Professional Documents
Culture Documents
338.1 KWP Solar PV Project Proposal For pumps-WASIA-1
338.1 KWP Solar PV Project Proposal For pumps-WASIA-1
Abdullah Harakati
Building no. 2425, eng.abdullah@anpsolutions.sa.com
King Abdullah Road, Dist: As Sad, +966- 556679811
AL Madinah Al Munawara, Saudi
Arabia-42382
PROPOSAL FOR
SUPPLY OF SOLAR POWER
SYSTEM
Prepared for
The National Water Company
Riyadh, Saudi Arabia
Page | 1
CONTENT
1 INTRODUCTION 3
2 EXECUTIVE SUMMARY 3
4 DESIGN BASIS 5
7 PROJECT TIMELINE 8
8 SCOPE OF WORK 8
10 PROJECT COST 9
11 PAYMENT TERMS 10
12 WARRANTY 11
13 CONFIDENTIALITY 12
14 POINT OF CONTACT 12
ANNEXURE -I 12
BILL OF MATERIAL 12
ANNEXURE -II 13
MAKE OF COMPONENTS 13
ANNEXURE -III 14
PROPOSED SOLAR LAYOUT 14
Page | 2
1. INTRODUCTION
The National Water Company (Hereafter NWC Saudi), a Saudi joint stock company fully
owned by the government (namely the Public Investment Fund), was established to provide
water and wastewater treatment services in accordance with the latest international standards.
This is achieved by the concerted efforts of national cadres in partnership with carefully
selected international operators through foreign PPP.NWC specializes in providing the highest
quality drinking water, ensuring the presence of water and wastewater connections in all
households, preserving natural water resources and the environment, using the Treated Sewage
Effluent (TSE) with maximum efficiency, and training qualified Saudi employees in
accordance with the latest international standards.
Adapt Natural Power company (Hereafter ANP) provides onsite solar solutions for industrial,
commercial and residential customers. ANP is dedicated to discovering the creative solutions
that provide optimistic benefits to the customers to meet their rooftop/onsite solar power
requirement with in house engineering-design-procurement installation and commission
capabilities.
2. EXECUTIVE SUMMARY
To reduce the Green House Gas Emissions (Carbon Footprint) and electrical energy
consumption of Saudi electricity company (SEC), NWC Saudi is looking for a solar power
project to be installed on the ground near to water pump feeding substation building. Based on
the inputs and discussions with NWC Saudi, the solar rooftop power capacity of 338.1 kWp
can be installed on the ground near to substation.
The proposed plant is estimated to produce 600000 (sixty hundred thousand) Units (kWh)
per Annum. Payback of the system is approximately 14 years*. After payback, NWC Saudi
can avail the benefit of power at negligible cost (maintenance cost only). This project will
also help the client to reduce carbon emission by 600 (six hundred) tonnes per annum and
approx. 13900(Thirteen Thousand nine hundred) tonnes for the life of the system.
Page | 3
Following is the proposed layout of the plant.
Page | 4
4. DESIGN BASICS
1 Location Riyadh
For Detailed Bill of material (BOM), Make of components refer to annexure II, III
Adapt natural Power company will install a grid-tied solar power generation system using
ground mounted structure. Figure shows the schematic diagram of a typical grid-tied solar
system.
Sunlight captured by solar panels is converted into DC electricity. This DC Power is then
Page | 5
converted into AC power by means of grid tie inverters. This AC power is then finally
injected into existing MV electrical panel.
5.1.System Components
1. PV modules
PV modules are collections of PV cells that convert sunlight to electricity. These panels will
be mounted on module mounting structure and will be electrically connected to the bank of
inverters by means of UV resistance DC cable.
Tier-1 Quality, high efficiency>16%, and high wattage solar panels will be used in the
system. Panels are tested in accordance with IEC61215, IEC61730, TUV and UL1703
certified.
2. Grid Tie Inverters
The grid tie inverters in a solar PV power plant will converts the DC power generated by the
PV module in to suitable AC power. They have anti islanding protection thus will automates
the start-up and shut down functions as per the availability of the grid supply. By incorporating
advanced maximum power point tracking technology, it maximizes the energy harvested for
PV modules.
