Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Transfer and Development

Lengths of Concentrically
Prestressed Concrete

J. R. Martí-Vargas, Ph.D.
Civil Engineer
Department of Construction
Engineering and Civil Engineering
Projects
Polytechnic University of Valencia
Valencia, Spain
M. A. Fernández-Prada, Ph.D.
Civil Engineer
Department of Construction
Engineering and Civil Engineering
Projects
Polytechnic University of Valencia
C. A. Arbeláez, Ph.D. Valencia, Spain
Civil Engineer
Department of Construction
Engineering and Civil Engineering
Projects
Polytechnic University of Valencia
Valencia, Spain

P. Serna-Ros, Ph.D.
Civil Engineer
Department of Construction
Engineering and Civil Engineering P. F. Miguel-Sosa, Ph.D.
Projects Civil Engineer
Polytechnic University of Valencia Department of Construction
Valencia, Spain Engineering and Civil Engineering
Projects
Polytechnic University of Valencia
Valencia, Spain

74 PCI JOURNAL
At nominal strength of member

fps
Stress in the prestressing strand

fse

Prestress
only

Transfer length Flexural bond length

Development length
Fig. 1. Idealized relationship between strand prestressing stress and development length.

T
An experimental investigation to develop a test to he behavior of pretensioned concrete members depends
characterize the bond between prestressing strand on the bonding mechanism between the strand and the
and concrete has been carried out at the Polytechnic surrounding concrete; strand prestressing forces are main-
University of Valencia in Spain. The proposed test tained solely by this mechanism. Two fundamental requirements
must be met to ensure bond integrity of prestressed concrete
determines the transfer and development lengths by
members: the transfer of prestressing forces at strand release and
measuring the force in the strand in a series of test the ability of the strand to develop adequate stress forces when
specimens with different embedment lengths. The subjected to overload conditions.
test sequentially reproduces the transfer of prestress Section 12.9 of ACI 318-05 defines the following lengths
in a specimen and simulates service load through related to strand bond (Fig. 1):1
a pull-out test on the same specimen. With this • Transfer length: the distance over which the strand
should be bonded to the concrete to develop the effec-
technique, the Hoyer Effect is produced prior to the
tive prestress in the prestressing steel fse.
pull-out phase of testing. An experimental program • Flexural bond length: the additional length over which the
determined the applicability of the test method and strand should be bonded so that a stress in the prestressing
the feasibility of a standardized test for quality con- steel at nominal strength of the member fps may develop.
trol of prestressing strand bonding. Transfer- and • Development length: the sum of the transfer length
development-length tests were conducted on seven- and the flexural bond length.
The development length is represented by the following
wire prestressing strand using 12 different concretes.
expression:1
Results show that the test is valid and practical. Test
data indicate that ACI 318 equations are conserva-  f  f −f 
ps se 
tive. Details of testing equipment and procedures ld =  se  db +  d
  b (1)
 3000   1000 
are also presented in this paper.

