Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 14

Standard Procedure For Microwave

Swap Site

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

Huawei Confidential
Standard Procedure For Microwave Swap Site

Revision Declaration
This document is prepared and explained by the Site Business Dept of Global Technical Service D
Specifications or documents related to this document:
Related international specifications or document consistency:
Specifications or documents that are replaced or expire:
Correlation of specifications and documents:

Version Prepared by Reviewed by Approved by Revision Record


V1.0 Initial release

Issue Date: 2009-07-15 Effective Date: 2009-07-15

Huawei Technologies Co., Ltd.


All rights reserved

Page 2
Standard Procedure For Microwave Swap Site
1,Cutover
(1) Cutover services from other vendor's Microwave to Huawei Microwave RT
(2) Test services after cutover successful
(3) Roll Back procedure
Pole
Antenna

ODU and Coupler

Rack GND

IDU DC Power

ACDB DCDB
IF cable
Ground bar
DDF
IDU
DC power cabinet PGND
Battary

Page 3
Standard Procedure For Microwave Swap Site

Tape measure Marking pen Level bar Percussion drill Claw hammer Torque wrench

Socket wrench Adjustable wrench Phillips screwdriver Flat-head screwdriver Heat gun Multimeter

Wire stripper Sharp-nose pliers Diagonal pliers Pliers Crimping pliers Wire cutter

E1 BER tester Feeder punchdown tool Bayonet wrench Paper knife Ladder File

Electric iron Camera Compass inclinometer cleaner punching wire pliers

Allen wrench Lifting rope Lifting hook

HUAWEI Confidential Page4/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover 1.1-A Preparation AB 30 minutes

Procedure
1-A 1-
B
1 Check hardware connection, DDF,E1 cable,ground cable, etc.

2 Make sure the microwave equipment RTN900 is power on.

Record exiting E1 and Ethernet cables connection and make clear labels in
3
both source and sink sites. This is for roll back in case needed.

Note

2 1

Tools
1 2 3
4 5
Materials
1 2
3 4
5 6

HUAWEI Confidential Page5/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover 1.1-B Preparation AB 30 minutes

1-A 1-B Procedure

1 Make sure the microwave equipment RTN900 is power on

2 Can login Equipment with Weblct.

2
3

4
5
Note

3
4
Tools
1 2 3
4 5
Materials
1 2
3 4
5 6
SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover 1.1-C Preparation AB 30 minutes

Procedure

HUAWEI Confidential Page6/14


Check the RSL, it should be normal,Check the alarm, there should be no
1
abnormal alarm except T-ALOS.

4
5
Note

1 The RSL should be consistent with design value.

3
4
Tools
1 2 3
4 5
Materials
1 2
3 4
5 6

HUAWEI Confidential Page7/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover
1.2A E1 Software Loopback AB 30 minutes

Procedure
In the Function Tree, click the tributary board where the loopback is to be
1
performed.
Choose Configuration > PDH Interface in the Function Tree. Then, the PDH
2
Interface page is displayed.
Select the E1 signal to be looped back. Then, double-click Tributary Loopback
3
and select Inloop or Outloop.

4 Click Apply.

5
Fron
Note
t
view 1 E1 inloop indicates that the E1 signal is looped back toward the backplane.

2 E1 inloop indicates that the E1 signal is looped back against the backplane.

Tools

1 2 3

4 5 6

Materials

1 2

3 4

5 6

Page 8
SN Task Description Operator Duration
Standard Installation of OptiX RTN 900
1.2B Test the E1 Services AB 30 minutes

Procedure

1 Perform the hardware loopback of the E1 signal on the DDF.

Click the tributary board to be tested, and choose Configuration > PRBS Test in
2
the Function Tree. Then, the PRBS Test page is displayed.
Select the E1 signal to be looped back. Double-click Direction and select
3
Tributary. Then, set the test duration to 15 minutes.

4 Click Start to Test to start the PRBS test.

Note

The test directions of the PRBS test function as follows. In the tributary direction,
the bit errors from the local DDF to the equipment can be tested. When the
1
remote E1 signal is looped back and the cross direction is selected at the local
end, the bit errors from the radio link to the local tributary board can be tested.

Tools

1 2 3

4 5 6

Materials

1 2

3 4

5 6

Page 9
SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover
1.3 Change jumpers AB 30 minutes
Procedure
Cut over E1 cable connection at both source and sink sites. E1 cut over must be
1
done one by one, and confirm with NOC the current E1 is working properly.
2 Make new jumpers between RTN900 equipment and BTS
After all E1 and Ethernet services cut over are completed, the service is up
3
again. Record the time and report to Huawei and Operator.
4
5

Note

Tools
1 Punching wire pliers 2 Marking pen 3 Diagonal pliers
4 Paper knife 5 6
Materials

1 2
3 4
5 6

HUAWEI Confidential Page10/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover
1.4-A Check Microwave alarm AB 50 minutes
Procedure
Check alarm of RTN900, the T-ALOS alarm should be
1
disappeared and no other abnormal alarm any more.
2

4
5

Note

Tools
1 2 3
4 5 6

Materials

1 2
3 4
5 6

HUAWEI Confidential Page11/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover
1.4-B Serivce test&observe AB 50 minutes

Procedure

1 Observe the service at least 30 mintues.

Note

1 if the site has worse problem after cutover,use 《Fall


Back Procedure》

Tools

1 Cell phone 2 3

4 5 6

Materials

1 2

3 4

5 6

HUAWEI Confidential Page12/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover Check site
1.5 AB 10 minutes
cleanliness
Procedure

1 Collect the tools and excessive cables on site

2 Clear up the equipment room and the outdoors.

Note

1 No packing boxes or boards are placed at random on the installation field.

2 No cable ties or other sundries are left on the floor or in the cabinets.

Tools

1 2 3

4 5 6

Materials

1 2

3 4

5 6

HUAWEI Confidential Page13/14


SN Task Description Operator Duration
Standard Procedure For RTN900 Cutover
1.6 Roll Back Procedure AB 30 minutes

Procedure
If the service down time exceeded 4 hours and the swap is not completed, roll
1 back has to be performed. The roll back must be confirmed with Huawei and
Operator in advance.
2 Recover E1 and Ethernet cables as previous connection.

3 Check E1 and Ethernet service.

Note

1 Record the time and report to Huawei and Operator.