Professional Documents
Culture Documents
The Art of Transformer Maintenance, Inspection and Repair (Recommended Practices)
The Art of Transformer Maintenance, Inspection and Repair (Recommended Practices)
The Art of Transformer Maintenance, Inspection and Repair (Recommended Practices)
Factory tests
The remainder of the twelve factory tests are briefly summarized below. The details of the test set
connections and formulas of some of the listed tests are already described in separately published articles,
and for the rest you are directed to ANSI/IEEE Standard C57.12.90 for these details.
12 Transformer Factory Tests Briefly Explained (on photo: 420 kV power transformer, rated power 400
MVA produced by KOLEKTOR ETRA; transformer total mass is more than 400 tons and it operates in power
plant in Germany, owned by SWM Infrastructure GmbH.)
This list is not complete, there are few tests missing, not mentioned here, like Turn ratio test
or Measurement of voltage ratio and check of phase displacement, but you can find them also separatly
published at EEP (use Search).
1. No-Load Losses
2. No-Load Excitation Current
3. Load Losses and Impedance Voltage
4. Dielectric Tests
5. Switching Impulse Test
6. Lightning Impulse Test
7. Partial Discharge Test
8. Insulation Power Factor
9. Insulation Resistance
10. Noise Measurement
11. Temperature Rise (Heat Run)
12. Short-Circuit Test
1. No-Load Losses
The tests measures the no-load losses at specified excitation voltage and a specified frequency. Sine-wave
voltages are used unless a different waveform is inherent in the operation of the transformer.
The recommended method is the average-voltage voltmeter method, employing two parallel-connected
voltmeters. One voltmeter is an average-responding but RMS calibrated voltmeter and the other voltmeter
is a true RMS-responding voltmeter.
The test voltage is adjusted to the specified value as read by the average-responding voltmeters. The
readings of both voltmeters are used to correct the no-load losses to a sine-wave basis.
Connection diagram for measuring no-load losses
2. No-Load Excitation Current
This current is measured in the winding used to excite the transformer with the other windings open-
circuited. It is generally expressed in percent of the rated current of the winding. No-load excitation
current is not sinusoidal and contains, as we have seen, odd harmonics (predominantly third harmonic
current).
The ammeter used to record the no-load excitation current is an RMS meter which reads the square root
of the sum of the squares of the harmonic currents.
3. Load Losses and Impedance Voltage
The transformer must be in a specific state before the load losses and impedance voltage are measured.
The temperature of the insulating liquid must be stabilized and the difference between the top and bottom
oil temperatures shall be less than 5°C.
The winding temperatures must be measured (using a resistance method) before and after the test and
the average taken as the true temperature. The difference in the winding temperature before and after
the test must not exceed 5°C.
The two test methods for measuring load losses and impedance voltage are:
1. Wattmeter-voltmeter-ammeter method and
2. Impedance bridge method.
9. Insulation Resistance
This test applies a high-voltage DC voltage to one winding at a time with the other windings grounded. The
leakage current is measured and the insulation resistance is calculated using Ohm’s law.
An Insulation resistance test set is designed specifically to carry out this test, and its meter is calibrated in
mega ohms in order that the calculation may be avoided. The Megger as well as other manufacturers has a
portable instrument that can easily carried around in the field.