PROPOSED HDD DESIGN CALCULATION OF POND & TEMPLE AREA CROSSING AT CH.

0+882 KM FOR 12"

PROJET: LAYING OF STEEL & MDPE PIPELINE SERVICE FOR TOTTENT GAS, GORAKHPUR GA
CLIENT: TORRENT GAS PRIVATE LIMITED
CONTRACTOR: M/s. SPUR INFRASTRUCTURE PVT LTD
TPIA: International Certification Services pvt ltd
Drawing No: TPGL/SIPL/GORAKHPUR GA/HDD-01

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of
pipes by HDD are as follows:

A. INPUT VALUES AND PARAMETERS:


1 Pipe Dia D 32.39 cm Given
2 Wall Thickness t 0.64 cm Given
3 Internal Dia 31.11 cm Calculated
4 Pipe Grade X52 Grade Given
2
5 Specified Min. Yield Strength S 3654.7571 kg/cm Given
6 Cross Sectional Area As 63.84 cm2 Calculated
7 Moment of Inertia I 8,047.25 cm4 Calculated
8 Section Modulus of Pipe Z 496.90 cm3 Calculated
9 Weight of empty Pipe in air Wp 0.50 kg/cm Calculated
10 Weight of Water Filled Pipe in air Ww 1.261 kg/cm Calculated
11 Modulus of Elasticity E 2038902 kg/cm2 Given
12 Soil Friction Angle 30 Degrees Standard
13 Design Pressure 49.97 kg/cm2 Given
14 Pre Hydrotest Pressure Prh 76.48 kg/cm2 Calculated
15 Post Hydrotest Pressure Poh 76.48 kg/cm2 Calculated
16 Operating Pr. Of Pipeline Pop 30.00 kg/cm2 Given
17 Length of Crossing L 18638 cm Calculated
18 Entry Angle 8 Degrees Designed
19 Exit Angle 8 Degrees Designed
20 Poisson's ratio m 0.3 Standard
21 Fluid drag coeff (betn slurry and pipe) f 0.00352 kg/cm2 Standard
22 Coeff of friction between pipe and soil f' 0.3 Standard
23 Buoyant weight of pipe w 0.4464 kg/cm calculated
3
24 Density of mud used Db 0.00115 kg/cm Standard
25 Max depth of crossing h 428 cm Given
26 Column height from water level to Bed Level Hw 100 cm Given
27 Maximum ht. of soil above pipe Hs 439 cm Given
28 Soil Density Ds 0.00185 kg/cm3 Geotech
29 Water Density Dw 0.001 kg/cm3 Standard
o
30 Coeff of Linear Expansion a 0.0000117 /C Standard
31 Difference in Temperature during operation D 10 Assumed
32 Proposed ROC R 35000 cm Calculated
33 Hoop Stress Limitation 0.9 of SMYS Given
34 Bending Stress limitation 0.9 of SMYS Given
35 Surface Area of Pipe 1896531.8 cm2 Calculated
36 Rig Pulling Capacity 25 Tons To be Used
37 OFC OD 0.00 cm Given
38 OFC w.t. 0.00 cm Given
39 OFC weight 0.00 Kg/cm Given
40 OFC net Bouyancy 0.00000 Kg/cm Calculated
41 Roller Spacing 1200 cm
Notes & Calculations

A. GIVEN:
To Install 32.39 cm x 0.64 cm W.T. API 5L Gr. X52 steel pipelines by Horizontal Directional
Drilling technique as per ASME B31.8

B. PURPOSE:
Pipelines to be used for gas transmission. P = 30.00 kg/ cm2

C. REFERENCE:
i) Specifications, ASME B31.8 for Gas Transmissions in Pipelines
ii) Angle of Soil Shearing resistance ASTM D-3080 methods (30 degrees)
iii) Average coeff of friction between pipe & soil; recommended values between 0.21 to 0.30 (Maidla)
Maidla, EE: “Borehole friction assessment and. application to oilfield casing design in directional. wells”,
Ph.D. Thesis, Louisiana State University (1987)
iv) Drag Coeff of Friction taken as 0.05 psi (Empirical)
NEN 3650 - Requirements for steel pipeline transportation system. Dutch Standard – 1993
v) Soil Investigation data

Page 1 of 5
PROPOSED HDD DESIGN CALCULATION OF POND & TEMPLE AREA CROSSING AT CH.0+882 KM FOR 12"

PROJET: LAYING OF STEEL & MDPE PIPELINE SERVICE FOR TOTTENT GAS, GORAKHPUR GA
CLIENT: TORRENT GAS PRIVATE LIMITED
CONTRACTOR: M/s. SPUR INFRASTRUCTURE PVT LTD
TPIA: International Certification Services pvt ltd
Drawing No: TPGL/SIPL/GORAKHPUR GA/HDD-01

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of
pipes by HDD are as follows:

D. CALCULATIONS:

1 OVERBURDEN PRESSURE AND COLLAPSE PRESSURE


The collapse pressure is determined from the theoretical elastic curve equation
2 2
Pc = 2E / [(1-µ )(D/t)(D/t-1) ]
Where: D/t = 32.39 / 0.64 = 50.61
= 35.98 kg/cm2
The collapse pressure, Pc = 35.98 kg/cm
2

The maximum overburden pressure


Po = (h*Db + hs*Ds + hw*Dw)
Po = 428 x 0.00115 + 439 x 0.00185 + 100 x 0.001
= 1.40 kg/cm2
Po/Pc = 3.90%
Since Overburden is only 3.90% of Collapse Pressure, Pipe is safe

2. BOUYANCY OF PIPE
Pipe Volume
Displacement of pipeline in drilling mud where volume
V, = 3.14 (D)(D)/4
D = 32.39 cm
V = 823.97 cc/linear cm.
Buoyancy
Buoyancy in drilling mud where mud density
B = Volume of Mud Displacement by pipe x mud density
= V x Db
B = 823.97 x 0.00115
= 0.948 kg/cm
Net Buoyancy
Net buoyancy when pipeline is empty and fully submerged
= B-W or 0.948 - 0.501
= 0.446
= 0.4464 kg/cm force

3 COATING STRESSES
The maximum shear stress in the pipeline coating during installation depends upon relative movements
of the pipeline and the surrounding soil. Using bentonite mud, the low-friction soil-coating interface
will be at a minimum.
Coating Failure Check
PP coatings Resistance = 2.5 kg/sq.cm. Std. Peel Test Value
Longitudinal Soil Stress. t = t = N(2-sin d)tan d
where ,
N is the force normal to the pipeline due to buoyancy
= 0.4464 kg/ cm
Friction Angle (d) = 30 (as per soil investigation report)
N = N/(30/360*3.14*D)
= 0.0526 kg/sq.cm.
o
2-sin 30 = 1.5
t = (N x 1.5 x tan(30)
= 0.0456 kg/sq.cm.
Which is negligible as compared to the adhesive force of 2.5 kg/sq.cm that is 1.824%
So, Coating is safe.

4. Max Tensile Stress During Pull


Allowable stress = 90 % of SMYS
T = 0.9 x S x As
= 209,978.39 kg

Page 2 of 5
PROPOSED HDD DESIGN CALCULATION OF POND & TEMPLE AREA CROSSING AT CH.0+882 KM FOR 12"

PROJET: LAYING OF STEEL & MDPE PIPELINE SERVICE FOR TOTTENT GAS, GORAKHPUR GA
CLIENT: TORRENT GAS PRIVATE LIMITED
CONTRACTOR: M/s. SPUR INFRASTRUCTURE PVT LTD
TPIA: International Certification Services pvt ltd
Drawing No: TPGL/SIPL/GORAKHPUR GA/HDD-01

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of
pipes by HDD are as follows:
Check for Tensile Stress
Max long stress that can be applied by Rig = 25 Tons
= 25000 / As
= 391.62 kg/sq.cm.
Percentage of SMYS = 10.72% of SMYS
Since Max. Tensile Stress is within limits and thus SAFE
Check for Bending Stress
For Long Bending Stress During installation at ROC = 35000 cm
= Ec/r E = modulus of elasticity
= 943.43 kg/cm2 c = distance of natural axis from edge of section
Percentage of Total SMYS = 25.81% of SMYS r = radius of curvature (ROC)

Hence Long. Bending Sress at above radius is safe.

5. Radius of Curvature Calculations

A. Before Installation
Pulling Load = 0 kg
Bending Load = 90 % of SMYS during Overbend or on rollers
Hoop Stresses = 90 % of SMYS on ground before overbend

Before Installation
Min Radius for Temporary Pipe Handling
Limiting SMYS = 90%
Bending Stress S = Ec/r
or R = 10039 cm
= 100.39 meters
B. During Installation

Max Pulling Load = 25 Tons


P=F/As = 391.621 kg/sqcm
Bending Stress Radius 35000 cm
= 943.43 kg/sqcm
Hydrotest Stress = 0.00 kg/sqcm
TOTAL Stress = 1335.05 kg/sqcm
Total Percent of SMYS = 36.53%

C. After Installation (Post Hydrotesting will be done at this stage)


Bending Stress at ROC = Ec/R
Longitudinal Stress at Test Pressure = pd/4t
Pulling Load = 0
Min Radius for Permanent Pipe Installation
As per ANSI B 31.4 factor of 1.85
Permanent Radius of Curvature - R = Ec/(0.75.S.SMYS-pd/4t)
Where S is design factor of 0.72
= 33020017.89 / [ 1974 - 967.65 ]
= 32825.77 cm
= 328.26 meters
Taking 10% higher ROC = 361 meters
Permanent Radius Calc Check:
Bending Stress at ROC = Ec/R
= 943.43 kg/sqcm