September–October 2006 75
where: Strand-concrete bond performance is lengths of prestressing strands:16
ld = development length in tension of essential for pretensioned concrete ap- 1. Measurement of the longitudinal
pretensioned strand plications. ACI 318-05 states that for concrete strains in the surface of
db = nominal diameter of prestress- bond applications, quality assurance a specimen.
ing strand procedures should be used to confirm 2. Measurement of the strand-end
fse = effective stress in prestressing that the strand is capable of adequate slip of a prestressed member.
steel (after allowance for all prestress bond.1 Neither ASTM A416 nor ACI These two test methods are the basis
losses) 318-05,1,12 however, include minimum of different standards to determine
fps = stress in prestressing steel at nom- requirements for bond performance the transfer length of prestressing
inal flexural strength of the member of prestressing strands, and neither do strands.17,18 These standards, however,
The first term in Eq. (1) represents other standards.13 In spite of the large do not include the following procedures
the transfer length of the strand, and number of experimental studies con- to determine development length:
the second term, the flexural bond ducted to date, there is no consensus on 3. Breaking beams with concen-
length. This expression is based on a standard test method for bond qual- trated loads at various distances
test results for transfer length and flex- ity.14 According to Rose and Russell,15 from the supports.
ural bond length.2,3 The ACI equation a standard test for the strand bond in 4. Pull-out tests.
for ld first appeared in ACI 318-63 and pretensioned concrete would benefit These four test methods are dis-
has remained unchanged through ACI all parties involved in the precast/pre- cussed in this paper.
318-05.1,4 stressed concrete industry: manufactur-
The mechanical bond of steel pre- ers, producers, designers, builders, and Measurement of Longitudinal
stressing strand to concrete is a function owners. Concrete Strain
of numerous factors listed by Comité
Euro-International du Béton (CEB).5 Electrical or mechanical strain
Analysis of the influence of these fac- gauges are attached along the sides of
tors was the objective of many past and Objectives and Scope a pretensioned concrete member prior
recent studies.6–8 The impact of high- of the Research to release of strand tension. When the
strength concrete in the fabrication and prestressing force is transferred, the
construction of prestressed concrete compressive strains in the concrete are
and the development of new (higher The purpose of this study is to de- registered at various distances from the
tensile strength, lower relaxation, and velop a test method for measuring the ends of the member. Transfer length
larger diameter) steel strands, and transfer and development lengths of is determined directly from the data
new materials for prestressing strands prestressing strand. The most impor- curve (concrete strains versus distance
(epoxy-coated steel strands and fiber- tant condition for the test was that the from the end of a member) by the
reinforced polymers) have been the strand release and the pull-out opera- slope-intercept method or the 95% av-
subjects of many research programs. tions be performed sequentially on the erage maximum strain (AMS) method
Significant experimental results were same specimen. In this way, the devel- (Fig. 2).16,19,20 Some researchers apply
obtained by Cousins et al.,9 who ob- opment length is determined for speci- a smooth fit to the data curve,21 while
served transfer and development lengths mens that have been subject to prestress others use 100% of the average maxi-
of uncoated 0.5-in.-diameter (13 mm) transfer with the same procedures used mum strain.22
seven-wire strand much greater than in the construction of precast, pre-
those calculated by ACI 318 equations. stressed concrete in practice. In deter- Measurement of Strand-End Slip
In response to these test results, the Fed- mining the transfer and development
eral Highway Administration (FHWA) lengths of seven-wire strand, the study Based on Guyon’s theory, this meth-
issued a memorandum that required the included 12 different concretes in the od uses the amount of the strand-end
ACI development length expression experimental program to validate the slip δ during the release of tension on
to be multiplied by a factor of 1.6 and test method. the casting bed.23 Guyon proposed an
disallowed the use of 0.6-in.-diameter expression where the transfer length
(15 mm) strand in pretensioned concrete lt is linearly proportional to δ and in-
for highways bridge applications.10 versely proportional to the initial strand
The FHWA memorandum generated Experimental strain εsi.
subsequent research to study bond of Determination δ
pretensioned strand and to establish of Transfer and
lt = α (2)
ε si
design recommendations for transfer
and development lengths. Results from Development Length
these research projects indicated wide The coefficient α represents the
variations in the measured transfer and Various researchers use the follow- shape of the bond stress distribution
development lengths; a review of these ing two methods to experimentally de- along the transfer length and is typi-
studies is presented by Buckner.11 termine the transfer and development cally a value between 2 and 3. Several

76 PCI JOURNAL
been conducted with this method.26,27
The influence of the embedment length
on the maximum and average values of
Transfer Transfer
length length the bond stress are documented.14
The Moustafa pull-out test uses a
concrete block and a number of unten-
95% Average sioned prestressing strand samples with
maximum strain long embedment lengths.28 In this test,
the strands are individually pulled out.
This test has been used by researchers
to correlate the results of the pull-out
force of prestressing strand with the
results of transfer and development
Specimen length
lengths obtained in beams.6,15,25 Pull-
out tests with tensioned prestressing
strands were conducted to simulate an-
Fig. 2. Idealized relationship between concrete strain and specimen length.
chorage bond behavior,29 and with the
exception of work done by Mahmoud
et al.,22 these tests do not reproduce the
researchers have proposed different the beam will exhibit bond failure with sig- transverse expansion (Hoyer Effect30)
values for α based on experimental re- nificant strand slip. The development length of the prestressing strand.
sults and theoretical studies.24 of the prestressing strand is determined as
the embedment length at which flexural Push-In Tests
Beam Breakage by Concentrated crushing without bond failure occurs; this
Loading method has been used in other research.21,25 The influence of prestressing strand
expansion can be analyzed by means of
After strand release, a series of preten- Pull-Out Tests a push-in test as follows (Fig. 3):
sioned beams are tested in a three-point • A strand is pretensioned be-
or four-point flexural test. The variable Results of pull-out tests on specimens tween two plates (A and B).
in this beam series is the length from the with different embedment lengths can be • A concrete specimen is cast
end of the beam to the point of maximum used to measure the tensile force reached around the strand near the third
moment. If the embedment length tested by the prestressing strand in order to de- plate (C).
is greater than the required development termine the development length. Mah- • The prestressing force is re-
length, the beam will reach the flexural moud et al. provide a concrete specimen leased at plate A, originating
crushing load without exhibiting bond configuration for this method:22 a prism movement of the strand toward
failure. If the embedment length tested is specimen comprising two concrete parts plate B and creating bond
less than the required development length, with a concentric strand, each connected stresses because the concrete is
by a hollow jack and a hollow load cell. fixed at plate C.
After release, force is gradually applied The push-in technique has been used
with an internal hollow jack to separate by researchers to simulate bond behav-
A the two concrete parts. ior along the transfer length.29,32 For
greater control during the strand stress,
a testing frame with longer free strand
Strand
lengths was patterned by Rose and
Test Methods to Study Russell.15 A simulation of the transfer
Concrete
Basic Bond Properties length and the flexural bond length is
simultaneously performed in the test
proposed by Cousin et al.,33 wherein
C Following are two testing techniques a hydraulic actuator at the reaction
often used to study the basic bond prop- plate C moves the concrete specimen
erties of prestressing strand:14 toward plate A (Fig. 3). Strand stress
• Pull-out tests. on the top side (toward plate A) of
B • Push-in tests. the concrete specimen will decrease
(push in) and the strand stress on the
Pull-Out Tests bottom side (at plate C) will increase
Fig. 3. The setup of plates A, B, and C (pull out). Sophisticated measurement
shows a push-in test based on Keuning Several experimental studies of un- procedures that do not disturb the bond
et al.31 tensioned prestressing strand have phenomenon (photoelasticity or the ul-

