ITEM WISE BREAKDOWN FOR ANY QUANTITY

Cement Sand Crush Bricks Steel Tiles Mud Surkhi Polthyne Bitumen Skilled Unskilled
S.NO Discripation of items Qty
(bags) (cft) (cft) (No) (ton) (No) (cft) (kg) (sheet) sft (kg) Labor Labor

1 P C C (1:4:8) 100 9.00 47 95 1 3

2 P C C (1:2:4) 100 17.0 44 88 1 3

3 Bricks works(1:4CSM) 100 5.0 25 1360 1 3

4 Bricks works(1:3CSM) 100 6.0 23 0 1 3

5 Bricks works(1:6CSM) 100 3.5 26 0 1 3

6 Steel 1/2" dia 100 0.030 1 3

7 Steel 3/8" dia 100 0.017 1 3

8 Brick Tiles(10"X5"X1.25") 100 288

9 Bitumens 10/20 Grade 100 9

10 Polthyene Sheet 100Gauge 100 100

11 DPC (1:2:4) 100 2.74 44 88

12 Mud 100 0.33


Cement Plaster 1/2"
13 thick(1:3csm) 100 1.3 5 1 2
Cement Plaster 1/2"
14 thick(1:6 csm) 100 1.3 5 1 2

15 Coping (1:3:6) 100 1.3 5 92.4 1 2

16 Floor PCC1:2:4 100 1.3 5 92.4 1 2

17 Struck pointing (1:3 csm) 100 1.3 5 66.4

18 1/2" Skirting (1:2 csm) 100