 4.17 Measured Air Loss versus Air Loss Predicted Using Air Loss Model in
Equation [4.1]
61
3.00
Data
Equality
2.00
0.00
-1.00
-1.00 0.00 1.00 2.00 3.00
Measured Air Loss (%)
Figure 4.18 Measured Air Loss versus Air Loss Predicted Using Relative Air Loss
62
Table 4.5 Percent Air Losses for Various Configurations and Positions Using the Air
%AC
Position HOG D90 S90 ZNA NAA
Before
63
Table 4.6 Percent Air Losses for Various Configurations and Positions Using the
%AC
Position HOG D90 S90 ZNA NAA
Before
Figure 4.19 shows the slump values before and after pumping. Little systematic
changes in slump can be observed. In fact, the average slump before pumping is 4.93
inches, while the average slump after pumping is 4.97 inches—virtually the same as that
before pumping—in the control project, although there was a 0.57% average air loss.
64
10.0
Slump
Equality
8.0
4.0
2.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0
Slump before Pumping (in)
The analysis on air change of the data in Phase I of the study indicated that,
generally, air content before pumping is higher than that after pumping. The average air
change was calculated to be a loss through the pumping process, although occasionally
air can be gained. The average loss of air is 1.06%, which agreed with a previous finding
(1.0%) reported in the literature [5, 6]. A 95% confidence interval for the mean loss is
0.62% to 1.48%. This confidence interval shows a rather large spread for the average air
change, indicating that other factors, in addition to the air content before pumping, should
65
Accompanied by the loss of air is an average loss of slump of 0.6 inch, which is also in
agreement with a previous finding (0.5 inch) in the literature [5, 6].
The analysis performed on the data with air content that is equal or greater than
4.0% [2] indicated that the average air loss after removing those less than 4.0% air
content before pumping is 1.23%, which a slight increase compared to the overall 1.06%.
This increase is attributed to the fact that air loss is proportional to the air content before
pumping, which is quantified in the data analysis of the control project. With the 1.23%
air loss, the average slump loss remained unchanged to be 0.6 inch.
Based on the analysis, the factors that affect the air change can be classified into
three categories: probable influential factors, possible influential factors, and improbable
influential factors. Eight factors were found to have either probable or possible
influence:
1. Drop distance.
2. Boom slope.
3. Length of boom.
5. Collection method.
6. Precipitation.
8. Pump size.
Dividing the factors into three categories gave focus to what should be looked at
in more depth. The improbable factors allow less focus to be put on areas of less
significance.
66
4.3.2 Data analysis for Phase II
have a moderate effect on the air content. Maximum differences of 0.6% for the four
methods used before pumping and 0.4% for the four methods used after pumping were
observed. In general, gentler handling of the material results in higher air content
measurements that are believed to be closer to the true values. Standardization of the
Errors in measuring air content introduced by the testers and pots were found to
be minimal. Training and certification of the tester, calibration of the pot, and switching
testers and pots when taking multiple measurements are an effective way to minimize
Ambient temperature and pump pressures were analyzed. They did not appear to
be influencing factors to the changes in air content due to pumping for the data available.
attachment of the boom, the extension or shape of the boom (reflected by the position),
and the air content before pumping. The differences in air loss can be up to 1.52% (HOG
versus NAA) due to differences in configurations and attachments of the boom; and the
maximum difference in air loss is 0.56% (Position 1 versus Position 3) for the difference
67
in boom extension; while the air loss due to air content before pumping is 0.64% per
percent on average.
produced highest air losses. The difference between the two configurations is statistically
insignificant. It was the attachments, D90 (Double 90°), S90 (Single 90°), and HOG
(Hose on Ground), that played key roles in reducing the air losses to various degrees.
Two models were developed for the prediction of air loss, an air loss model and a
relative air loss model. The models developed in the control project are valid in the range
of air content before pumping from 5.3% to 8.1%. Excessive extrapolation should be
avoided. Comparisons indicated that these models give nearly identical predictions, and,
hence, the air loss model in Equation [4.1] is the preferred for its simplicity. Using the
air loss model, 29.2% of the predictions have residuals outside ±0.5%, and 5.6% have
This contradicts the finding in Phase I, a reduction of 0.6 inch, which is believed to be
due to the special configurations and attachments used in the control project.
68
CHAPTER 5
This research study investigated the change in air content of hydraulic concrete
due to pumping. The study was conducted in two phases. Phase I was used to gain an
understanding of the factors that affect air content in pumped concrete. Based on Phase I,
Phase II established the correlation between the air change and various influential factors
5.1 Conclusions
• Analysis on all data collected in Phase I indicates that the change in air content of
• The 95% confidence interval for the mean air loss is 0.62% to 1.48%. This
confidence interval implies a large spread for the average of 1.06%, indicating
that there are other factors affecting the air change, in addition to the air content
before pumping.