Longitudinal Stress at Test Pressure = pd/4t


= 967.65 kg/sqcm

Total Stresses = 1911.08 kg/sqcm


Stresses as Percent of SMYS = 52.29%

Page 3 of 5
PROPOSED HDD DESIGN CALCULATION OF POND & TEMPLE AREA CROSSING AT CH.0+882 KM FOR 12"

PROJET: LAYING OF STEEL & MDPE PIPELINE SERVICE FOR TOTTENT GAS, GORAKHPUR GA
CLIENT: TORRENT GAS PRIVATE LIMITED
CONTRACTOR: M/s. SPUR INFRASTRUCTURE PVT LTD
TPIA: International Certification Services pvt ltd
Drawing No: TPGL/SIPL/GORAKHPUR GA/HDD-01

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of
pipes by HDD are as follows:
6. Combined Equivalent . Stresses
A: Before Installation

Hoop Stress Sh = pd/2t


Test Pressure Pt = 76.48 kg/sqcm
= 1935.30 kg/sqcm
= 52.95% of SMYS

Bending Moment for Pipe at 1200 cm Supports


2
= Ww.L /12
= 151,356.00 kg-cm
Bending Stress Sb = BM/Polar MI
= 304.602 kg/sqcm

Combined Long Stress Sl1 = m x Sh + Sb Or m x Sh - Sb


= 580.59 + 304.60 = 580.59 - 304.60
2 2
= 885.19 kg/cm = 275.99 kg/cm

Resultant Eq. Stress


2 2
Sqrt (Sl1 - Sl1xSh+Sh2)
2
Resultant 1 = Sqrt (Sl1 - Sl1xSh+Sh ) Or
= 1678.05 kg/cm2 1813.13 kg/cm2
= 45.91% of SMYS 49.61% of SMYS
B: After Installation
Pressure at Final Hydrotest = 76.48 kg/cm2
Hoop Stress Sh = 1935.30 kg/cm2
Bending stress at give radius Sb = Ec/r
= 943.43 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 580.59 - 0.00 + 943.43
= 1524.02 kg/cm2

Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb


= 580.59 - 0.00 - 943.43
= -362.84 kg/cm2
Resultant Eq. Stress
2 2
Resultant 1 = Sqrt (Sl1 - Sl1xSh+Sh ) VON MISES' EQUATION
= 1765.95 kg/cm2
= 48.32% of SMYS
2 2
Resultant 2 = Sqrt (Sl2 - Sl2xSh+Sh )
= 2139.92 kg/cm2
= 58.55% of SMYS
C: During Operation
Operating Pressure = 30.00 kg/cm2
Hoop Stress Sh = pd/2t
= 759.14
Bending stress at give radius Sb = Ec/r
= 943.43 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 227.74 - 238.55 + 943.43
= 932.62 kg/cm2
Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb
= 455.14 - 238.55 - 943.43
= -726.84 kg/cm2
Resultant Eq. Stress
2 2
Resultant 1 = Sqrt (Sl1 - Sl1xSh+Sh )
= 859.12 kg/cm2
= 23.51% of SMYS
2 2
Resultant 2 = Sqrt (Sl2 - Sl2xSh+Sh )
= 1287.00 kg/cm2
= 35.21% of SMYS

Page 4 of 5
PROPOSED HDD DESIGN CALCULATION OF POND & TEMPLE AREA CROSSING AT CH.0+882 KM FOR 12"

PROJET: LAYING OF STEEL & MDPE PIPELINE SERVICE FOR TOTTENT GAS, GORAKHPUR GA
CLIENT: TORRENT GAS PRIVATE LIMITED
CONTRACTOR: M/s. SPUR INFRASTRUCTURE PVT LTD
TPIA: International Certification Services pvt ltd
Drawing No: TPGL/SIPL/GORAKHPUR GA/HDD-01

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of
pipes by HDD are as follows:

7 ROLLER SPACING DURING PULL


Allowable Bending Moment for Roller Spacing = 90% SMYS
2
= 3289.28 kg/cm
Max Tensile force that can be applied = 25 tons
P=F/As = 391.62 kg/cm2

Available Stress for Bending Fb = 2897.66 kg/cm2

Bending Moment = Z*Fb


1,439,839.04 kg-cm
This bending moment will determine the roller spacing

For Simple spans (In between Rollers) BM = wL2/12


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 1,439,839.04 x 12 / 0.501 )
= 5871.86 cm
= 58.72 meters max

For Cantilever (On last Roller) BM = wL2/2


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 1,439,839.04 x 2/ 0.501 )
= 2397.18 cm
= 23.97 meters max

8 PULLING REQUIREMENTS
Pulling loads is divided into 3 main forces. Viz:
= Fluid Drag Resistance + Soil Drag Resistance + Fluid Weight on Pull Head
= pDLf + f'wL + DbhA
= 6675.792 + 2496.25 + 405.6
= 9577.60 kg
= 9.58 Tons

Total Pulling Force Required = 10.54 Tons cosidering safety factor 1.1
% of Force Required to Rig Capacity = 42.14%