Precasting and PPVC

: In Integrated
Integrated Digital Deliver y
Eugene Seah
Senior Director, Group CEO’s Office
Lead, Digital Management Office
June 2020

1
Remembering sg.org
Source: SCMP
BCA-SINGAPORE
Construction Industry
Transformation Map 2018

Towards IDD
Integrated Digital Delivery

Slide 5
What is IDD ?
Integrated Digital Delivery
1

Fully integrates all


processes & stakeholders 4 2
along the entire value
chain through advanced
info-communications
technology (ICT) &
smart technologies
3
Scope of IDD
Digital Design
Collaborative and coordinated
design via BIM/VDC and other
1 2 Digital Manufacturing &
Fabrication
computational tools to achieve Integration of BIM/VDC design to
design objectives and ease and off-site production, fabrication and
optimize downstream component management through
manufacturing, fabrication, automation, robotics optimization.
construction and maintenance.

Digital Asset Delivery


IDD Digital Construction
Integration of BIM/VDC design
& Management and off-site manufacturing/
Verification and handing over fabrication to delivery and
of the asset for operations and installation on-site through use of
maintenance through effective real-time ICT solutions, as part of
project management and Lean

4 3
use of digital tools.
construction

Source : BCA
IDD Objectives / aims:
To achieve >>timely,
cost effective,
productive & high quality
project delivery - design, manufacturing, fabrication, construction
and asset delivery

To adopt >> BIM/VDC & other Digital solutions

To convey >>relevant, accurate, & timely digital info


through collaborative working approaches & integrated platforms

IDD
Source : BCA
Current Industry Challenges

DIGITAL
1 DIGITAL
MANUFACTURING
2 DIGITAL
3 DIGITAL ASSET
DELIVERY &
4
DESIGN CONSTRUCTION
& FABRICATION MANAGEMENT

 Design BIM model is  Design/Construction  BIM is not fully utilized  Building owners
often developed for BIM not directly linked during construction still learning how
BCA submission only. to manufacturing, beyond 3D geometry to link BIM to FM
 BIM Model not fabrication & logistics,
planning & execution  Documentation still  Lack of capability
suitable for DfMA/FM very paper-based and infrastructure
 Digital Designers are  Opportunities for
to support FM
rare to find(Designer further automation,  Real-time information operations
who can code) use of robotics and 3D not captured and used digitally.
printing effectively to guide
coordination,
execution, & validation

Digital information are mostly segregated, great need to integrate across the value chain for greater effectiveness

Source : BCA
1 Digital Design - components
BIM
Quality
Checks

AR-VR Automated Code


Use of Compliance
Intelligent Checker
Objects

Computational &
DESIGN BIM MODEL
Rule-based Tender Release
design & Handover
Buildability and Constructability

Source : BCA
2 Digital Manufacturing and Fabrication components

BIM to Shop Floor Robotics installation


(e.g. using mobile Quality Control
device)

Production Storing & Tagging (e.g.


Management System using RFID linked To
(e.g. from BIM to machinery) BIM elements)

Fabrication Model Creation Delivery


(e.g. Detailing & BBS) (e.g. Fleet Tracking)

Source : BCA
2a. Fabrication Model Preparation
 Design upfront for ease of manufacturing and assembly
 Highly automated offsite production facilities - PPVC
 Efficient and clean on-site installation process -

Source : UD2 Slide 12


2b. BIM to Machine - DfMA
Production Management Systems
BIM to machine for DfMA
Structure, MEP, Architectural Facades

Source : BCA Slide 13


DIGITAL DESIGN

Parametric Design (Input & Output) Design Performance

Collaboration Virtual Reality (VR) Immersive Virtual Reality (IVR)/Computer Aided Virtual Environment (CAVE)
2c. BIM to
Shop Floor
Cold Formed
Light Gauge Steel Truss
Fabrication Line in
direct BIM/CAD control

Slide 15
2d. Automation & Robotics
Automated Fabrication and Welding
TEKLA Integration