September–October 2006 77
AMA
Strand
Embedment length system
Adjustable strand
anchorage
Anchorage

Hollow load cell


Hydraulic Support separator
Frame Concrete Sleeve
actuator
specimen

D A C B
Fig. 4. Design of anchorage-measurement-access (AMA) test equipment setup.

trasonic waves34,35) have not yet been • The length between frame plates to prevent the confining influ-
sufficiently developed. A and C allows measurement ence of plate C, measure the
of the transfer and development force in the strand by means of
lengths of prestressing strand a hollow-load cell, and increase
in addition to providing data on the strand stress at plate B with a
Proposed Test basic strand bond properties. pull-out operation.
• Plates C and B, the two separa-
A test to measure the transfer and de- tors between these plates, and Test Procedure
velopment lengths of prestressing strand the sleeve on the bottom end of
has been developed.36 Figure 4 shows the strand specimen are de- The test procedure for a specimen is
the design of this test (called ECADA, signed to simulate the sectional as follows:
the Spanish acronym for “Ensayo para stiffness of the specimen during A. Preparation stage
Caracterizar la Adherencia mediante the transfer of the prestress- 1. Strand is placed through the
Destesado y Arrancamiento,” which ing force when the specimen holes between plates D and B.
translates to “Test to Characterize the embedment length is equal to or 2. Anchorage devices are put into
Bond by Release and Pull Out” in English). greater than the transfer length. place, and a hydraulic actuator is
The test equipment has been de- This test assembly is called the placed at plate A.
signed to introduce some variations anchorage measurement access 3. The strand is tensioned between
from the Keuning test (Fig. 3):31 (AMA) system and is designed plates D and B using the hydrau-
lic actuator to pull the anchorage
devices separating plate D from
plate A.
4. Adjustable strand anchor-
age is engaged until it makes
contact with the plate D. The
initial force in the strand PI is
anchored. Then, the hydraulic
actuator is unloaded and stress is
relieved (Fig. 5).
5. Concrete is mixed and placed
into the prepared form in the
frame near plate C and consoli-
dated. After concrete placement,
the specimen is cured to achieve
the desired concrete properties
for testing.
B. Testing stage
B1. Prestress transfer phase
1. The hydraulic actuator is placed
Fig. 5. Adjustable prestressing strand anchorage. at the frame plate A and is

78 PCI JOURNAL
Fig. 6. Pull-out phase of testing.

loaded to recover the force P0 pull-out operation. Interpretation of Specimen Test


