Professional Documents
Culture Documents
Causes of Time Overrun of Education Trust Fund BLDG Projects in North Central Nigeria PDF
Causes of Time Overrun of Education Trust Fund BLDG Projects in North Central Nigeria PDF
info/journals/jorind
E-mail: richardkoko5@gmail.com.
Abstract
The study surveyed Education Trust Fund building projects in some tertiary institutions in north central Nigeria
with the aim of ascertaining the causes of time overrun of these projects. The survey was carried out with the help of
a structured questionnaire administered to clients, consultants and contractors’ alike. Oral interview was equally
conducted to clarify some gray area identified. The data collected were analysed using descriptive, analysis of
variance and chi-square methods of data analysis. The results shows that 73.91% of forty six(46) projects surveyed
in this zone had cases of time overrun and four major factors were identified to be responsible which are: design
changes, poor contract management, poor financing and mis-management of mobilization fee by the contractors.
The paper concludes that time overrun can be prevented by given due consideration to design and planning at the
inception of the project by the parties involved.
183
JORIND 11(1), June, 2013. ISSN 1596-8308. www.transcampus.org/journals; www.ajol.info/journals/jorind
This paper examines causes of time overrun of in Nigeria. Act No. 40 of 1998 amended the law
Education Trust Fund building projects in selected establishing the Fund to reposition it to meet with new
tertiary institutions in some states in North Central challenges (Babayo, 2010). In repositioning the Fund,
Nigeria. the law was again amended in May 2011 as Tertiary
Education Trust Fund to carter for educational problems
of tertiary institutions only (Anuku, 2011). The main
The Education Trust Fund (ETF) source of income available to the Fund is the two percent
levy paid from the accessible profit of companies
Against the background of deteriorating educational
registered in Nigeria. The Federal Inland Revenue
infrastructure and the falling standard of education in the
Service (FIRS) is empowered by the Act to assess and
late 80’s and early 90’s in Nigeria, agitations arose for
collect education Tax, and so far N361.79 billion was
reforms in the education sector. In response, the
collected as at December 2009 as per CBN transfers
Education Tax Fund was established in 1993 under (Babayo, 2010).
decree No.7 as amended by Act No. 40 of 1998 as a
Trust Fund, with the objective of using funding with
project management to improve the quality of education
The normal sectored allocations for the period 1999- In evaluating and analysing the causes of time overrun of
2009 stood at N195, 224,327,611.49 and this was ETF building projects in tertiary institutions in North
allocated to the various tiers of the education i.e. tertiary, Central Nigeria, a structured questionnaire of seven
secondary and primary sub-sectors. Within the same identified causes were served on clients, consultants and
period, the sum of N110, 850,530,030.71 was disbursed contractors of these projects. A total of 24 questionnaires
to benefiting institutions. The disbursement is pre- made up of the client, one consultant and two contractors
conditioned on the satisfactory utilization of the funds were chosen per institution in the study area. It was
released to each beneficiary. The conditions for organised in the form of a priority scaling i.e Likert scale
disbursement put in place by the Fund have significantly (1=Strongly disagree, 2=Disagree, 3=Undecided,
enhanced cash flow to the beneficiaries for the timely 4=Agree, 5=Strongly agree). The questionnaires were
completion of projects. Because of this, the Fund has not analysed and presented in the descriptive and inferential
recorded any abandoned project since 1999 (Babayo, methods using tables, percentile, chi-square and student
2010). t-test from which results were drawn.
Even though the Fund claims the above, what we do not
know is the level of efficiency and effectiveness. How
Presentation of results and discussions
time effective these projects are is what this study seeks
to evaluate. A summary of the initial and final durations of the
projects including starting and finishing dates in all the
institutions surveyed are tabulated below.
Research method
184
JORIND 11(1), June, 2013. ISSN 1596-8308. www.transcampus.org/journals; www.ajol.info/journals/jorind
185
JORIND 11(1), June, 2013. ISSN 1596-8308. www.transcampus.org/journals; www.ajol.info/journals/jorind
186
JORIND 11(1), June, 2013. ISSN 1596-8308. www.transcampus.org/journals; www.ajol.info/journals/jorind
A t-test of initial durations of projects in institutions in the institutions surveyed had serious cases of time
Plateau, Benue and Kogi states show p-values of 0.001, overrun as indicated by the results of the analysis as well
0.005 and 0.001 respectively at 5% level of significances as the simple percentile indicated in the above tables.
