DRAWING OF RCC CIRCULAR STORAGE TANK

CAPACITY OF TANK 120000 LITERS.


NOT TO SCALE

VENTILATOR
0.10 M

MAN HOLE COVER


H= 1.10
5.65
INLET 0.23
0.30 RING

3.40
3.70 M-30
6.70

G.L.

1.20 OUT LET


0
0.45
M-30
0.10
1.600 4.86 1.600
8.06

6.46

Executive Engineer,
IPH Division, Sunder Nagar.
K

NOT TO SCALE
Dia of tank (internal) 6.70 m
R= 5.65 m
h= 1.116667 1.10 m

MAN HOLE COVER Capacity of tank: 120000 Ltrs.


Taking height: 3.40 say 3.40
Dia of tank: 6.70
SQUARE
BEAM Capacity calculation:
0.785 d^2 3.40 120 cum
d^2 44.93
d 6.70 m
M-30
Thickness at top 0.20
Thickness at bottom 0.22 0.230

OUT LET H^2/Dt Ratio= 8.88

0.23

8.06 780
6.46 238
1018.00 631.16

ve Engineer,
sion, Sunder Nagar.
DETAIL OF MEASUREMENT
Detailed Project Report for Dehar and Multi Village Group Piped Water Supply Scheme for Part of
Sundernagar Block of Mandi District (H.P)
(S. H :- C/O RCC Circular Storage Tank 120000 Liters Litres Cap. at Khanokhar)

Sr. Description of items No. x L x B x H Quantity


No.
1 2 3 4 5 6 7
1 Excavation in foundation and
trenches etc.in earth work in
Pick Jumper work.

For Storage Tank 22/28 x 8.06 x 8.06 x 1.20 61.25 Cum


For Scour arrangement 10 x 0.70 + 0.60 x 1.20 7.80 Cum
2
Total :- 69.05 Cum
2 P/L C.C.M-15 (not weaker than
1:3:6) in foundation & plinth.
For Storage Tank 22/28 x 8.06 x 8.06 x 0.10 5.10 Cum
3 P/L R.C.C. M-30 (Not weaker than CC
1:1:2) .
(i) In foundation and plinth
(a) In footing 3.1429 x 6.46 x 1.60 x 0.23 7.47 Cum
(b) Inner base slab 22/28 x 4.86 x 4.86 x 0.10 1.86 Cum
Total:- 9.33 Cum
(ii) Walls (any thickness but not
less than 0.1 m thickness)
plinth and string courses.

(a) Vertical Walls 3.1429 x 6.90 x 0.22 x 3.40 15.85 cum.


4 (a) Ring Beams : 3.1429 x 6.93 x 0.23 x 0.23 1.15 cum.
4(b) Dome slab: 2x 3.1429 x 5.65 x 1.10 x 0.10 3.91 Cum
(v) Crown ring beam 3.1429 x 0.95 x 0.20 x 0.20 0.12 cum.
Total :- 4.03 cum.
5 Providing Tor Steel
Reinforcement :-
(a) In base slab , 9.33 90 Kg./Cum 839.00 Kg.
(b) In beams & walls:- 17.00 90 Kg./Cum 1530.00 Kg.
(c) In Dome 4.03 90 Kg./Cum 362.00 Kg.
Total:- 2731.00 Kg.
6 Providing Form work with steel
plates.
(i) Foundation and plinth: 3.1429 x 8.06 x 0.23 5.83 Sqm.
(ii) In Vertical walls:-
(a) Inner side:- 3.1429 x 6.70 x 3.40 71.59 Sqm.
(b) Outer side:- 3.1429 x 7.13 x 3.40 76.19 Sqm.
Total:- 147.78 Sqm.
(iii) In beams:
(a) Sides 2x 3.1429 x 6.93 x 0.23 10.02 Sqm
(b) Soffit: 1x 3.1429 x 6.93 x 0.03 1.31 Sqm
Total:- 11.33 Sqm
7 Providing Form work with
ordinary timbers.

(i) In Dome slab:


