Tax Invoice

Date: 18th March 2020.

To,
BHARAT BIJALEE
No.02, MIDC,
Thane Belepur Road,
Airoli Navi Mumbai-b 400708
GST No: 27AAACB2900K1ZZ
PAN NO: AAACB2900K

Subject:- STRUCTURAL STRENGTHENING - MOTOR DIVISION OFFICE BUILDING


P. O. No. :- 6000032560 Date:- 18.11.2019
SAC CODE: 995414

SUMMARY SHEET OF R.A.BILL NO.- 4th RA


Bill No: MAR20/019.

FINAL AMOUNT

Total Bill Amount #REF! (A)


SGST 9% #REF! (B)
CGST 9% #REF! (C)
Total Amount D = A +B+C #REF! (D)
Say #REF! (E)

Rs : Seven Lakhs Ninty Five Thousand Six Hundred Fifty Four Only
PAN No. : ACBPJ4374P
GST NO:- 27ACBPJ4374P1Z5
HDFC BANK, Account no. 01468020000297 , IFSC code - HDFC0000146

For Gubbi Civil Engineers

Authorised Signatory.
TAX INVOICE

Date: 19th March 2020


Bill No: MAR20/019

To,
BHARAT BIJALEE
No.02, MIDC,
Thane Belepur Road,
Airoli Navi Mumbai- 400708
GST No: 27AAACB2900K1ZZ
PAN NO: AAACB2900K

Subject:- STRUCTURAL STRENGTHENING - MOTOR DIVISION OFFICE BUILDING


P. O. No. :- 6000032560 Date:- 18.11.2019

SUBJECT :- STRUCTURAL STRENGTHENING - MOTOR DIVISION OFFICE BUILDING.

TOTAL
SAC WO RA01 Bill RA02 Bill RA 02 RA03 Bill RA 03 THIS This Bill
Sr. No Description Unit Rate RA 01 Amount Total Qty CERTFD.
CODE Quantity Qty Qty Amount Qty Amount BILL QTY Amount
AMOUNT
A 995414 Motor Plant/Office Building
1 995414 Plaster Breaking
Labour for cutting breaking/
removing loose plaster of RCC items
and brick masonary chajja/ canopy & Sqmt 2000 210.00 723.93 152,025.30 409.69 86,034.90 - - 129.48 1,263.10 27,191.28 265,251.48
carting away the debris

2 995414 Loose Concrete Breaking - - -


Labour for cutting breaking/
removing loose cracked concrete with
light weight breaker of RCC items Sqmt 1300 172.00 386.20 66,426.40 90.17 15,509.24 - - #REF! #REF! #REF! #REF!
and carting away the debris

3&4 995414 Rusticide - - -


Labour for removing loose rust from
reinforcement by light hammering
water jet wire brush RCC items and
Supplying and applying rusticide of
sunanda speciality Coatings by brush
onlyt to rusted steel as per kg 200 157.00 47.10 7,394.70 8.00 1,256.00 - - #REF! #REF! #REF! #REF!
manufactures specifications ( 182 litrs)
TOTAL
SAC WO RA01 Bill RA02 Bill RA 02 RA03 Bill RA 03 THIS This Bill
Sr. No Description Unit Rate RA 01 Amount Total Qty CERTFD.
CODE Quantity Qty Qty Amount Qty Amount BILL QTY Amount
AMOUNT
5&6 995414 Polyalk Fixo Prime - - -
Supplying & applying two coat of
polyalk fixo prime of sunanda cement
slurry in the proportion of 1:1:25 to
steel reinforcement and moistering Sq.m 1300 162.00 382.10 61,900.20 90.17 14,607.54 - - #REF! #REF! #REF! #REF!
the surface for 4 hours

7 995414 Bonding Coat - - -


Supplying applying a bonding coat of
POLYALK EP and cement slurry in
the ratio of 1:0.5 by weight to the
Sq.m 1300 100.00 382.10 38,210.00 90.17 9,017.00 - - #REF! #REF! #REF! #REF!
entire broken concrete surface