(force in the strand just before The force in the strand is recorded
release) at the adjustable strand during all test stages (tensioning, re- Figure 7 shows the force in the strand
anchorage at plate A. lease, and pull-out) by a hollow-load and the force exerted by the hydraulic
2. The prestressing force P0 is cell placed between plate B and the an- actuator versus time. The represented
released at plate D by means of chorage device at plate B. A pressure force in the strand P0 corresponds to
the hydraulic actuator. At this sensor controls the force exerted by the the variation registered at the onset of
moment, the transfer of the pre- hydraulic actuator. The instrumentation the testing. Two possible test results
stressing force to the concrete is used in the test is simple and reusable. are presented depending on the speci-
complete. The concrete speci- To prevent interference with the bond men embedment length:
men is supported at the reaction phenomenon, an internal measuring • If the specimen embedment
frame plate C. device was not used in the specimens. length is equal to or greater than
3. Stabilization period. If the AMA system stiffness and the the transfer length, after the
B2. Pull-out phase sectional stiffness of the specimen are stabilization period, the force in
1. The hydraulic actuator is posi- equal, the value of the measured force the strand at the AMA system
tioned at the frame plate C. in the strand at end B (after release) is shows a drop ΔP equal to ΔPest
2. Strand stress is increased using a measure of the strand force inside (Fig. 7). This drop is due to
the hydraulic actuator to pull the concrete specimen. System com- compatibility of strains between
the anchorage device to separate ponents are manipulated so the AMA concrete and strand. The force in
plate B from plate C (Fig. 6). system stiffness matches the specimen the strand after the stabilization
Using the same specimen, the sectional stiffness. From the charac- period PT (prestressing force
ECADA test sequentially reproduces teristics of the AMA system and those transferred [PT = P0 - ΔP] to the
the transfer of the prestress (push-in) of the specimens, one may obtain the concrete) will be the effective
and anchorage (pull-out) forces in the theoretical estimation of loss of force prestressing force after elastic
strand in the same manner as in-service ΔPest registered in the strand during shortening loss (PE = P0 - ΔPest).
pretensioned concrete members (re- the transfer of prestress for specimen • If the specimen embedment length
lease and overloading). In this way, the embedment lengths equal to or greater is less than the transfer length, the
Hoyer Effect is reproduced prior to the than the transfer length.36 force in the strand at the AMA

September–October 2006 79
ƒP

ƒP

ƒPest

Fig. 7. Specimen test results show strand force and hydraulic actuator force versus time: a prestressed concrete specimen where
embedment length > transfer length and a specimen with embedment length < transfer length.

80 PCI JOURNAL
system shows a drop ΔP greater Thus, the development length will cor- transfer and development lengths will
than ΔPest after the stabilization respond to the lesser embedment length depend on the sequences of lengths of
period (Fig. 7). The prestressing for which PD is reached without strand the specimens tested.
force transferred to the concrete slip at the free end of the specimen. In
PT will be less than PE. light of this, a displacement transducer
After the stabilization period, if the is used as additional instrumentation at
transfer of prestress force is complete the free end of the specimen during the Experimental Program
(PT ≈ PE), the force in the strand is in- pull-out process.
creased by the pull-out operation. The An experimental program to verify
maximum force reached in the strand Interpretation of a Complete Test the feasibility of the ECADA method
PR will depend on the specimen em- for determining the transfer and de-
bedment length. Related to the nominal With the ECADA method, the trans- velopment lengths of prestressing
development force PD, the following fer and development lengths are deter- strand was conducted. Twelve differ-
conditions are noted: mined by testing a series of specimens ent concretes were tested with a range
• If the specimen embedment with different embedment lengths. The of water-cement ratios (w/c) of 0.3 to
length is less than the devel- transfer length will be the lesser em- 0.5, cement quantities C of 590 lb/yd3
opment length, PD cannot be bedment length of the test specimens to 843 lb/yd3 (350 kg/m3 to 500 kg/m3),
reached in the strand (PR < PD). where the effective prestressing force and compressive strengths at time of
• If the specimen embedment PE in the strand is reached after the testing f ʹci ranging from 3481 psi to
length is equal to or greater than stabilization period. The development 7977 psi (24 MPa to 55 MPa).
the development length, PD is length will correspond to the lesser em- The concrete components are CEM
reached in the strand during the bedment length of the test specimens in I 52.5 R type cement,37 crushed lime-
pull-out operation. which the nominal development force stone aggregate, washed rolled lime-
In addition to the definition of the PD in the strand is reached in the pull- stone sand, and ISOCRON FM-211
development length in ACI,1 Buck- out operation and in the absence of high-range water-reducing admixture.
ner indicates that the stress fps must be strand slip at the free end of the speci- Table 1 shows the different concretes
developed without strand-end slip.11 men. The resulting determination of the tested. The prestressing strand is a

Table 1. Test Program


Tested Embedment Lengths, in.
f ciʹ
Cement C (lb/yd3) w/c
(psi)
Series A Series B