69
• Analysis on the data with air content that is equal or greater than 4.0% indicates
that the average air loss is 1.23%, which a slight increase compared to the overall
1.06%. This increase is attributed to the fact that air loss is proportional to the air
content before pumping. With the 1.23% air loss, the average slump loss
remained unchanged to be 0.6 inch, the same as that when the data for air content
• There are many factors that affect the air change in concrete due to pumping.
probable, possible, and improbable influential factors. Eight factors were found
depth:
1. Drop distance.
2. Boom slope.
3. Length of boom.
5. Collection method.
6. Precipitation.
8. Pump size.
The following conclusions can be drawn from the analysis performed in Phase II
of this study:
70
• Concrete sampling methods have a moderate effect on the measured air content
for the methods tested. The maximum difference in measured air content is 0.6%
for before pumping and 0.4% for after pumping. In general, gentler handling of
the material, such as “shovel to collection vessel” and “chute to collection vessel
• Errors in measuring air content introduced by the six testers and six pots are found
to be minimal. It should be mentioned here that all testers used in this experiment
were ACI certified and the Pots were calibrated before testing.
• The ambient temperature ranged from 40° F to 80° F and the pump pressures do
ranges represented in this study may have a significant effect on the air change in
and attachment of the boom, the extension or shape of the boom (reflected by the
▪ For the configurations and attachments tested, namely, Double 90° (D90),
of the boom. While NAA loses most air on average, HOG shows a slight air
gain.
71
▪ The maximum difference in air loss is 0.56% (“closed in” versus “fully
extended”). The closer the location is to the pump, the more the air loss.
▪ The air loss due to air content before pumping is found to be 0.64% per
produced highest air losses. The difference between the two configurations is
statistically insignificant. It was the attachments, D90 (Double 90°), S90 (Single
90°), and HOG (Hose on Ground), that played key roles in reducing the air losses
to various degrees.
• Two models, an air loss model and a relative air loss model were developed for
the prediction of air change. They are both functions of boom configuration and
attachment, boom extension, and air content before pumping. These models are
valid at the range of air content before pumping from 5.3% to 8.1%.
Comparisons indicate that these models give nearly identical predictions, which
makes the air loss model in Equation [4.1] preferred for its simplicity.
5.2 Recommendations
The following recommendations are made based on the results of the entire
research study:
72
• It is recommended that the sampling procedures be standardized with gentler
collection vessel with 2-foot or less drop” is appropriate. For sampling after
pumping, “swing pump over”, “hose to collection vessel”, or “gently shovel from
• The pump pressure does not have to be taken into account since little effect on the
• It is recommended that the boom attachment of hose on the ground or double 90°
elbow be used to produce the least air change across a concrete pump. Since it is
difficult to use a hose on the ground, a double 90° elbow the preferred choice.
• The air change caused by the boom configuration should be taken into account.
losses.
The models work well within the ranges of temperatures, slumps, and other
variables that are in the specifications. Extreme conditions should be studied in the
future to determine if the models are valid for those conditions. Concrete mixes that
have additives, such as silica fume or plasticizers should also be studied to determine
if they fit the models. Finally, concrete mixes with light-weight aggregates should be
73
REFERENCES
1988.
2000.
5. Yazdani, N., M. Bergin, and G. Mujtaba. Variations in the Short- and Long-Term
74
7. Crepas, Robert. Pumping Concrete: Techniques and Applications, Third Edition.
8. National Ready Mixed Concrete Association. What, Why & How? Loss of Air
12. Whiting, D., and D. Stark. Control of Air Content in Concrete. National
13. Wilk, W., and G. Dobrolubov. Influence of Sands Used in Switzerland on the
14. Expanded Shale, Clay and Slate Institute. Guide for Pumping Lightweight
75
15. Yingling, James, Gary M. Mulling, and Richard D. Gaynor. Loss of Air in
Pumped Concrete. Concrete International: Design and Construction, Vol. 14, No.
17. Hover, Kenneth C., and Roger J. Phares. Impact of Concrete Placing Method on
18. Boulet, Daniel, Richard Pleau, and Michel Lessard. Influence of Pumping on the
Annual Conference of the Canadian Society for Civil Engineering, Part 7 (of 7),
19. Nelson, Mark D., Christina Spindler, Khaled Ksaibati, and Charles W. Dolan.
Evaluating the Air Content Changes in Hydraulic Concrete due to Pumping. 81st
6 July 2000.
Michigan, 1999.
76
22. Nelson, Mark, Christina Spindler, Khaled Ksaibati, and Charles Dolan.
77