8 995414 Polymer - - -
Supplying & applying by hand
POLYMER MODIFIED MORTAR in
the proportion of 1kg polyalk EP and
5kg cement and 15kg graded quality Sq.m 1300 1,310.00 382.10 500,551.00 90.17 118,122.70 - - #REF! #REF! #REF! #REF!
sand with controlled waterin layer of
15mm thick and repeating the same
till you cover broken concrete original
9 995414 Reinforcement - - -
surface with steel trowel and curing
Providing
the surface/for
fixing HYS deformed
48 hours and IS
1785 to 500water
sprinkling roundforbars
3-4indays
place
toof Kgs 2000 115.00 435.99 50,138.85 71.99 8,278.85 - - #REF! #REF! #REF! #REF!
broken
receive and badly
normal rusted
plaster in position
(upto 25mm
complete
thickness )
10 995414 External Plaster - - -
Providing and applying sand faced
cement plaster in two coats in CM 1:4
with Dr. fixit water proofing
compound to all external exposed Sq.m 2000 943.00 513.88 484,588.84 194.91 183,800.13 - - #REF! #REF! #REF! #REF!
surfaces including crack filling
polyfill AR paste and curing
11 995414 Internal Plaster - - -
Providing and applying cement
plaster in CM 1:4 single coat to all
exposed internal surfaces and surface Sq.m 480 680.00 210.04 142,827.20 214.78 146,050.40 - - #REF! #REF! #REF! #REF!
finished with Birla White putty to
receive paint
12 995414 Ingection Grouting - - -
Providing injection grouting with -
specified cement water mix with
pressure in very badly damaged RCC Nos 20 367.00 - - - - - - - - -
beams/slabs including pipe/nipple
upto 0.25 kg/per point
13 995414 Micro Concrete - - -
TOTAL
SAC WO RA01 Bill RA02 Bill RA 02 RA03 Bill RA 03 THIS This Bill
Sr. No Description Unit Rate RA 01 Amount Total Qty CERTFD.
CODE Quantity Qty Qty Amount Qty Amount BILL QTY Amount
AMOUNT
Providing of jacketing damaged RCC
columns using MICROCONCRETE
with POLYCRETE A of SUNANDA Kgs 1000 75.00 500.00 37,500.00 775.00 58,125.00 - - - 1,275.00 - 95,625.00
as per manufactures specifications
including all centering curing
TOTAL
SAC WO RA01 Bill RA02 Bill RA 02 RA03 Bill RA 03 THIS This Bill
Sr. No Description Unit Rate RA 01 Amount Total Qty CERTFD.
CODE Quantity Qty Qty Amount Qty Amount BILL QTY Amount
AMOUNT
15 995414 Waterproofing - - - -
Waterproofing of chajjas by removing
existing IPS over coba/watta and
apply 1kg polyalk WP and 1.25 kg
cement by brush and apply 2nd coat
of polyalk WP/Cement slurry and Sq.m 356 1,100.00 - - 98.33 108,163.00 - - #REF! #REF! #REF! #REF!
cure it 4 to 5 days and then laying IPS
over above treatement with
SUNPLEX and top finished with
square cut lines
16 995414 Breaking 400mm thick wall - - -
Cutting breaking 400 mm thick wall
by side of column and making good
Cu.m 40 ### - - 4.05 50,908.50 - - #REF! #REF! #REF! #REF!
in concrete/plaster after repair with
polymer
B 995414 Closing of steel staircase opening in -
Motor Plant Office Building - - -

1 995414 Prepare Surface - - -


Labour for cleaning the existing beam
surface for fixing M.S beam supports Sq.m 3 179.00 2.48 443.92 - - - - - 2.48 - 443.92