Very precise and minimum errors


Save on material wastage

Campus using methodology for coordination


For PPVC with MEP

Slide 16
2e. DfMA : Better Quality Control

Source : BCA Slide 17


DIGITAL MANUFACTURING & FABRICATION
3 Digital Construction - components

Site Progress Tracking Smart Installation


& Inspection (e.g. smart crane &
(e.g. using drone) robotics)
Site Safety & Security
Material Tracking
(e.g. using RFID) (e.g. using video analytics)

Field BIM
Equipment Tracking
(e.g. using BIM for
(e.g. using GPS)
layout)
Lean ICE Meeting Session
Construction

Site Data Monitoring


Project Management & Submission
Manpower Tracking Construction
Command Centre (e.g. Silt Detection System)
(e.g. using wearable) BIM model

Source : BCA
3a. VDC Process – BIM in Construction

VDC=BIM+ICE+PPM /Metrics (Stanford University)


ICE (Integrated Concurrent Engineering)
PPM (Production & Process Management)
Metrics (Continuous QC & Monitoring)

Slide 20
VDC Fuzor & MS Teams

Source : UD2 Slide 21


VDC – READY PLAYER ONE

Source : BCA Slide 22


3bc. Manpower, material &
Equipment – Live Tracking
Using : :
Radio Frequency Identification (RFID)
GPS Tracking
Mobile GSM tracking
Building Information Modelling (BIM)

Live tracking of Construction machinery, equipment, & manpower

Source : BCA Slide 23


3d. Site Progress tracking
- Ariel Progress with Drones
- Robots to access inhospitable areas
- Updating progress with the planned activity

Source : BCA Slide 24


3e. Smart Installation & Site Assembly
Remote controlled tower cranes
Sensor to assist fixing, installation & troubleshooting

Source : BCA Slide 25


Site Safety
Using BIM :
Simulate Site safety issues
Simulate Crane reach and headroom's
Mock-ups for shoring and underpinning
Formwork simulation and Quantification

Source : BCA Slide 26


Site Monitoring – Remote & Video Surveillance

Source : BCA Slide 27


4 Digital Asset Delivery & Management - components

BIM Handover Quality


BIM As-built Verification
Check (e.g. check data
(e.g. using 3D scanner)
correctness)
Defect Management Asset Monitoring
System (e.g. using (e.g. using video analytics
cloud-based mobile system) to detect leakage)

Asset Management (e.g.


Quality Assessment using BIM data for
System (e.g. using maintenance)
robot for building
inspection)
Source : BCA
QA QC Assessment
Before Handover >>
 Using Robots for internal
inspections
 Crawling Robots for inaccessible
spaces

Source : BCA Slide 29


Handover & As-Built Verification
Verifying As-Built with Lidar Scans
Checking As-Built with the original design
Updating Design Models

Slide 30
DIGITAL ASSET DELIVERY & MANAGEMENT

Scan to BIM
Asset Monitoring & Asset Management

Source : SMM Slide 32


2 Digital Manufacturing and Fabrication components
…… Coming Back to …….

BIM to Shop Floor Robotics installation


(e.g. using mobile Quality Control
device)

Production Storing & Tagging (e.g.


Management System using RFID linked To
(e.g. from BIM to machinery) BIM elements)

Fabrication Model Creation Delivery


(e.g. Detailing & BBS) (e.g. Fleet Tracking)

Source : BCA Source : BCA Slide 33


Source : Greyform
Source ; Listland
IDD & ISO-19650
ISO 19650 is an international standard for managing information over the
whole life cycle of a building/ built asset using BIM

Source : UD2 Slide 40


IDD - Workflow
From Inception to Completion and Beyond

Source : UD2 Slide 41


IDD – The remote way
The Digital Tools for
Communication
- MS Teams
- Webex
- Zoom
- Skype for business
- IP Cameras
- Drone inspection
- WhatsApp Group

Source : UD2 Slide 42


Code Checking
Model Checker (SMC) is now able to check Codes and Regulations based on Rule
sets. Rule sets define the Authority codes into a computer understandable
algorithm for automatic machine checking

Knowledge of Scripting

Source : UD2 Slide 44


Thank You

Aaron Foong
Eugene Seah Managing Director,
Senior Director, Special Projects KTPC Management
Group CEO’s Office (part of the SJ Group)
Eugene.seah@Surbanajurong.com aaron.foongkk@ktpworld.com

Slide 47