The overall progress of the CA-58 contract is 47% for electric works, 58.4% for RSS civil works, and 42% for ASS works. For electric works, transformers have been erected at RSS and 1 km of cable has been laid. For RSS civil works, 30 equipment foundations and 2 firewalls have been completed along with 20 columns for the first floor. For ASS works, transformers have been installed at 3 stations and GIS at 2 stations out of the total 13 stations.
The overall progress of the CA-58 contract is 47% for electric works, 58.4% for RSS civil works, and 42% for ASS works. For electric works, transformers have been erected at RSS and 1 km of cable has been laid. For RSS civil works, 30 equipment foundations and 2 firewalls have been completed along with 20 columns for the first floor. For ASS works, transformers have been installed at 3 stations and GIS at 2 stations out of the total 13 stations.
The overall progress of the CA-58 contract is 47% for electric works, 58.4% for RSS civil works, and 42% for ASS works. For electric works, transformers have been erected at RSS and 1 km of cable has been laid. For RSS civil works, 30 equipment foundations and 2 firewalls have been completed along with 20 columns for the first floor. For ASS works, transformers have been installed at 3 stations and GIS at 2 stations out of the total 13 stations.
a. Power and Traction transformers erected at RSS, Oil filtration and accessories installation work under progress. b. 1 km 110 kV EHV cable route laid out of 3.25 km cable route.
2. RSS Civil Works: overall progress 58.4%
a. 30 nos Equipment foundations completed out of 44. b. 2 nos firewall completed out of 3. c. 20 Columns out of 27 completed of 1st floor. d. 308 mtr earthing of RSS completed out of total scope 2000 mtr.
3. ASS Works: overall progress 42%
a. 500KVA Transformer installed at 3 stations (Bandongri, M&M and National park) out of 13 stations b. 33 kV GIS installed at 2 stations (Bandongri and National park) out of 13 stations.
*Weightage considered for overall progress: Design=20%, Supply= 20%, Installation=40%,