2 995414 Fixing MS Plates - - -


Supporting the slab welded to MS
plaster of size 200 X 275 X 12 mm to
existing RCC beams with 2 X 4 Nos Kgs 8 175.00 65.79 11,513.25 - - - - - 65.79 - 11,513.25
16mm dia. Anchor bolts 200m long
with REV3 hits chemical including
3 995414 painting with
Structural primer & two coats of
Steel - - - -
enamel paint to structural beam
Supply / Fabrication / Erection of
beams for supporting the slabs
welded to M.S Plate with one coat of Kgs 2200 135.00 1,209.45 163,275.75 - - - - - 1,209.45 - 163,275.75
primer & two coats of enamel paint

4 995414 Concreting - - - -
Providing / Casting in situ M 250
grade reinforced concrete slab 125mm
thick including for steel reinforcement Sq.m 25 7,340.00 40.86 299,912.40 4.81 35,305.40 - - #REF! #REF! #REF! #REF!
all centering consolidated by
vibration / curing as per drawing
5 995414 Expantion Joint Filler - - -
Providing & fixing 5m thick bitumen
fibre for expansion joint with hot
RM 8 520.00 8.50 4,420.00 - - - - #REF! #REF! #REF! #REF!
dammer 130m wide

C 995414 Extra Items - - -


1 995414 Dismantling RCC Members - - -
TOTAL
SAC WO RA01 Bill RA02 Bill RA 02 RA03 Bill RA 03 THIS This Bill
Sr. No Description Unit Rate RA 01 Amount Total Qty CERTFD.
CODE Quantity Qty Qty Amount Qty Amount BILL QTY Amount
AMOUNT
Dismantling RCC Members carefully
of any size / shape, as directed,
without damaging other parts of the cum 2,000.00 - - - - 5.98 11,955.63 - 5.98 - 11,955.63
building,cutting / removing the steel
bars, removing / carting away the
debries, cleaning, etc. complete
2 995414 Dash Coat / Trowelling - - -
Providing & applying dash coat in
CM 1:4, wherever plaster thickness
increase beyond 25mm thk including Sqm 550.00 - - - - 62.35 34,289.86 - 62.35 - 34,289.86
addition of PP fibre 125 gms per bag
of cement etc. complete.
3 995414 Providing & Anchoring Hilti Grout - - -
Drilling holes with the help of
Drilling machine,Provoding & Fixing
reinforcement with the help of hilti/ No 350.00 - - - - 214.00 74,900.00 - 214.00 - 74,900.00
Fisher's chemicals etc complete.

4 995414 Plywood Covering - - -


Providing & Covering the Existing
Windows, Ventilators, with Plywood
Sqm 225.00 - - - - 27.96 6,291.56 - 27.96 - 6,291.56
with nails etc complete

5 995414 Breaking of Tiles - - -


Breaking carefully the existing Tiles,
diposing off the debries, cleaning etc
complete Rft 100.00 - - - - 50.00 5,000.00 - 50.00 - 5,000.00

6 995414 Crack Filling - - -


Crack filling :- Cleaning the crack
surface with the help of clean
water,drying the surface in natural Rft 80.00 - - - - 806.75 64,539.90 - 806.75 - 64,539.90
sun ,providing & applying the
bonding coat, filling the same with
polymer modified mortar in white Total Amount 2,021,127.81 835,178.66 196,976.95 #REF! #REF!
cement and sunplex for surface cure
M/s Gubbi
natural Civil
for 24 Engineers
hrs.etc GST No :
complete.
27ACBPJ4374P1Z5 This Bill Amount #REF! #REF!
PAN CARD NO : ACBPJ4374P Add @ SGST @ 9% #REF! #REF!
Add @ CGST @ 9% #REF! #REF!
Net Total Amount #REF! #REF!

Rs. Seven Lakhs Ninty Five Thousand Six Hundred Fifty Three And Paisa Seventy Eight Only.