0.30 7977 2.0, 5.9, 9.8, 13.8, 17.7, 21.7 3.9, 7.9, 11.8, 15.7, 19.7, 23.6
843 0.35 6817 13.8, 15.7, 17.7, 19.7, 21.7, 23.6
0.40 4496 13.8, 17.7, 21.7, 23.6, 25.6, 29.5 19.7, 23.6, 27.6, 31.5, 35.4, 39.4
0.35 6817 13.8, 17.7, 21.7, 25.6, 29.5, 33.5 15.7, 19.7, 23.6, 27.6, 31.5, 35.4
758
0.40 5221 13.8, 17.7, 21.7, 25.6, 29.5, 33.5 15.7, 19.7, 23.6, 27.6, 31.5, 35.4
0.35 6526 13.8, 17.7, 21.7, 25.6, 29.5, 33.5 15.7, 19.7, 23.6, 27.6, 31.5, 35.4
0.40 5511 9.8, 15.7, 21.7, 27.6, 33.5, 53.1 13.8, 15.7, 17.7, 19.7, 21.7, 23.6
674
0.45 4061 17.7, 19.7, 21.7, 23.6, 25.6, 27.6
0.50 3481 19.7, 23.6, 27.6, 31.5, 35.4, 39.4 21.7, 25.6, 29.5, 33.5, 37.4, 41.3
0.40 6672 17.7, 19.7, 21.7, 23.6, 25.6, 27.6
590 0.45 5366 17.7, 19.7, 21.7, 23.6, 25.6, 27.6
0.50 4061 13.8, 17.7, 21.7, 25.6, 29.5, 33.5 15.7, 19.7, 23.6, 27.6, 31.5, 35.4
Additional series
C: 13.8, 31.5, 37.4, 53.1
843 0.30 7977 D: 11.8, 13.8, 15.7, 17.7, 19.7, 21.7
E: 15.7, 15.7, 17.7, 17.7
F: 17.7, 17.7, 19.7, 39.4

Notes: 1 lb/yd3 = 0.5932 kg/m3; 1 psi = 6.895 kPa; 1 in. = 25.4 mm.

September–October 2006 81
low-relaxation, seven-wire strand as For each specimen, the release and the effective prestressing force after
specified in UNE 36094:97 Y 1860 S7 pull-out operations of the strand with elastic shortening loss PE. In contrast,
13.0,13 with diameter of 0.5 in. (13 mm) the ECADA test method were sequen- all the test specimens with embedment
and a guaranteed ultimate strength of tially performed. Strand release oc- length less than 15.7 in. (400 mm) pre-
270 ksi (1860 MPa). curred 24 hours after concrete place- sented values of PT less than PE. The
The concrete specimens are 4 in. × 4 ment, and the pull-out operation took test specimens with embedment lengths
in. (100 mm × 100 mm) in cross section place subsequent to the stabilization equal to 15.7 in. (400 mm) present data
and are prestressed with a concentri- period, typically two hours after re- that border on values for complete
cally located single strand at a prestress lease. The nominal force to attain PD in transfer of prestress. Therefore, for the
level of 75% of the ultimate tensile the strand was established at 35.6 kip embedment lengths tested, it may be
strength. All specimens were subjected (158 kN), corresponding to 0.1% of the concluded that the transfer length de-
to the same concrete consolidation and nominal yield strength of strand.13 termined by the ECADA test method is
curing conditions. The release and pull- 17.7 in. (450 mm).
out processes were gradual. Figure 9 shows the maximum force
For each concrete type, the transfer reached in the strand without strand
and development lengths are deter- Test Results and slip at the free end of the specimen dur-
mined from a series of 6 or 12 speci- Analysis ing the pull-out operation. Data in Fig.
mens. Table 1 lists the embedment 9 show that all test specimens that at-
lengths that were necessary to deter- tained the effective prestressing force
mine the transfer and development Figure 8 shows the prestressing PE present values of PR greater than
lengths in each concrete type. Addi- force transferred to the concrete PT ver- PE. Specimens of embedment length
tional tests on the C 843 (w/c = 0.3) sus the embedment length for the C 843 equal to or greater than 23.6 in. (600
concrete had a double objective: to ver- (w/c = 0.3) concrete. Test specimens mm) present values of force PR greater
ify the operation of the designed AMA with embedment lengths equal to or than the nominal force to develop PD
system and to verify the applicability greater than 17.7 in. (450 mm) present (35.6 kip [158 kN]). Breakage occurred
and effectiveness of the test method. identical values of PT, with PT equal to in the anchorage device without strand

45 200 45 200
Development length Development length
40 180 40 180

35 160 35 160

140 140
30 30
Force (kip)

Force (kip)

120 120
25 25
(kN)

(kN)
100 100
20 Transfer length 20
80 80
Transfer length
15 15
60 60
10 10
40 40
Cement 590 lb/yd 3 Cement 674 lb/yd3
5 w/c 0,45 20 5 w/c 0,35 20

0 0 0 0
0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40
Embedment length (in.) Embedment length (in.)

