Professional Documents
Culture Documents
Time-Cost Tradeoff
Time-Cost Tradeoff
Time-Cost Tradeoff
Time-Cost Tradeoff
O Is an attempt to answer what is the relationship
between how long something takes and how
much it costs.
C G
9 12
A
7
D
11
PS H PF
13
E
8
B
8
F I
10 14
And the following table of time-cost data.
/
B-F-I A-D-H
F @ $ 100/week A @ $150/week
I @ @125/week D @ $100/week
Direct Cost ($) 10,850 10,200 9,950 9,750 9,600 9,475 9,400
Indirect Cost ($) 5,000 5,400 5,600 5,800 6,000 6,200 6,400
Total Cost ($) 15,850 15,600 15,550 15,550 15,600 15,675 15,800
18000
16000
14000
12000
10000
Cost ($)
4000
2000
0
25 26 27 28 29 30 31 32 33
Project Duration (Weeks)
Consider :
O Indirect Cost of $200 per week
O Delay damages of $500 per week for Project duration
beyond 30 weeks.
Project Duration
(Weeks) 25 27 28 29 30 31 32
Direct Cost ($) 10,850 10,200 9,950 9,750 9,600 9,475 9,400
Indirect Cost ($) 5,000 5,400 5,600 5,800 6,000 6,200 6,400
Total Cost ($) 15,850 15,600 15,550 15,550 15,600 16,175 16,800
18,000
16,000
14,000
12,000
Cost ($)
10,000
Direct Cost ($)
Indirect Cost ($)
8,000
Liquidated Damages ($)
6,000 Total Cost ($)
4,000
2,000
0
25 26 27 28 29 30 31 32 33
Project Duration (weeks)
Example 2: For the given project
Activity Depends Normal Crash Normal Crash cost
upon time time cost
A - 7 3 3000 3600
B A 8 7 1700 2000
C A 10 6 2200 2400
D A 5 2 2400 3000
E B, C, D, A 7 3 1900 2500
F C, D, A 5 4 800 1000
G E, F, A, B, 3 1 500 900
C, D
1. The duration that I can decrease so that the cost of crashing
does not exceed 400$
2. The cost of decreasing the project duration by six days is
3. The min. duration of the project
4. The total cost of the project at min. duration is