THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 278
ON SITE STAFF & LABOUR RECORD Day: Wednesday Date: 2020/7/22 ON SITE PLANT & EQUIPMENT RECORD
No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs
2 DGM 1 9 ● 2 Lorry 1 9
10 Financial Manager 1 9 3
11 Construction Staff 9 9 4
12 Office Staff 7 9 5
14 7
15 8
2 2 Formwork for the beam and slab for the " H " block part 2 area 90%
3 3 Reinforcement work of the baeams and slabs for ”H“ block part 2 area 85%
4 Formwork for the beam and slab for “E” block mezzaine floor 60%
5 5 Reinforcement work for the beam and slab for mezzanine floor 50%
6 Scaffolding work for the ground floor “F” block part 1 area 90%
REMARKS 7 Formwork for the beams and slabs for the ground floor “F”block part 1 area 60%
8 Reinforcement work for the beams and slabs for the ground floor “F” block part 1 area 40%
The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Scaffolding work for the ground floor “H” block part 3 area 45%
1
technican and local labor based the site progress and the local workers
have decreased rapidly at site. 10 Scaffolding work for the first floor ”H“ block part 1 area 50%
11 Reinforcement work for the first floor lift shaft ”H“ block 60%
Working time of the local workers has to be decreased from 9 hours to 7 hours
12 HSE work
2 for one day due to transportation problem caused by COVID-19 and they also
need more payments such as special transportation fee for their work.
Submission : Noted: