Itemized Expenses ENTER EXPENSES

HOME CONSTRUCTION
BUDGET

PROJECT INFORMATION
Project Name Kitchen Remodel

Take out old flooring, replace with new tile. Finish and trim all new flooring. Replace
Project Description
current cabinets with more modern style. Finish and trim all cabinets.

Contractor Alpine Ski House


Funds Used To
Licensed/Bonded Number C#12345678 Date: $2810,000
(80%)
Contact Name Mike Miller Funds Remaining:
$690,000 (20%)
Website http://www.alpineskihouse.com/

Phone 603-555-0198

Address 789 Smith Street, Bozeman, MT 06030

FINANCIAL STATUS
Cash Amount $3,500

Financed Amount $0

Total Allotted Funds $3,500

Funds Used To Date $2,810

Funds Remaining $690

Page 1 of 2
Budget Summary
BUDGET SUMMARY

LIST OF
EXPENSES

PROJECT FUNDS ALLOTTED FUNDS USED TO DATE FUNDS REMAINING


$3,500.00 $2,810.00 $690.00

This shape represents


Item Category Amount a table slicer. Table
slicers are supported
Take out flooring Labor $150.00
in Excel or later.

Strip flooring glue Labor $50.00 If the shape was


modified in an earlier
Sand floor Labor $50.00 version of Excel, or if
the workbook was
saved in Excel 2007
Prep floor Labor $100.00 or earlier, the slicer
can't be used.
Floor installation Labor $200.00

Floor caulking Labor $25.00

Floor trim Labor $50.00

Remove old cabinets Labor $150.00

Prep cabinet area Labor $50.00

Install new cabinets Labor $300.00

Caulk cabinets Labor $100.00

Apply cabinet coating Labor $100.00

Install cabinet hardware Labor $50.00

Total $1,375.00