45 200 45 200
Development length Development length
40 180 40 180

35 160 35 160

140 140
30 30
Force (kip)

Force (kip)

120 120
25 25
(kN)
(kN)

100 100
20 20
80 80
15 Transfer length 15 Transfer length
60 60
10 10
40 40
Cement 758 lb/yd3 Cement 843 lb/yd3
5 w/c 0,40 20 5 w/c 0,35 20

0 0 0 0
0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40
Embedment length (in.) Embedment length (in.)

P0 PT PR

Fig.10. Test results of prestressing force versus embedment length for various concretes. Note: 1 in. = 25.4 mm.

82 PCI JOURNAL
slip at the free end of the specimen. 50 220
With the embedment lengths tested, it 45 200
may be concluded that the development

Force in the strand (kip)


40 180
length determined by the ECADA test 160
35
method is 23.6 in. (600 mm). 140
30
The recorded prestressing force 120
25

(kN)
transferred and the force developed 100
for the different embedment lengths 20
80
(Fig. 8 and 9) indicate a similar rela- 15
60
tionship to that of the idealized dia- 10 40
gram represented in Fig. 1 but with a 5 20
slight discontinuity at the point of slope 0 0
change. This result agrees with data re- 0 5 10 15 20 25 30 35 40 45 50 55
ported by Mahmoud et al.22 Embedment length (in.)
From the results obtained in the se- Series A
Series E
Series B
Series F
Series C
Average P0
Series D
Calculated value PE
ries of six specimens made with C 843
(w/c = 0.3), it is concluded that the test Fig. 8. Results of prestressing force transferred versus embedment length for concrete
is systematic and reliable. For the other C 843 (w/c = 0.3). Note: 1 in. = 25.4 mm.
concretes, a series of 6 or 12 specimens
with different embedment lengths were
tested under the same conditions as
concrete C 843 (w/c = 0.3). Results are
shown in Fig. 10.
Figures 11 and 12 show results for
the transfer and development lengths,
respectively, for all tested concretes
versus the compressive strength of
concrete at the time of testing. A de-
crease in the transfer and development
lengths with an increase of compres-
sive strength of concrete can be ob-
served. Results for lengths are less than
those of ACI 318-051 (where fse is ap-
plied to the corresponding strand stress
for the average force PE for all tested
concretes and where fps corresponds to
strand force PD). For transfer lengths, Fig. 9. Results of maximum prestressing strand force reached without free-end slip
test results are between 50% and 80% versus embedment length for concrete C 843 (w/c = 0.3). Note: 1 in. = 25.4 mm.
of those calculated by ACI 318-05
equations.1 For development length,
test results are between 45% and 65%
of those calculated by ACI 318-05
equations.1
For the materials used and the estab-
lished test parameters, good correlation
to experimental results is shown in the
following expressions:

lt = 29.85 - 0.0016 f ʹci (3)

ld = 35.08- 0.0014 f ʹci (4)

where:
lt = transfer length (in.)
ld = development length (in.)
f ʹci = compressive strength of
concrete at time of testing (psi)
The application feasibility of the Fig. 11. Transfer length versus concrete compressive strength. Note: 1 psi = 6.895 kPa.

September–October 2006 83
The test would be limited to
checking whether the effective
prestressing force and/or the
nominal force to develop in the
strand are achieved.
• To determine the effects of
manufacturing procedures on
bond features of a prestressing
strand.

Acknowledgments

The contents of this paper are part of


the research programs being carried out
Fig. 12. Development length versus concrete compressive strength. by the Concrete Technology and Sci-
ence Institute of the Polytechnic Uni-
versity of Valencia. The authors grate-
ECADA test method for the determi- 7977 psi (24 MPa to 55 MPa) at fully acknowledge the collaboration of
nation of the transfer and development the time of testing, the transfer the companies PREVALESA and ISO-
length of prestressing strands has been length results are between 50% CRON. Financial support provided by
verified. Moreover, studies on basic and 80% of those calculated by IMPIVA (Project IMTEIE/2000/85),
bond properties of prestressing strand ACI 318-05 equations, and the the Ministry of Education and Culture
can be made using this test, and the test development lengths are (Project MAT2000-0346-P4-03), the
test can be applied to any type of pre- between 45% and 65% of those Ministry of Science and Technology,
stressing tendons and wires. Therefore, calculated by ACI 318-05 equa- and FEDER funds (Project MAT2003-
the proposed test is valid as a basis for tions. 07157) made it possible to conduct this
standardization of bond quality in the • Expressions to predict the research. The authors also express their
pretensioning industry. transfer and development lengths gratitude to the technical staff of the
from concrete compressive Concrete Structures Laboratory at the
strength (at time of testing and Polytechnic University of Valencia for
for test conditions) are presented. their assistance in the preparation and
Conclusions testing of the specimens.