2 3.1429 x 5.65 x 1.10 39.07 Sqm.
Less for man hole: 3.1429 x 0.56 2 Nos. (-) 0.49 Sqm.
Total:- 38.58 Sqm.
8 P/F Man Hole Cover with 2 Nos.
Frame of 560 mm dia.
9 P/F Connecting Pipes:-
(a) Inlet pipe:- 200 mm = 6 Rmt.
(b) Outlet pipe:- 200 mm = 6 Rmt.
© Scour pipe:- 200 mm = 10 Rmt.
10 P/F Cast Iron Sluice Valves:-
(a) In Let Valve 200 mm = 1 No.
(b) Common Header Valve 200 mm = 1 No.
(c) Scour Valve 200 mm = 1 No.
11 Steel work welded in built up
sections,trusses and framed
work
(i) In Ventilator work
Verticals MS angles ISA 6 Nos. 0.75 x - 3.80 17.10 Kg.
50x50x5
Angle Rings at Top & Bottom 2 Nos. 3.142 x 0.75 3.80 17.91 Kg.
ISA 50x50x5
MS Sheet Cap over ventilator 2x 3.14 0.75 x 0.45 12.55 26.62 Kg.
(ii) In Ladder (outer
MS Angle 50x50x6mm @ 4.50 4 x 6.00 x 4.50 = 108.00 Kg
Kg /mtrs.
MS Angle 40x40x5mm @ 3.00 52 x 0.90 x 3.00 = 140.40 Kg
Kg /mtrs.(26 steps x 2 Nos.)
MS Flats 20 x 5 mm @ 0.80 Kg/ 468 x 0.25 x 0.80 = 93.60 Kg
mtrs (26 steps x 18 Nos.)
(iii) Landing
Vertical angles 50x50x6mm @ 4 x 4.50 x 4.50 = 81.00 Kg
4.50 Kg/mtrs.
MS Angle 40x40x5mm @ 3.00 8 x 0.90 x 3.00 = 21.60 Kg
Kg /mtrs. (2 Nos.)
MS Flats 20 x 5 mm @ 0.80 Kg/ 36 x 0.90 x 0.80 = 25.92 Kg
mtrs (Both Side)
(iv) Railing
MS Pipe 32 mm dia 1.52 2 x 9.16 x 1.52 = 27.85 Kg
Kg/mtrs.
Square Bar 12 mm dia @ 1.13 40 x 0.90 x 1.13 = 40.68 Kg
Kg/mtrs.
Total :- 600.68 Kg
or 6.01 Qtls.
12 Providing and Fixing Wire
Gauge for Ventilator in all leads
and lifts.
1 No. 3.142 x 0.75 x 0.75 1.77 Sqm
13 Finishing walls with water
proofing cement paint of
approved brand and
manufacture of required shade
on undecorated wall surface
( two coats) to give an even
shade after throughly brushing
the surface to remove all
dirt,dust and remains of loose
material sand papered,stopping
complete in all respect.
Outer wall above GL(incl. RB) 1 No. 3.142 x 6.93 x 2.27 49.43 Sqm
Dome Outer face (as per Item No. 06) 38.58 Sqm
Total :- 88.00 Sqm
14 P/L C.C.M-15 (not weaker than 3.1428 x 8.66 x 1.50 x 0.15 6.12 cum.
1:3:6) in foundation & plinth. (as
plinth protection)

15 Boulder filling dry hand packed 3.1428 x 8.66 x 1.50 x 0.15 6.12 cum.
tightly under floors.(in plinth
protection
16 P/F Aluminimum Ladder 1 No.
450mm wide.

Executive Engineer
I&PH Division Sunder Nagar.
ABSTRACT OF COST
Detailed Project Report for Dehar and Multi Village Group Piped Water Supply Scheme for
Part of Sundernagar Block of Mandi District (H.P)
(S. H :- C/O RCC Circular MBR of 120000 Litres Cap. at Khanokhar)

Sr. Description of items Quantity Rate Unit Amount


No.
1 2 3 4 5 6
1 Excavation in foundations, trenches etc. in all 69.05 Cum 436.00 Per Cum 30106.00
kinds of soil such as pick jumper work blasting
and chiselling soft/ hard reock where blasting is
prohibited in all leads and lifts i/c trimming &
dressing of side levelling of bed stacking the
excavated soil in 15 Cm layers when required in
to sides of foundation etc. including consolidating
each deposited layer by ramming and watering
and then disposing of all surplus excavated soil
as directed in all leads and lifts and soring
strutting timbering & dewatering where ever
required complete in all respect as per the
direction & to the entire satisfaction of Engineer
in Charge.

2 Providing and laying cement concrete M 15 (Not 5.10 Cum 5581.00 Per Cum 28487.00
Leaner than CC 1:3:6, 1 cement:3 sand:6 graded
stone aggregate 40 mm nominal size) and curing
complete excluding cost of form work in
foundation and plinth in all leads and lifts.
3 Providing and laying cement concrete in M 30
grade but not leaner than 1:1:2 (1 cement : 1
sand : 2 graded stone aggregate 20 mm nominal
size) and curing complete excluding cost of form
work and reinforcement and reinforced concrete
work in :-

(a) Foundations and Plinth in all leads and lifts. 9.33 Cum 6396.00 Per Cum 59658.00
(b) wall (any thickness but not less than 0.1 m 15.85 Cum 6440.00 Per Cum 102089.00
thickness) attached pillasters, buttresses, plinth
and string courses, etc. from top of foundation
level upto floor two level.

4 Providing and laying cement concrete 1:1.5:3


(1cement:1.5 sand : 3 graded stone aggregate
20 mm nominal size) and curing complete
excluding cost of form work and re-inforcement
for reinforced concrete work in:
(a) Beams, cantilivers, girders and lintels sides and 1.15 Cum 6462.60 Per Cum 7446.00
soffits of beams,beam haunchings cantilivers,
girders, bressumers and lintels not exceeding 1
metre in depth in all leads and lifts.

