Tender No: 8/3/1-36/2009

Page 91 Description Unit Quantity Rate Amount


SECTION 1200: GENERAL REQUIREMENTS AND PROVISIONS

12.01 Locate existing services Prov Sum 5000


12.02 Excavate by hand m3 15 45 675
12.03 Shifting and reinstatement of services Prov Sum 10000
12.04 Keeping pavement dry m2 3050 30 91500
12.05 Standing time due to rioting Sum/day 5 Rate only
12.06 Political riot Prov Sum 10000
12.07 Percentage profit % 10000 5 500
12.08 Employment of community liason officer Prov Sum 15000
12.09 Percentage profit % 15000 5 750
12.1 Publication of tender notice Prov Sum 14000
12.11 Percentage profit % 14000 5 700

Carried Forward to summary 148125

Page 92
SECTION 1300: CONTRACT ESTABLISHMENT

13.01 Fixed obligation Sum 1 15300 15300


Value related obligation Sum 1 22950 22950
Time related obligation Month 6 19125 114750

Carried Forward to summary 153000

Page 93
SECTION 1400: HOUSING, OFFICES ETC

14.01 Office furnished Prov Sum 10000


14.03 Cellular cost of engineer Prime. C 6 1500 9000
14.1 Provision for photostat machine Month 6 0
14.11 Completion of survey Prov Sum 7500
14.12 Site supervision Prov Sum 90000

Carried Forward to summary 116500

Page 94
SECTION 1500: ACCOMODATION OF TRAFFIC

15.01 Accomodating traffic km 0.65 8500 5525


15.02 Shaping of temporary deviation km 0.5 8500 Rate only
15.03 Flagmen L.Sum 1 18000
Portable stop and gory sign No 2 2100 4200
Road signs R,… No 10 2100 21000
Road signs TW,...,… No 10 2100 21000
Road signs STW,...,… No 5 2100 10500
Delineators, single No 60 550 33000
Movable baricade No 5 1900 9500
Traffic cones No 50 35 1750
15.05 Temporary deviations m3 25 350 Rate only
15.06 Watering of temporary deviations KL 20 100 Rate only
15.07 Temporary deviations Km pass 10 1000 Rate only
Existing roads used as temporaries Km pass 10 1000 Rate only
15.1 Accomodation of traffic Km 0.65 8500 5525
Overhaul of material m3km 175 5 Rate only

Carried Forward to summary 130000

Page 95
SECTION 1700: CLEARING AND GRUBBING

17.01 Clear and grub where indicated by engineer m2 150 30 4500


17.04 Remove and grub existing hydraulic m2 100 45 4500
17.05 Clearing pipes upto 750mm m3 2 60 Rate only
Clearing pipes exceeding 750mm m3 2 60 Rate only

Carried Forward to summary 9000

Page 96
SECTION 1800: DAY WORK AND PLANT HIRE

18.01 Normal hours of duty: Foreman hour 100 Rate only


Normal hours of duty: Artisan hour 100 Rate only
Normal hours of duty:Team supervisor hour 50 Rate only
Normal hours of duty: Labourer hour 1000 Rate only
18.02 Bulldozer with ripper, 70KW hour 75 Rate only
Bulldozer with ripper, 170KW hour 75 Rate only
Rubber tyred tractor hour 150 Rate only
Self propelled motor grader hour 150 Rate only
Front end loader hour 50 Rate only
Traxcavator hour 50 Rate only
6m3 Tipper truck hour 200 Rate only
9000 Litre water bowser hour 150 Rate only

Carried Forward to summary 0

Page 97
SECTION 2200: PREFABRICATED CULVERTS

22.01 Excavation of 0m upto 1,5m m3 50 45 Rate only


Excavation of 1,5m upto 3m m3 2750 45 123750
Excavation of 3m upto 4,5m m3 1120 50 56000
Extra over for excavation m3 500 30 15000
22.02 Backfilling using excavted material m3 1500 40 60000
Backfilling using extra over items m3 100 40 Rate only
Concrete pipes, 75 D load 1200mm diameter m 10 750 7500
Concrete pipes 75 D load, 1500mm diameter m 480 800 384000
Concrete pipes 100 D load, 1200mm diameter m 10 900 Rate only
Concrete pipes 100 D load, 1500mm diameter m 25 1200 30000
22.05 Culverts 1500mm m 20 2000 40000

Carried Forward 716250

Page 98

Brought Forward 716250

25/19 Mpa concrete m3 5 1500 7500


Class F1 surface finish m2 20 10 200
22.1 Welded steel fabric kg 240 10 2400
22.18 230mm thick brickwork m2 15 400 6000
22.19 Plaster m2 30 50 1500
22.23 Service ducts 200mm m 40 180 7200
Service ducts 110mm m 25 130 3250
22.24 Marker blocks No 10 150 1500
22.25 Overhaul excavated material m3.km 175 5 Rate only