Based on the results of this research,


the following conclusions can be made: Recommendations References
• A valid test method for measur-
ing the transfer and development The proposed test method can be 1. ACI Committee 318. 2005. Building
lengths of prestressing strands is standardized for different purposes: Code Requirements for Structural Con-
proposed. • For quality control of prestress- crete (ACI 318-05) and Commentary
• Sequential testing operations on ing strand: Under standard (ACI 318R-05). Farmington Hills, MI:
the same specimen are repre- conditions, the transfer and ACI.
sentative of procedures used development lengths can be 2. Kaar, P. H., R. W. LaFraugh, and
in actual precast/prestressed determined. Standard conditions M. A. Mass. 1963. Influence of Con-
construction. must include concrete materials crete Strength on Strand Transfer
• The test is systematic and reliable. specifications, concrete dosage, Length. PCI Journal, Vol. 8, No. 5
• The instrumentation used in the and methodology for making (September–October): pp. 47–67.
test is simple and reusable. Inter- specimens. 3. Hanson, N., and P. Kaar. 1959. Flexural
nal devices that might distort the • To evaluate the bond quality of Bond Test of Pretensioned Prestressed
bond phenomenon are not used. a prestressing strand in construc- Beams. ACI Journal, Vol. 30, No. 7
• An increase in concrete com- tion site conditions: The mate- (January): pp. 783–802.
pressive strength at the time of rial characteristics (prestressing 4. ACI Committee 318. 1963. Building
testing results in a decrease of strand and concrete) must be Code Requirements for Reinforced
strand transfer and development taken into consideration. Concrete (ACI 318-63). Detroit, MI:
lengths. • As an acceptance-rejection ACI.
• For concretes with compres- test of a prestressing strand in 5. Comité Euro-International du Béton
sive strengths from 3481 psi to specific working conditions: (CEB). 1987. Anchorage Zones of Pre-

