Professional Documents
Culture Documents
Evpm Ce
Evpm Ce
Evpm Ce
Sandip Chakraborty
Civil Engineering Department
IIEST, Shibpur
9830733143
26th August 2020
Syllabus
1. Concept of engineering project; Types of projects;
characteristics of civil construction project;
Importance of construction project management;
Role of construction project manager; Stakeholders
in construction project; Ethical issues in civil
construction
2. Purpose of Estimating; Quantity Survey; Types of
Estimating – Detailed Estimate, Preliminary
Estimate, Approximate Estimate; Revised
Estimate, Supplementary Estimate, Maintenance
Estimate, Introduction to Rate Analysis of
different items of works of a standard residential
building.
Syllabus
Foundation
Plinth
Superstructure
Components of Buildings
Foundation,
Plinth,
Walls and columns,
Floors,
Lintels and chajjas,
Roof,
Doors and windows,
Stairs and lifts,
Finishing work (plastering and painting),
Building services,
Components of Buildings
Components of Buildings
Components of Buildings
Foundation
Plinth
Walls
Column
Beam
Slab
Staircase
Tie Beam
Tie Beam
Lintel
Lintel and Chajja
Continuous lintel for doors and windows
Damp Proof Course
Mezzanine Floor: An intermediate floor
between two floors above ground level with
area of mezzanine restricted to one-third of the
area of that floor with a minimum height of
2.2m.
Covered Area: Ground area covered by the
building immediately above the plinth level
Carpet Area: The covered area of the usable
rooms at any floor level (excluding the area of
the wall).
Plinth Area: The built up covered area
measured at the floor level of the basement or
of any storey.
Doors
Windows
Utilities of a building
• Electricity supply
• Gas supply
• Water supply
• Sewage and drainage system
• communications services
Introduction to Estimation
Estimate????
39
Measurement form
Item Description or No. Length Breadth Height / Content
no. particulars depth or
quantity
40
Abstract of estimate form
Sl. Description or Quantity Unit Rate Unit of Amount
No. particulars Rs. P. rate Rs. P.
41
Data Required for Preparing Detailed Estimates
• Drawing
• Specifications
• Rates
• Up dated mode of measurement for standard
deductions or additions are also necessary to
determine the correct quantities of work
• Standing circulars for taxes and insurances etc.
are required to fix up rates of those items which
are not in the schedule of rates. 42
Factors to be considered during
preparation of a detailed estimate
• Quality of materials
• Availability of materials
• Transportation of materials
• Location of site
• Local labour charge
43
Preliminary / approximate / rough estimate
• To find out the approximate cost in a
short time.
• It enables the authority to consider the
financial aspect of the scheme.
• Such an estimate is framed after
knowing the rates of similar works and
from practical knowledge in various of
ways for various types of works such as:
© Plinth area or square meter method
© Cubic rate or cubic meter method
© Service unit or unit rate method
© Bay method
© Approximate quantities with bill method
© Cost comparison method
© Costs from materials and labour
Quantity estimate or survey
• This is a complete estimate or list of
quantities for all items of work required to
complete the concerned project.
46
Revised estimate
• A revised estimate is a detailed estimate for
the revised quantities and rates of items of
works originally provided in the estimate
without material deviations of the structural
nature from the design originally approved
for a project.
47
• It is required to be prepared for the following
reasons:
a) When a sanction estimate is likely to exceed
by more that 5%.
b) When the expenditure of work exceeds or
likely to exceed by more than 10 % of the
administrative approval (for more than Rs. 5
lakhs)
c) When there are material deviations from the
original proposal but not due to deviation of
structural nature.
d) When it is found that the sanctioned estimate
is more than the actual requirement. 48
Supplementary estimate
While a work is in progress, some changes or
additional works due to material deviation
of a structural nature from the design
originally approved may be thought necessary
for the development of a project.
An estimate is then prepared to include all
such works, called supplementary estimate.
49
Difference between revised and supplementary estimate
51
• Complete estimate includes the following:
∆ Cost of land
∆ Cost of legal expenses required
between owner and the contractor
∆ Cost of main contract or material,
labour and supervision
∆ Contingency @5% of the work for
extra works
52
∆ Engineering fees
Cost of preparation of plan, design,
estimate and sanction fee
Cost for supervision of works
∆ Permit free for water and electricity during
construction
∆ Miscellaneous (i.e. transportation cost of
owner with his party)
53
Annual maintenance or repair estimate
54
Nomenclature of an item
• There should be an adequate but concise
description of the nature of the item of work,
specially the names of materials, their quantities,
proportions of all materials, workmanship,
operation including all transport, tools and plant
required to complete the work.