3. Module mounting structure
The ground mounted structure which will made up from hot dipped galvanized iron will be
used to support the Solar PV modules. The installation of structure will be done by digging the
holes in the ground and filling it by concrete of suitable grade. The Structure is designed to
withstand the wind speed as per IS875 Part 3 Code.
4. Injection of power in existing MV Panel
After analyzing an electrical Single line diagram received from the NWC Saudi, the solar
power injection will be in the existing LT panel in the substation building. The breaker at the
point of solar power injection will be provided by the NWC Saudi. The PV system will work
Page | 6
parallelly with the SEC supply and will cater to the load as per the generated power to reduce
overall SEC electricity consumption.
5. Monitoring system
A plant monitoring system will be installed which will enable permanent system monitoring
and performance evaluation. We will collect the electrical data on site via our PV monitoring
system. These data will be available for remote diagnosis. Also, we will make these data
available online to NWC Saudi.
6. PROJECT IMPLEMENTATION & SCHEDULE
Various activities under the project development and implementation are listed below (in
no particular order):
Detailed Site survey and detailed engineering design
Civil works and preliminary engineering construction (clearing, fencing, soil
exploration, ground improvement, foundations, surfacing, grading, etc.)
Rooftop PV support structure design, drawings, documentation
Safety signage
Installation, interconnection and commissioning of solar photovoltaic panels
Connection of PV array junction (combiner) box & main junction boxes
Installation and commissioning of grid-connected inverter
All DC cabling (conduits, fasteners etc.) up to inverters
AC cabling, switchgear, fuse boxes etc. from inverters to local PCC
Installation and commissioning of power evacuation system including
transmission of power from generation side to the point of connection
Installation of proper metering equipment in conformance with SEC codes
SCADA system installation and commissioning
All regulatory approvals for project and to connect to AC mains grid
Staff and client training
Operational & maintenance services
Page | 7
7. PROJECT TIMELINE
4 Weeks 7 Weeks 7 Weeks 1 Weeks
8. SCOPE OF WORK
ANP’s Scope
➢
Preparation of Engineering Drawing, Design for solar structure and solar power
plant as per relevant IS standard
➢
Supply of Solar Modules, Inverters, Structures, Cables, and Balance of Plant
➢
Installation of structure, solar modules, inverter, AC-DC cable, LT panel etc. for
solar power plant
➢
Installation of monitoring and controlling system for solar power plant.
➢
Commissioning of Solar Power Plant and supply of power to LT panel of NWC Saudi
Page | 8
9. OPERATION & MAINTENANCE OF THE PV PLANT
The Operations and Maintenance package offered by ANP company will include the following
services:
a) Performance monitoring of the PV plant
b) Remote diagnosis and failure response
c) Preventive maintenance
d) Corrective maintenance
The maintenance cost will be very small as compare to construction cost. The module cleaning
will be in the client scope and schedule for cleaning will be shared by ANP company.
Page | 9
10. PROJECT COST
Sr No Description Amount
SAR 152145
2.Installation and commissioning (One fifty-two thousand &
one hundred forty-five
Saudi Riyals only)
SAR 1521450
(one million five twenty-one
2
Total System Cost thousand & four hundred
fifty Saudi Riyals only)
Page | 10
For Installation & Commissioning:
12. WARRANTY
PV modules used in solar power plants/ systems are warranted for 10 years against any
manufacturing defect. Also, these modules are warranted for output peak watt capacity, which
will not be less than 90% at the end of 10 years and 80% at the end of 25 years from OEM.
Page | 11
OEM Warranty is applicable for workmanship against manufacturing defects, is subject to
equipment / material or part thereof not being subject to accident, alteration or improper use.
13. CONFIDENTIALITY
Except as may be required by Law, ANP and NWC Saudi will treat all information as strictly
confidential and will not disclose to any third party without prior written consent of the other,
any information which comes into their possession, the possession of their employees, agents
or others by virtue of this project
Page | 12
ANNEXURE-I
BILL OF MATERIAL
Name of the client: NWC Saudi
Project details:338.1 kWp Roof top solar Power plant
Sr. Total
Description of items to be supplied UOM
No. Qty
Page | 13
ANNEXURE-II
MAKE OF COMPONENTS
PV Modules Jinko/Risen/REC
Page | 14
ANNEXURE-III
PROPOSED SOLAR PLANT LAYOUT
Page | 15
ANNEXURE-IV
Page | 16