Carried Forward to summary 745800

Page 99
SECTION 2300: CONCRETE KERBING

23.01 Precast concrete kerbing m 1050 150 157500

Carried Forward to summary 157500

Page 100
SECTION 3100: BORROW MATERIAL

31.01 Excess overburden m3 500 45 22500


31.03 Soft material ha 0.5 25000 12500

Carried Forward to summary 35000

Page 101
SECTION 3300: MASS EARTHWORKS

33.01 Compaction m3 225 100 22500


33.03 Extra over intermediate excavations m3 55 100 5500
Extra over hard excavations t 40 150 6000
33.03 Cut to spoil soft excavations m2 3590 30 107700
Cut to spoil intermediate excavations m3 50 50 2500
Cut to spoil hard excavations m3 40 55 2200
33.09 Blading material to the window m2 100 60 6000
33.1 Compaction m3 680 10 6800
Overhaul of material m3.km 13000 5 65000

Carried Forward to summary 224200

Page 102
SECTION 3400: PAVEMENT LAYERS OF GRAVEL MATERIAL

34.01 Compaction of gravel layer m3 1070 190 203300


Compaction of gravel subbase m3 530 200 106000
Compaction of gravel shoulders m3 180 190 34200
Compaction of gravel wearing course m3 140 65 9100
34.02 Extra over intermediate excavations m3 150 90 13500
Extra over hard excavations m3 50 150 7500
Overhaul of material up to 1.0km m3 50 45 2250
Overhaul of material in excess of 1.0km m3.km 6500 5 32500

Carried Forward to summary 408350

Page 103
SECTION 3500: STABILIZATION

35.01 Chemical stabilisation on subbase m3 530 120 63600


35.02 Chemical stabilisation agent, portland cement t 23 650 14950
35.04 Water for curing kl 100 100 Rate only

Carried Forward to summary 78550

Page 104
SECTION 5600: ROAD SIGNS

56.01 Prepaint sign boards not exceeding 2m2 m2 10 1110 11100


Prepaint sign boards exceeding 2m2 m2 10 1200 12000
56.02 Extra over for class II m2 15 1110 16650
Extra over for class III m2 15 1200 18000
56.03 Steel tubing kg 150 10 1500
56.05 Excavation and backfilling m3 10 75 750
56.06 Extra over excavation m3 10 50 500
56.08 Dismantling up to 2m2 No 4 100 400
56.05 Dismantling exceeding to 2m3 No 1 100 100

Carried Forward to summary 61000

Page 105
SECTION 5700: ROAD MARKINGS

57.02 100mm White lines m 500 15 7500


300mm White lines m 10 15 150
100mm Yellow lines m 500 15 7500
300mm Yellow lines m 500 30 Rate only
White lettering and symbol m2 30 60 1800
57.06 Setting out and premarking the lines km 20 2400 48000
57.07 Reestablishing the painting L. Sum 25000
Carried Forward to summary 89950

Page 106
SECTION 7300: CONCRETE PAVING

73.01 Supply and deliver block paving m2 3150 150 472500


Supply bedding sand m2 3150 90 283500
Compact concrete paving m2 3150 10 31500
Supply jointing sand m2 3150 10 31500
73.02 Cast in situ concerete m2 40 85 3400

Carried Forward to summary 822400

Page 93 SUMMARY OF SECTIONS

SECTION DESCRIPTION AMOUNT (Rands)

1200 GENERAL REQUIREMENTS AND PROVISIONS 148125


1300 CONTRACTOR ESTABLISHMENT 153000
1400 HOUSING, OFFICES,ETC 116500
1500 ACCOMODATION OF TRAFFIC 130000
1700 CLEARING AND GRUBBING 130000
1800 DAY WORK AND PLANT HIRE 0
2200 PREFABRICATED CULVERTS 716250
2300 CONCRETE KERBING 157500
3100 BORROW MATERIAL 35000
3300 MASS EARTHWORKS 224200
3400 PAVEMENT LAYERS 408350
3500 STABILIZATION 78550
5600 ROAD SIGNS 61000
5700 ROAD MARKINGS 89950
7300 CONCRETE BLOCK PAVING 822400

SUBTOTAL 3270825
ADD 5% CONTIGIENCI 163541.3
SUBTOTAL 3434366
ADD 14%VAT 480811.3

TOTAL CARRIED FORWARD TO FORM OF OFFER 3915178