ID Task Name Duration Start Finish July 2020

20 23 26 29 2 5 8 11 14 17 20 23
1 PCC - ADDITIONAL WORKS VERTIS OFFICE Catch Up Schedule 34 days Mon 6/22/20 Sat 7/25/20
2 INTERIOR WORKS 27 days Mon 6/22/20 Sat 7/18/20
3 Supply and Installation of Closed-circuit Tevelevision (CCTV) Cameras 10 days Mon 6/22/20 Wed 7/1/20
4 Supply and Installation of Access Devices 10 days Thu 7/2/20 Sat 7/11/20

5 Testing and Commissioning of cctv and door access 3 days Sun 7/12/20 Tue 7/14/20
6 Installation of water heater 7 days Mon 6/29/20 Sun 7/5/20
7 supply and installation of convex mirror 7 days Mon 7/6/20 Sun 7/12/20
8 Supply and installation of additional power outlets 8 days Sat 6/27/20 Sat 7/4/20

9 testing of installed power supply 5 days Sun 7/5/20 Thu 7/9/20


10 Installation of hand dryer 14 days Mon 6/22/20 Sun 7/5/20
11 Assembly of steel racks 5 days Fri 6/26/20 Tue 6/30/20
12 Delivery of Podium 10 days Wed 7/1/20 Fri 7/10/20
13 Delivery of air purifier 10 days Mon 6/22/20 Wed 7/1/20
14 Delivery of air cooler 10 days Wed 7/1/20 Fri 7/10/20
15 Delivery and installation of projector platform 8 days Wed 7/1/20 Wed 7/8/20
16 restoration of affected wall and ceiling 22 days Sat 6/27/20 Sat 7/18/20
17 Punchlisting 7 days Sun 7/19/20 Sat 7/25/20

Task Milestone External Tasks


Project: PCC VERTIS Catch Up sched
Split Summary External Milestone
Date: June 20, 2020
Progress Project Summary Deadline