(b) suspended floor, Dome roofs, landings shelves 4.03 Cum 6462.60 Per Cum 26023.00
and their supports balconies, beams, girders
,bressumers and cantilevers etc in all leads and
lifts of any shape in all leads and lifts.
5 Providing tor steel reinforcement for R.C.C. work 2731.00 Kg. 73.00 Per Kg 199363.00
including bending, binding and placing in position
complete upto floor two level in all leads and lifts.
Sr. Description of items Quantity Rate Unit Amount
No.
6 Providing form work with steel plates 3.15 mm
thick welded with angle iron in frame 30x30x5
mm so as to give a fairfinish I/c centring ,
shuttering , strutting and proping etc.with wooden
battens and ballies, height of propping and
centring below supporting floor to ceiling not
exceeding 4m and removal of the same for insitu-
reinforced concrete & plain concrete work in :-

(a) Foundations, footings, basis of columns & the 5.83 Sqm. 238.50 Per Sqm 1390.00
like and mass concrete in all leads and lifts.
(b) Beams, cantilivers, girders and lintels sides and 11.33 Sqm. 416.70 Per Sqm 4719.00
soffits of beams,beam haunchings cantilivers,
girders, bressumers and lintels not exceeding 1
metre in depth in all leads and lifts.
(c) Vertical surfaces such as walls (any thickness), 147.78 Sqm. 304.90 Per Sqm 45059.00
partitions and the like including attached
pillasters, buttress,plinthand string courses and
the like in all leads and lifts.
7 Providing form work of ordinary timber plankings
so as to give a rough finish including centering
,shuttering, propping etc. height of propping and
centering below supporting floor to ceiling not
exceeding 4 meters and removal of the same for-
in-situ reinforced concrete and plaiin concrete
work in:-

(d) Arches, domes, vaults up to all span in all leads 38.58 Sqm. 3255.20 Per Sqm 125577.00
and lifts.
8 Providing & fixing precast concrete manhole 2 Nos. 2090.20 Each 4180.00
cover & frame conforming to IS-12593-1988,part-
I and IS 12592-1991, part-II, 560mm diameter ,
medium duty in all leads and lifts.

9 Providing and Laying in trenches,4.00 mm Thick


MS Pipes as per ISO:3183 with all specials like
Tees, Bends, Reducers, Nipples etc. (earth work
to be measured and paid for separately)

(a) Inlet pipe:-200mm 6.00 M 3113.00 Per Rmt 18678.00


(b) Outlet pipe:-200mm 6.00 M 3113.00 Per Rmt 18678.00
© Scour pipe:-200mm 10.00 M 3113.00 Per Rmt 31130.00
10 Providing and fixing C.I. Sluice valve (with hand
wheel) as per IS:780 Class-I upto 300 mm dia
(including brass spindleand as per IS:2906 class
II for diameters more than 300 mm complete with
bolts, nuts, rubber insertion etc,(The tail pieces if
required shall be measured and paid for
separately)

(a) In Let Valve 200 mm 1 No. 59952.00 Each 59952.00


(b) Common Header Valve 200 mm 1 No. 59952.00 Each 59952.00
(c) Scour Valve 200 mm 1 No. 59952.00 Each 59952.00
11 Steel work welded in built up sections,trusses 6.01 Qtls 8274.90 Per 49706.00
and framed work including cutting,hoisting, fixing Quintals
in position and applying a priming coat of red
lead paint :- in gratting, framed guard bar,
ladders, railing brackets and similar works in all
leads and lifts.

12 Providing and Fixing wire gauge using 1.77 Sqm. 156.10 Per Sqm 276.00
galvanised M.S. wire gauge of I.S. gauge
designation 85 G. with wire of dia 0.56 mm for
Ventilator of tank complete in all respect in all
leads and lifts.
Sr. Description of items Quantity Rate Unit Amount
No.
13 Finishing walls with water proofing cement paint 88.00 Sqm. 73.85 Per Sqm 6499.00
of approved brand and manufacture of required
shade on undecorated wall surface ( two coats)
to give an even shade after throughly brushing
the surface to remove all dirt,dust and remains of
loose material sand papered,stopping complete
in all respect.

14 P/L C.C M-15 (not weaker than CC 1:3:6) in 6.12 Cum 6114.14 Per Cum 37441.00
foundation & plinth. (as plinth protection)

15 Boulder filling dry hand packed tightly under 6.12 Cum 2607.70 Per Cum 15969.00
floors.(in plinth protection
16 P/F Aluminimum Ladder 450mm wide of 1 No. 10000.00 Each 10000.00
rectangular section 65mmx 35mm having length
3.60m to 4.80m in all lead and lifts to the entire
satsfaction of Engineer-in-Charge.

G. 1002330.00
Add 10% for Site Development 10.00 % of Basic cost Total :- 100233.00

G. 1102563.00
Total :-

Executive Engineer,
I&PH Division, Sunder Nagar.