PROCEDURE
Page | 1
H = Hold Point
R = Record Review 1. Contractor Al-Sharif Group & KEC Ltd.
ITP for Erection Works W = Witness
I = Inspection
S = Surveillance 2. Client / Consultant SEC / AJEC / PCE/ DARCE
2.1.1 Drawings are approved and at correct revision. R R Document Review NA IFC Stamped
Drawing
2.1.2 Tower Material Inspection including Bolt & Nut H S As per Approved Galvanize
Drawing thickness
>130microns
2.1.3 Ensure location is accessible for Assembly I S On site Visual NA
Inspection
2.1.4 Ensure availability of lifting equipment I S On site Visual NA
Inspection
2.1.5 Handling and storage of Materials I S On site Visual NA
Inspection
2.1.6 Check for Damaged and Mis-fabricated Member I S On site Visual NA
Inspection
Page | 2
Clause Description Responsibility Frequency Inspection /Test Acceptance Record Remark
1 2 3 Method Criteria
2.2 Ground Assembly
2.2.3 Inspection of Cross Arm and OPGW cross arm I S On site Visual 16mm – 10 to
bolt torque checking Inspection 14 kgm
20mm – 17 to
23 kgm
2.2.4 Inspection of Cross Arm and OPGW cross arm I S On site Visual NA
bolt Palnut installation Inspection
3 Tower Erection
Page | 3
1 2 3 Method Criteria
4 Post Erection
4.1 Inspection of bolt torque checking I S On site Visual 16mm – 10 to
Inspection 14 kgm
20mm – 17 to
23 kgm
4.2 Inspection / Ensure installation of bolt palnut I S On site Visual NA
Inspection
Page | 4