Removal of Debris-Filling - Levelling & Compacting
Removal of Debris-Filling - Levelling & Compacting
JHA Preparation Team: Responsible Implementation Team: Evacuation/Muster point: As Per Individual Sites
1 – Hazem Yousef- DUS Construction 1 –DUS Construction
2 – Mahmoud Halawah- DUS Construction 2- Tools and or Equipment required:
3 – Mansour Alsubaie - HSE Supervisor 3- Excavator, Jack Hammer (Depending on the
4 - Anas Shelbayeh– PE 4- scale of the trial hole)
5- 5- Hand Tools, Mandatory PPE.
6- 6-
7- 7- JHA No: M-BCW-000DS0-GH00-JHA-000015 Rev.01
RISK RESIDU ACTION
Job Steps HAZARDS IDENTIFIED RATI CONTROL METHOD AL BY/RECOR
NG RISK D
STEP 1. - Risks/Hazards not identified at work location 12 - Undertake effective daily STARRT 4 Supervisor
- Deliver daily STARRT card before undertaking works. briefing before conducting works. Obtain
briefing. H signatures and forward copies to the ES&H L
- Poor communication / no crew engagement. department.
- Open discussions are to be promoted
Refn: Safety Task Analysis and Risk - Miscommunication due to language barrier through a more informal forum when the
Reduction Talk (STARRT) JHA is delivered. JHA is to call on workers
- Failure to convey the JHAs content, to discuss their personal experiences of
-Permits must be adhered to at procedures and hazards efficiently. safety issues for similar activities.
all times - JHA will be communicated by an
- Workers used for the task are not qualified or authorized translator through the workers’
insufficiently trained. native language.
STEP 6. 9 4 GF/SE
-Completion of task -Injury due to removal of signage, handrail, -Proper PPE and manual handling in place.
and/or barricades.
- Personal Hygiene. - Skin Disease. 8 - Regular housekeeping and bathing. 3 All Team
- Eat quality foods and hydrate regularly. Members
Refn: Welfare Arrangements - Illness. M Seek medical advice if in doubt. L
(M-BCW-000000-GH00-PRO-000075) - Individual is to immediately report to their
- Body Odour. supervisor in a case of illness.
- Ensure of adequate welfare facilities to a
suitable standard are in place prior to work
commencing.
- Considering Location’s - Difficult Terrain, Vegetation, Snake Bites, 5 -Wear appropriate boots and clothing. 3 Supervisor /
Environment Risks. Scorpion, Camel Spider etc. - Store all personal belongings indoors and All Team
M inspect areas regularly. L Members
Refn: HS&E Responsibilities - Inform staff of the Clinics located on site
(M-BCW-000000-GV00-MPL-00001) to provide emergency assistance.
PROBABILITY TEST
PROBABILITY LEVEL
PROBABILIITY DEFINITION
1 Practically Never Occurs Consequence unheard of or not known to have occurred on Bechtel, Almabani or CCC projects or in the EPC industry
2 Not likely to Occur Consequence rarely occurs on Bechtel, Almabani or CCC projects or in the EPC industry
3 Could Occur Consequence may have occurred on Bechtel, Almabani or CCC projects and could occur again
4 Known to Occur Consequence has occurred more than once on Bechtel, Almabani or CCC projects and will likely occur again
5 Occurs Frequently Consequence has occurred multiple times on Bechtel, Almabani or CCC projects and will very likely occur again
PROBABILITY LEVEL
SEVERITY Increasing Probability
LEVEL
1 – Practically Never Occurs 2 – Not Likely to occur 3 – Could Occur 4 – Known to Occur 5 – Occurs Frequently
Increasing Severity
Traffic Management Segment Installation Public Safety Mobile plant movement Lifting Activity
Hearing Protection Tripod Scaffold Power Hand Tools Do not Use tag Confined Space
Do not Enter High Pressure /
SCBA Retractable Life line Fire Extinguisher Scissor Lift
signage Abrasive Blasting
Suspended
Compressor Unauthorised Keep
Airline Restraint Line Jack Hammer Personnel
machine away
Platform
Tunnel Boring Hazardous
machine Substances
EWP boom > 11m Tunnel Boring machine Excavator Rigger II Asbestos removalist
Scissor Lift Articulate Boom Platform Front End Loader Rigger III Light Vehicle
Concrete Placing Boom Working inside manhole Backhoe Dogger Heavy Rigid
NOTE: For further guidance please refer to the following project procedure - M-BAC-000000-GH00-PRO-000081 Job Hazard Analysis