2 c.

Membuat MRP table untuk semua komponen

MPS Table
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
General Requirement 100 50 75 150

MRP Table
Lead time 1 week
Venti20 Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 0 100 0 0 0 50 0 75 0 0 0 0 150
Scheduled Receipt
Projected on Hand 25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 0 75 0 0 0 50 0 75 0 0 0 0 150
Planned-order receipt 75 50 75 150
Planned-order release 75 50 75 150

Lead time 2 weeks


Bag Valve Mask Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 50 50 50 50 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 25 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 25 50 75 150
Planned-order release 25 50 75 150
Lead Time 1 weeks
Chip Board Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 50 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 50 50 75 150
Planned-order release 50 50 75 150

Lead Time 1 weeks


Driver Module Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 50 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 50 50 75 150
Planned-order release 50 50 75 150

Lead Time 1 weeks


DC Motor Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 50 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 50 50 75 150
Planned-order release 50 50 75 150
Lead Time 1 weeks
Switch Button Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 150 0
Scheduled Receipt
Projected on Hand 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 50 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 50 50 75 150
Planned-order release 50 50 75 150

Lead Time 1 weeks


Power Supply Adapter Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 50 50 50 50 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 25 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 25 50 75 150
Planned-order release 25 50 75 150

Lead Time 1 Week


Cable Ties Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 300 0 0 0 200 0 300 0 0 0 0 600 0
Scheduled Receipt
Projected on Hand 150 150 150 150 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 150 0 0 0 200 0 300 0 0 0 0 600 0
Planned-order receipt 150 200 300 600
Planned-order release 150 200 300 600
Lead Time 1 weeks
Bolts Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 975 0 0 0 650 0 975 0 0 0 0 1950 0
Scheduled Receipt
Projected on Hand 200 200 200 200 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 775 0 0 0 650 0 975 0 0 0 0 1950 0
Planned-order receipt 775 650 975 1950
Planned-order release 775 650 975 1950

Lead Time 1 weeks


Nuts Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 975 0 0 0 650 0 975 0 0 0 0 1950 0
Scheduled Receipt
Projected on Hand 200 200 200 200 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 775 0 0 0 650 0 975 0 0 0 0 1950 0
Planned-order receipt 775 650 975 1950
Planned-order release 775 650 975 1950

Lead Time 1 weeks

Beg Week
Laser Cut Acrrylic 8 mm
Inv
Lot size : lot-for-lot 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 100 100 100 100 25 25 25 25 0 0 0 0 0 0 0 0
Net Requirement 0 0 0 0 0 0 25 0 75 0 0 0 0 150 0
Planned-order receipt 25 75 150
Planned-order release 25 75 150
Lead Time 1 weeks

Beg Week
Laser Aluminium 3 mm
Inv
Lot size : lot-for-lot 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 75 75 75 75 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 0 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 50 75 150
Planned-order release 50 75 150

Lead Time 2 weeks


PEEP Valve Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 50 50 50 50 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 25 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 25 50 75 150
Planned-order release 25 50 75 150

Lead Time 2 weeks


Extention Tube Beg Week
Lot size : lot-for-lot Inv 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Gross Requirement 0 0 75 0 0 0 50 0 75 0 0 0 0 150 0
Scheduled Receipt
Projected on Hand 50 50 50 50 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 0 25 0 0 0 50 0 75 0 0 0 0 150 0
Planned-order receipt 25 50 75 150
Planned-order release 25 50 75 150
2 d. Total Cost the company should pay for 15 weeks period
Total Holding Cost = 2225 unit X $2 = $ 4.450
Total Ordering Cost = 54 X $25 = $ 1.350
Total Cost = 4450 + 1350 = $ 5.800