PROJECT

DAILY PROGRESS REPORT LOCATION VANAGARAM


DATE 11-09-2020
PLANNED Vs ACTUAL PROGRESS FOR THE DAY(10-Sept-2020)

Planned Actual Plan Vs Actual Qty. for the day


SI.NO ACTIVITY UOM REASON FOR SHORTFALL
Manpower Manpower PLAN ACTUAL % ACH SHORTFALL

414- Lintel Concrete & Loft


1 2 set 1 m³ 0.94 0.94 100% 0
Concrete

2 4th Floor-Block Work 4 Set 2 Sqft 415 215.98 52% -199.02 used 2 set

East Side outer Plastering


3 ,Sunshade plastering &208 & 7 set 4 Sqft 215 194.75 91% -20.25 Used 4 sets
209 Loft & Ledge Wall Plastering

Door Frame Fixing and Sunken


4 2 0 N0s 10 0 0% -10 Labour Shortage
Filling

5 215 Gypsum Wall Plastering 4 3 sqft 107 90.42 85% -16.58 jambs area

306 Guide Point Fixing & Gypsum


6 4 4 sqft 326 317.87 98% -8.13 Final Finishing
Plastering

7 301 Gypsum Plastering 2 2 Sqft 163 89.475 55% -73.525 Jambs area , corners

8 209 Gypsum Plastering 4 3 Sqft 302 278.58 92% -23.42 Final Finishing

72 frame are
9 Door Frame Making 2 3 Nos NA NA
prepared

105 Ceiling Putty Work & Wall


10 3 3 Sqft 3356 3533 105% 177
Primer(90%)

4th Floor Lintel Loft Shuttering


11 2 0 sqft 140 0 0% -140 Labour Shortage
sunshade Shuttering

LMR Slab Rebar work & OHT Wall


12 4 4 Sqft 270 279.94 104% 9.94
Shuttering

315 -Kictchen wall chasing & 310


13 2 2 Executed As planned
wall chasing

14 315&302-Drain Pipe Line 2 2 Executed As planned

1st Floor Brass Point Height Level


15 1 1 Executed As planned
Checking-Pressure test