which means there is significant difference in the Only College of Education Katsina Ala, Benue State
durations of projects in the states in North Central whose time overrun ranges between 25% and 165.75%
Nigeria. has the least case. Other institutions are as follows,
University of Jos, 65% to 291.67%; Plateau State
A one-way analysis of variance for duration variances in Polytechnic, Barkin Ladi, 225% to 366.67%; University
North Central Nigeria shows a p-value of 0.628 for of Agriculture, Makurdi, 175% to 933.33%; Federal
initial and 0.937 for final duration at 5% level of Polytechnic, Idah, 7.4% to 456.25%, COE Ankpa 35% to
significance which shows that there is no significant 456.25%.
variation in durations of projects in the states. A post
Hoc test for multiple comparisons gives the following p- Causes of time overrun
values, Kogi and Plateau, 0.942 initial and 0.727 final,
Kogi and Benue, 0.396 initial and 0.923 final, Benue and Seven factors that can cause time overrun were identified
Plateau, 0.468 initial and 0.788 final. Hence, there is no and the stakeholders were asked to identify which of
significant variation in the durations of the projects in these could lead to such overrun and their responses are
different states in North Central Nigeria. Impliedly, all shown in Table 8 below:
All the three stakeholders (Clients, Consultants, and c) financing and payment of completed works: Release
Contractors) agree on three factors viz, a) Design of funds for these projects are in three tranches:- 50%
changes: It was discovered that the designs are mostly mobilisation, 35% second payment after roofing and
altered which is caused by both clients and consultants 15% after completion., the contractors do not manage
their mobilisation fee well and the second release takes
b) poor contract management and
time and can be seen as factors of time overrun.
187
JORIND 11(1), June, 2013. ISSN 1596-8308. www.transcampus.org/journals; www.ajol.info/journals/jorind
A one way analysis of variance (ANOVA) and chi- projects as they are bound to keep to
square tests are carried out to check the variability of the construction schedule and avoid time overrun.
responses among stakeholders. The p-value of the
ANOVA test is 0.718. A post Hoc test for multiple References
comparisons shows the following p-values, 0.481 for
Ali, A.S. and Rahmat, I. (2010). “The Performance
clients and consultants also same for clients and
Measurement of Construction Projects Managed by ISO-
contractors, 1 for contractors and consultants. A chi-
Certified Contractors in Malaysia”. Journal of Retail
square test gives a p-value of 0.983. All these results
and leisure Property (2010)9, 25-35. www.palgrave-
mean that there is no variation among stakeholders as to
journals.com/rlp/journal/v9/nl/abs/rlp200920a.htm
causes of time overrun.
Retrieved 5th August, 2011.
Conclusions
From the survey carried out it was discovered that the Anuku,W. (2011). Tertiary Education Trust Fund Bill.
modalities put in place by Education Trust Fund http://www.elendureports.com. Retrieved 23rd June,
administrators should ensure timely completion of most 2011.
of the projects being executed in our tertiary institutions.
However, the following findings were made: Babayo, M. (2010). ETF 2009 Annual Report. Cavalet
Publications Ltd
a. There are cases of time overrun in almost all the
building projects in the institutions considered, forty six Barkley, B. and Saylor, J. (1994). Customer-driven
building projects were constructed in the six institutions Project Management. New York, McGraw-Hill.
studied in North Central Nigeria. Thirty four
Falco, M.D. and Macchiaroli, R. (1997). Timing of
representing 73.91% have cases of time overrun.
Control Activities in Project Planning. Elsevier science
b. All the parties to the contract: client, consultant and
Ltd and IPMA, Great Britain.
contractors were responsible for such delay.
c. The factors identified to be responsible for such delay Kumaraswamy, M.M. and Thorpe, A. (1999).
are: design changes, poor contract management and “Systematizing Construction Project Evaluations”.
Financing and payment of completed works and Journal of Management in Engineering 12(1):34-39
improper management of mobilisation by contractors.
Rose, K.H.(1995). A Performance Measurement Model,
Recommendations Quality Progress 28(2):63-66
Based on the findings of the study, the following
recommendations are made: Salter, A. and Torbett, R. (2003).” Innovation and
The practice of each institution having her Performance in Engineering Design”. Journal of
consultants should be maintained. Construction Management and Economics 21:573-580.
Consultants should be more careful at planning
stage in order to avoid variation of works. Webster, F.M. and Knutson, J. (2006). What is Project
Clients should programme the payment Management? Project Management Concepts and
schedule in such a way that release of funds Methodologies. In: The AMA Handbook of Project
especially the 35% second payment should be Management 2nd ed. Paul c. Dinsmore, Jeannette.
on time to avoid time overrun. Cabanis-Brewin (Eds), Amacom, New York.
Contractors should engage professional builders
to manage the production of their building
188