Sl. 2020 2021 2022


Activity
No. Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Finalization of the Report of the Committee of
Technical Experts
2 Finalization of the Terms of Reference (ToR) of the
ESIA Consultant, followed by its engagement as per
Single Source Selection Method, with the approval
of World Bank

3 Finalization of Report of the ESIA Consultant

4 Engagement of an Economic & Financial Analysis


Consultant, also as per Single Source Selection
Method, with the approval of Bank

5 In-house preparation of Feasibility Study Report


incorporating, inter alia, ESIA recommendations &
EFA analysis
6 Acceptable of all Reports by the World Bank (to be
done stage wise)
7 Preparation of detailed estimates & bidding
documents and approval of those by the World Bank

8 Invitation of bids and processing upto Award of


Contract, requiring approval of the World Bank
9 Commencement of works at site