Daily Site diary & Progress Report

THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 278

Employer Engineer: Contractor

ON SITE STAFF & LABOUR RECORD Day: Wednesday Date: 2020/7/22 ON SITE PLANT & EQUIPMENT RECORD

No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs

1 Generl Manager 1 9 Weather Sunny Cloudy Rainy Windy Dusty 1 Loader 1 9

2 DGM 1 9 ● 2 Lorry 1 9

3 Contract manager 1 9 3 Mobile Crane 1 9

4 Engineering manager 1 9 Temperature Minimum:9C


8 C Maximum:28C
25 C 4 Generator 1 9

5 Safety director 1 9 5 Bar bender machine 2 9

6 MEP iManager 1 9 DELIVERY OF MATERIALS 6 Bar cutter machine 2 9

7 Construction manager 1 9 No. Material Qty. Unit 7 Concrete Pump 2 9

8 Commercial manager 1 9 1 8 Concret boom placer 2 9

9 Civil Engineer 4 9 2 9 Tower Crane 3 9

10 Financial Manager 1 9 3

11 Construction Staff 9 9 4

12 Office Staff 7 9 5

13 Site Works 190 7 6

14 7

15 8

VISITORS ON SITE DESCRIPTION OF WORKS DONE

No. Name Organization No. Qty.

1 1 Housekeeping for the basement and raining water drainage

2 2 Formwork for the beam and slab for the " H " block part 2 area 90%

3 3 Reinforcement work of the baeams and slabs for ”H“ block part 2 area 85%
4 Formwork for the beam and slab for “E” block mezzaine floor 60%

5 5 Reinforcement work for the beam and slab for mezzanine floor 50%

6 Scaffolding work for the ground floor “F” block part 1 area 90%

REMARKS 7 Formwork for the beams and slabs for the ground floor “F”block part 1 area 60%

8 Reinforcement work for the beams and slabs for the ground floor “F” block part 1 area 40%
The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Scaffolding work for the ground floor “H” block part 3 area 45%
1
technican and local labor based the site progress and the local workers
have decreased rapidly at site. 10 Scaffolding work for the first floor ”H“ block part 1 area 50%

11 Reinforcement work for the first floor lift shaft ”H“ block 60%
Working time of the local workers has to be decreased from 9 hours to 7 hours
12 HSE work
2 for one day due to transportation problem caused by COVID-19 and they also
need more payments such as special transportation fee for their work.