Professional Documents
Culture Documents
Project Description: 2.1. Project Location and Design
Project Description: 2.1. Project Location and Design
2. PROJECT DESCRIPTION
2.1. PROJECT LOCATION AND DESIGN
The proposed Project is located in the southwest of the SRR International Airport at Plaine Magnien,
District of Grand Port - Savanne, Figure 2-1.
The proposed route is 4.3 km long and will connect the airport to the M1 motorway through a southern
bypass of Plaine Magnien. In total 3 roundabouts are proposed along the route: to the north and
southwest of the new Holiday Inn Hotel; and to the south of Plaine Magnien (B8, ‘La Barraque Road’).
The junction with the M1 will be in the SE of Mare d’Albert where a new interchange will be provided.
The design speed selected for the New Access Road is 100 km/h, and the design life is 20 years. A
dual carriageway (2 x 2 lanes of 3.65m each) with a central reserve of 5 m is proposed. The
shoulders will be 3.5 m wide (2m paved and 1.5 unpaved). The total cross section will thus be 26.6m.
In the initial 0.6 km section of the Project (between the airport and roundabout near the Holiday Inn
Hotel) a single carriageway (2x1 lanes) already exists (Figure 2-3), connecting the airport and Holiday
Inn Airport Hotel to the Mon Désert Road (B85). In this section the proposed design is to widen the
existing road on the right side (in the airport – Hotel direction). The following 3.7 km of the Project
route (i.e. the section from the roundabout at Holiday Inn Hotel to the M1 Motorway) will be an entirely
new road, which mainly passes through sugarcane plantations. In developing the route, existing
parallel cane tracks will, as far as possible, be maintained so as not to hamper access to the
surrounding land and to preserve access that can be used for material transport during construction.
Figure 2-3: Existing single carriageway road along the first 0.6 km of the Project road.
Left: view from the airport to the south; Right: view from first roundabout towards the north
The new airport access road will be a ‘classified’ road and must be designed such as to fulfill its
functions at all times. The proposed drainage design is initially based on relevant criteria as
established by the WRU and Intensity-Duration-Frequency (IDF) curves provided by the Mauritius
Meteorological Services (MMS). The existing IDF curves, however, do not incorporate more recently
observed trends of climate change and related phenomena such as the noted increased frequency of
say, 25-year rainfall.
In response to these observations, a 25-yr return period was adopted for the design of drainage
structures. Various types of drains will be provided. Lined open channels will be provided locally to
direct the storm flow to cross drainage structures and from there to absorption pits. From there the
runoff will gradually percolate into the permeable underground.
In total, 7 absorption pits are proposed which typically measure 5m x 10m and 3 m deep. The typical
section of an absorption pit as proposed under the Project is shown in
Figure 2-4. The overall stormwater drainage layout is illustrated in Figure 2-5.
Figure 2-4: Absorption pit details, typical layout as proposed under the Project
9
New Airport Access Road
EIA Report February 2015
LED lightning will be provided throughout the Project route in the central reserve, as shown in Figure
2-2.
Preparatory works
Preparation of the contractor’s yard;
Land clearing; removal and temporary storage of topsoil;
Earthworks and temporary storage of soil;
Scarifying of existing roads and other sealed surfaces;
Rerouting of services;
Temporary storage of rubble / spoils.
Construction
Road construction: subgrade preparation and embankment construction;
Pavement construction;
Construction of roadside drains;
Construction of new service utilities networks;
Road furniture, electrical installations;
Landscaping;
Decommissioning of contractor’s yard and site clean-up.
Workforce
The estimated number of people to be employed under the Project is not known at this point in time.
At the tendering stage however, Contractors will be requested to indicate their manpower requirement
needed to complete the works within the prescribed time schedule.
2.5. LANDSCAPING
The New Access Road will be the gateway to Mauritius for any visitor from abroad and as such has
an important function in representing Mauritius as a top destination for high end tourism in the region
and in supporting the Government’s intention to develop Mauritius as an international hub in the
Indian Ocean.
Therefore a landscaping concept will be prepared separately as part of the detailed design to provide
for appealing plantations of high aesthetic value. Space for plantations is available throughout the
central reserve and the embankments as well as in the roundabouts.
7
Note that a PCU crushing plant is located in the immediate vicinity of the Project site