84 PCI JOURNAL
stressed Concrete Members. State-of- 16. Thorsen, N., 1956. Use of Large Ten- 1990. Pull-out Bond Tests of Epoxy-
the-Art Report. Bulletin No. 181. Swit- dons in Pretensioned Concrete. ACI coated Prestressing Strand. Journal of
zerland: CEB. Journal (February): pp. 649–659. Structural Engineering, Vol. 116, No.
6. Shing, P. B., D. E. Cooke, D. M. Fran- 17. Réunion Internationale des Labo- 8 (August): pp. 2236–2252.
gopol, M. A. Leonard, M. L. McMul- ratoires et Experts des Matériaux 28. Moustafa, S. 1974. Pull-out Strength
len, and W. Hutter. 2000. Strand De- (RILEM). 1979. Specification for the of Strand and Lifting Loops. Technical
velopment and Transfer Length Tests Test to Determine the Bond Properties Bulletin 74-B5. Concrete Technology
on High Performance Concrete Box of Prestressing Tendons. RPC6. Sys- Corp.
Girders. PCI Journal, Vol. 45, No. 5 tèmes de Constructions et Ouvrages. 29. Abrishami, H. H., and D. Mitchell.
(September–October): pp. 96–109. Bagneux, France: RILEM. 1993. Bond Characteristics of Preten-
7. Steinberg, E., J. T. Beier, and S. Sar- 18. Fédération Internationale de la Précon- sioned Strand. ACI Materials Journal,
gand. 2001. Effects of Sudden Pre- trainte (FIP). 1982. Test for the Determi- Vol. 90, No. 3 (May–June): pp. 228–
stress Force Transfer in Pretensioned nation of Tendon Transmission Length 235.
Concrete Beams. PCI Journal, Vol. 46, under Static Conditions. Report on Pre- 30. Hoyer, E., and E. Friedrich. 1939. Be-
No. 1 (January–February): pp. 64–75. stressing Steel: 7. London, U.K.: FIP. itrag zur Frage der Haftspannung in
8. Barnes, R. W., J. W. Grove, and N. H. 19. Deatherage, J. H., E. Burdette, and C. Eisenbetonbauteilen. Beton und Eisen,
Burns. 2003. Experimental Assessment K. Chew. 1994. Development Length Vol. 50, No. 9: pp. 717–736.
of Factors Affecting Transfer Length. and Lateral Spacing Requirements of 31. Keuning, R. W., M. A. Sozen, and C.
ACI Structural Journal, Vol. 100, No. 6 Prestressing Strand for Prestressed P. Siess. A Study of Anchorage Bond
(November–December): pp. 740–748. Concrete Bridge Girders. PCI Journal, in Prestressed Concrete. No. 251.
9. Cousins, T. E., D. W. Johnston, and P. Vol. 39, No. 1 (January–February): pp. University of Illinois Structural Re-
Zia. 1990. Transfer and Development 70–83. search Series.
Length of Epoxy-coated and Uncoated 20. Russell, B. W., and N. H. Burns. 1996. 32. Vandewalle, L., and F. Mortelmans.
Prestressing Strand. PCI Journal, Vol. Measured Transfer Lengths of 0.5 and 1994. Anchorage of Strands. Proceed-
35, No. 4 (July–August): pp. 92–103. 0.6 in. Strands in Pretensioned Con- ings of the Fédération Internationale
10. Chief, Bridge Division, Federal High- crete. PCI Journal, Vol. 41, No. 5 de la Précontrainte (FIP) XII Interna-
way Administration (FHWA). 1998. (September–October): pp. 44–65. tional Congress. Washington, DC: pp.
Prestressing Strand for Pretension Ap- 21. Lu, Z., T. E. Boothby, C. E. Bakis, and J16–J22.
plications—Development Length Re- A. Nanni. 2000. Transfer and Devel- 33. Cousins, T. E., M. Badeaux, and S.
visited. Memorandum (October 26). opment Lengths of FRP Prestressing Moustafa. 1992. Proposed Test for
Washington, DC: FHWA. Tendons. PCI Journal, Vol. 45, No. 2 Determining Bond Characteristics of
11. Buckner, C. D. 1995. A Review of (March–April): pp. 84–95. Prestressing Strand. PCI Journal, Vol.
Strand Development Length for Pre- 22. Mahmoud, Z. I., S. H. Rizkalla, and E. 37, No. 1 (January–February): pp. 66–
tensioned Concrete Members. PCI R. Zaghloul. 1999. Transfer and Devel- 73.
Journal, Vol. 40, No. 2 (March–April): opment Lengths of Carbon Fiber Rein- 34. Linger, D. A., and S. R. Bhonsle. 1963.
pp. 84–105. forcement Polymers Prestressing Rein- An Investigation of Transfer Length
12. ASTM Subcommittee A01.05. Standard forcing. ACI Structural Journal, Vol. in Pretensioned Concrete Using Pho-
Specification for Steel Strand, Uncoated 96, No. 4 (July–August): pp. 594–602. toelasticity. PCI Journal, Vol. 8, No.
Seven-Wire for Prestressed Concrete. A 23. Guyon, Y. 1953. Béton Précontrainte. 4 (July–August): pp. 13–30.
416/A 416M-99. West Conshohocken, Étude Théorique et Experiméntale. Ed. 35. Chen, H., and K. Wissawapaisal.
PA: ASTM International. Eyrolles. Paris, France: 711 pp. 2001. Measurement of Tensile Forces
13. Asociación Española de Normalización 24. Balázs, G. 1993. Transfer Length of in a Seven-Wire Prestressing Strand
y Certificación (AENOR). 1997. Alam- Prestressing Strand as a Function of Using Stress Waves. Journal of Engi-
bres y Cordones de Acero para Ar- Draw-in and Initial Prestress. PCI neers Mechanics (June): pp. 599–606.
maduras de Hormigón Pretensado. [In Journal, Vol. 38, No. 2 (March–April): 36. Martí, J. R. 2003. Experimental Study
Spanish.] UNE 36094. Madrid, Spain: pp. 86–93. on Bond of Prestressing Strand in
AENOR. 25. Logan, D. R. 1997. Acceptance Cri- High-Strength Concrete. [In Span-
14. International Federation for Structural teria for Bond Quality of Strand for ish.] Doctoral thesis, Polytechnic Uni-
Concrete (fib). 2000. Bond of Rein- Pretensioned Prestressed Concrete Ap- versity of Valencia. Microfilm UMI
forcement in Concrete. State-of-Art Re- plications. PCI Journal, Vol. 42, No. 2 3041710. Ann Arbor, MI: ProQuest
port. Bulletin No. 10. Switzerland: fib. (March–April): pp. 52–90. Information and Learning Co.
15. Rose, D. R., and B. W. Russell. 1997. 26. Salmons, J. R., and T. E. McCrate. 1977. 37. AENOR. 2000. Cemento. Parte 1:
Investigation of Standardized Tests to Bond Characteristics of Untensioned Pre- Composición, especificaciones y crite-
Measure the Bond Performance of Pre- stressing Strand. PCI Journal, Vol. 22, rios de conformidad de los cementos
stressing Strand. PCI Journal, Vol. 42, No. 1 (January–February): pp. 52–65. comunes. [In Spanish.] UNE EN 197-
No. 4 (July–August): pp. 56–80. 27. Brearley, L. M., and D. W. Johnston. 1:2000. Madrid, Spain: AENOR.

September–October 2006 85

You might also like