Thanks & Regards,


For Gubbi Civil Enginees,

Authorised Signatory.
A1 Unit-3 Internal Painting
LENGTH BREADTH DEPTH QUANTITY
SR.NO DESCRIPTION NO REMARK
(M) (M) (M) (Sqmt)

Staircase

1) Ground Floor Staircase from


canteen passage area -
-
Hand Rail Area (Left Side) Wall 1 2.60 2.40 6.24
-
Wall attached to the window wall -
left side next to hand rail wall 1 1.00 2.70 2.70
-
Window wall phase-1 -
( below indow patta) 1 3.50 0.77 2.70
-
Window wall phase-2 1 1.25 0.60 0.75
-
Window wall phase-3 -
(Trangle Area) 1 0.90 0.50 0.45
-

Ground Floor Staircase Bottom Patta 1 2.55 1.38 3.52


-
Ground Floor Staircase SidePatta
(Small) 1 2.55 0.23 0.59
-
Ground Floor Staircase Side Step
Tringle (Small) 9 0.25 0.17 0.38
-
Ground Floor Staircase Bottom Patta
-2 1 1.50 1.00 1.50
-
Ground Floor Staircase Small Bottom
Patta -3 1 0.13 0.36 0.05
-
Ground Floor Staircase below wall
left wall phase-1 1 1.31 1.00 1.31
-

Ground Floor Staircase below wall


left wall phase-2 triangle area 1 1.95 1.00 1.95
-
Ground Floor Staircase front wall (D-
64) Sign wall phase-1 1 3.50 1.31 4.59
-
Ground Floor Staircase (D-64) Sign
wall phase-2 (Tringle area) 1 0.70 1.00 0.70
-

Ground Floor Staircase front wall (D-


64) Sign wall phase-3 ( Small ) 1 0.70 1.00 0.70
LENGTH BREADTH DEPTH QUANTITY
SR.NO DESCRIPTION NO REMARK
(M) (M) (M) (Sqmt)

-
Ground Floor Small Staircase Bottom
Phase-1 1 1.23 1.35 1.66
-
Ground Floor Small Staircase Bottom
Phase-2 1 1.42 1.00 1.42
-
Ground Floor Small Staircase Front
Patta 1 0.23 0.85 0.20
-
Ground Floor Small Staircase Side
Triangle ( Steps) 3 0.25 0.17 0.13
-
Ground Floor Small Staircase Side
Triangle-2 1 0.38 0.27 0.10
-
Ground Floor Staircase Right Wall
Phase-1 1 1.45 2.10 3.05
-
Ground Floor Staircase Right Wall
Phase-2 1 2.55 2.10 5.36
-
Ground Floor Staircase Right Wall
Top Triangle Phase-3 1 0.66 0.10 0.07
-
Ground Floor Staircase Right Wall
Phase-4 1 0.66 1.10 0.73
-
Ground Floor Staircase Right Wall
Small Area Phase-5 1 0.20 0.33 0.07
-
Ground Floor Down Staircase-2 1 1.24 1.37 1.70
-
Ground Floor Staircase Phase-1 Tube
Light Wall 1 1.62 1.15 1.86
-
Ground Floor Down Staircase Side
Patta 1 1.37 0.21 0.29
-
Ground Floor Staircase Side Step
Triangle 4 0.25 0.17 0.17
-
Staircase between Ground Floor -
& 1st floor 2nd Flight -
( bottom of staircase) 1 3.05 1.37 4.18
-
Staircase between Ground Floor -
& 1st floor 2nd Flight -
( side of staircase) 1 3.05 0.25 0.76
-
Staircase between Ground Floor -
LENGTH BREADTH DEPTH QUANTITY
SR.NO DESCRIPTION NO REMARK
(M) (M) (M) (Sqmt)

