Project Internal Audit Procedure: Sheetalkumar

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

PROJECT INTERNAL AUDIT

PROCEDURE

Name Position Signature Date

Prepared By PRABHAKAR Eng. QA/QC 09/07/2018


SEKAR

Reviewed By RISHIKESH V. Construction 10/07/2018


PAWAR Manager-Projects

Approved By GEBRIL Consultant 11/07/2018


Engineer

Approved By SHEETALKUMAR Manager-Projects 11/07/2018

Page | 1
H = Hold Point
R = Record Review 1. Contractor Al-Sharif Group & KEC Ltd.
ITP for Erection Works W = Witness
I = Inspection
S = Surveillance 2. Client / Consultant SEC / AJEC / PCE/ DARCE

Clause Description Responsibility Frequency Inspection /Test Acceptance Record Remark


1 2 3 Method Criteria
1 Submittals

1.1 TL Route, Structure List R R Document Review NA IFC Stamped


Drawing

1.2 Method Statement R R Document Review NA Submittal


Approval

1.3 Tower Design / Drawing Document Review NA Submittal


R R Approval/ IFC
Stamped
Drawing
1.4 Tower Material Test Report /Certificate R R Document Review NA Submittal
Approval

2.1 Pre-Inspection for Ground Assembly

2.1.1 Drawings are approved and at correct revision. R R Document Review NA IFC Stamped
Drawing
2.1.2 Tower Material Inspection including Bolt & Nut H S As per Approved Galvanize
Drawing thickness
>130microns
2.1.3 Ensure location is accessible for Assembly I S On site Visual NA
Inspection
2.1.4 Ensure availability of lifting equipment I S On site Visual NA
Inspection
2.1.5 Handling and storage of Materials I S On site Visual NA
Inspection
2.1.6 Check for Damaged and Mis-fabricated Member I S On site Visual NA
Inspection

Page | 2
Clause Description Responsibility Frequency Inspection /Test Acceptance Record Remark
1 2 3 Method Criteria
2.2 Ground Assembly

2.2.1 Inspection of Tower ground Assembly and I S On site Visual NA


Cross Arm Assembly Inspection

2.2.2 Inspection of Missing or incorrect item I S On site Visual NA


Inspection

2.2.3 Inspection of Cross Arm and OPGW cross arm I S On site Visual 16mm – 10 to
bolt torque checking Inspection 14 kgm
20mm – 17 to
23 kgm

2.2.4 Inspection of Cross Arm and OPGW cross arm I S On site Visual NA
bolt Palnut installation Inspection

3 Tower Erection

3.1 Ensure location is accessible for Erection I S On site Visual NA


Inspection

3.2 Ensure availability of proper lifting tools and I S On site Visual NA


tackles Inspection

3.3 Check for pretension of guys I S On site Visual NA


Inspection

3.4 Check for Bent, deformed or damaged items I S On site Visual NA


Inspection

3.5 Ensure installation of bolts as required and I S On site Visual NA


tightness Inspection

Clause Description Responsibility Frequency Inspection /Test Acceptance Record Remark

Page | 3
1 2 3 Method Criteria
4 Post Erection
4.1 Inspection of bolt torque checking I S On site Visual 16mm – 10 to
Inspection 14 kgm
20mm – 17 to
23 kgm
4.2 Inspection / Ensure installation of bolt palnut I S On site Visual NA
Inspection

4.3 Inspection of ATB and ACD installtion I S On site Visual NA


Inspection

4.4 Inspection / Ensure installation of Tower I S On site Visual NA


identification plates Inspection

Page | 4

You might also like