& 1st floor 2nd Flight -


( step side triangle) 9 0.25 0.17 0.38
-
2nd Flight Ceiling-1 1 3.70 1.03 3.81
-
2nd Flight Ceiling-2 ( Small) 1 1.09 0.76 0.83
-
2nd Flight Ceiling-3 1 2.10 1.20 2.52
-
2nd Flight Passage Window Wall -
Side Column 2 0.07 1.17 0.16
-
2nd Flight Right Wall -
Phase-1 ( Hand rail ) 1 1.98 1.18 2.34
-
2nd Flight Right Wall -
Phase-2 Tringle 1 1.90 1.08 2.05
-
2nd Flight Right Wall -
Phase-2 1 1.90 1.86 3.53
-
2nd Flight Right Wall -
Phase-2 Tringle 2 1 0.70 1.15 0.81
-
2nd Flight Right Wall -
Phase-4 1 0.70 0.40 0.28
-
2nd Flight Right Wall -
Phase-5 1 0.32 0.35 0.11
-
Staircase Down Area ( top) 1 2.46 1.35 3.32
-
Staircase Top Small Passage 1 1.35 0.40 0.54
-
1st Floor m and CE Door Wall 1 2.15 2.23 4.79
Less Door -1 1.26 2.04 (2.57)
-
1st Floor IT & UP BG Door Wall 1 2.15 2.23 4.79
Less Door -1 1.26 2.04 (2.57)
-
1st Floor Staircase Top Patta -
( centre) 1 0.63 0.77 0.49
-
1st Floor Staircase Top Patta -
(Right) 1 1.35 0.47 0.63
-
1st Floor Staircase Top Patta -
(Left) 1 1.35 0.45 0.61
-
1st Floor Front Wall 1 3.72 2.23 8.30
-
LENGTH BREADTH DEPTH QUANTITY
SR.NO DESCRIPTION NO REMARK
(M) (M) (M) (Sqmt)

1st Floor Passage Ceiling 1 3.72 2.35 8.74


-
Unit-3 last Dead Wall Side Internal -
Staircase 1st Floor Front wall 1 3.93 2.23 8.76
-
1st Floor Right Door Wall 1 2.23 2.50 5.58
Less Door -1 1.27 2.50 (3.18)
-
1st Floor Left Door Wall 1 2.23 1.78 3.97
Less Door -1 1.27 2.50 (3.18)
-
1st Floor Ceiling- 1 1 2.74 2.26 6.19
-
1st Floor Ceiling- 2 1 0.15 1.91 0.29
-
1st Floor Ceiling- 3 1 1.61 0.13 0.21
-
1st Floor Ceiling- 4 1 0.97 1.98 1.92
-
1st Floor Attached Staircase Wall -
Column-1 1 0.36 2.23 0.80
-
1st Floor Attached Staircase Wall -
Column-2 1 2.70 0.40 1.08
-
1st Floor Attached Staircase Wall -
Phase-1 1 1.10 1.90 2.09
-
1st Floor Attached Staircase Wall -
Phase-2 Top Portion ( Tringle) 1 1.30 0.55 0.72
-
1st Floor Staircase Flight -
(Left Staircase) Hand rail wall 1 1.35 0.95 1.28
-
1st Floor Staircase Flight -
back ( Small Portion) 1 1.35 0.40 0.54
-
1st Floor Staircase Flight -
back Area 1 2.50 1.35 3.38
-
1st Floor Staircase Left Wall -
Phase - 3 1 2.00 1.25 2.50
-
Flight Passage Area Between 1st -
Floor & Ground Floor Ceiling -
Area Phase-1 1 1.25 1.35 1.69
-
Flight Passage Area Between 1st -
Floor & Ground Floor middle -
passage Ceiling Phase-2 1 1.38 0.80 1.10
-
LENGTH BREADTH DEPTH QUANTITY
SR.NO DESCRIPTION NO REMARK
(M) (M) (M) (Sqmt)

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Total Quantity 129.48 Sqmt