Adapt Natural power Company Eng.

Abdullah Harakati
Building no. 2425, eng.abdullah@anpsolutions.sa.com
King Abdullah Road, Dist: As Sad, +966- 556679811
AL Madinah Al Munawara, Saudi
Arabia-42382

PROPOSAL FOR
SUPPLY OF SOLAR POWER
SYSTEM

Prepared for
The National Water Company
Riyadh, Saudi Arabia

Adapt Natural Power Company

Date: 11 February 2020

Page | 1
CONTENT

1 INTRODUCTION 3

2 EXECUTIVE SUMMARY 3

3 BENEFITS OF ON-SITE SOLAR POWER 4

4 DESIGN BASIS 5

5 PROPOSED SOLAR PV SYSTEM 5

6 PROJECT IMPLEMENTATION & SCHEDULE 7

7 PROJECT TIMELINE 8

8 SCOPE OF WORK 8

9 OPERATION & MAINTENANCE OF THE PV PLANT 9

10 PROJECT COST 9

11 PAYMENT TERMS 10

12 WARRANTY 11

13 CONFIDENTIALITY 12

14 POINT OF CONTACT 12
ANNEXURE -I 12
BILL OF MATERIAL 12
ANNEXURE -II 13
MAKE OF COMPONENTS 13
ANNEXURE -III 14
PROPOSED SOLAR LAYOUT 14

Page | 2
1. INTRODUCTION

The National Water Company (Hereafter NWC Saudi), a Saudi joint stock company fully
owned by the government (namely the Public Investment Fund), was established to provide
water and wastewater treatment services in accordance with the latest international standards.
This is achieved by the concerted efforts of national cadres in partnership with carefully
selected international operators through foreign PPP.NWC specializes in providing the highest
quality drinking water, ensuring the presence of water and wastewater connections in all
households, preserving natural water resources and the environment, using the Treated Sewage
Effluent (TSE) with maximum efficiency, and training qualified Saudi employees in
accordance with the latest international standards.
Adapt Natural Power company (Hereafter ANP) provides onsite solar solutions for industrial,
commercial and residential customers. ANP is dedicated to discovering the creative solutions
that provide optimistic benefits to the customers to meet their rooftop/onsite solar power
requirement with in house engineering-design-procurement installation and commission
capabilities.

2. EXECUTIVE SUMMARY
To reduce the Green House Gas Emissions (Carbon Footprint) and electrical energy
consumption of Saudi electricity company (SEC), NWC Saudi is looking for a solar power
project to be installed on the ground near to water pump feeding substation building. Based on
the inputs and discussions with NWC Saudi, the solar rooftop power capacity of 338.1 kWp
can be installed on the ground near to substation.
The proposed plant is estimated to produce 600000 (sixty hundred thousand) Units (kWh)
per Annum. Payback of the system is approximately 14 years*. After payback, NWC Saudi
can avail the benefit of power at negligible cost (maintenance cost only). This project will
also help the client to reduce carbon emission by 600 (six hundred) tonnes per annum and
approx. 13900(Thirteen Thousand nine hundred) tonnes for the life of the system.

Page | 3
Following is the proposed layout of the plant.

For detailed layout of solar Plant, refer to ANNEXURE III.


*The payback period has been calculated by taking 0.18 SAR per Unit(kWh) tariff and will reduce if
there is increase in electricity tariff in future.

3. BENEFITS OF ON SITE SOLAR POWER

➢ Significant saving over the lifetime from the electricity cost.


➢ Greenpower which reduces carbon footprint.
➢ Can be injected directly into existing MV panel without any changes to the existing
system.
➢ Hassle-free operation & maintenance.

Page | 4
4. DESIGN BASICS

Sr. No Components Details

1 Location Riyadh

2 Proposed capacity 338.1 kWp DC

3 Type of system Grid Connected

4 No of modules 1 lot of 338.1 kWp

5 Type of Module Polycrystalline


6 Module Inclination As per site suitable conditions
7 Type of Inverter String Type Sine Inverter
8 Generation Voltage Sinusoidal AC

For Detailed Bill of material (BOM), Make of components refer to annexure II, III

5. PROPOSED SOLAR PV SYSTEM

Adapt natural Power company will install a grid-tied solar power generation system using
ground mounted structure. Figure shows the schematic diagram of a typical grid-tied solar
system.

Sunlight captured by solar panels is converted into DC electricity. This DC Power is then
Page | 5
converted into AC power by means of grid tie inverters. This AC power is then finally
injected into existing MV electrical panel.

5.1.System Components
1. PV modules

PV modules are collections of PV cells that convert sunlight to electricity. These panels will
be mounted on module mounting structure and will be electrically connected to the bank of
inverters by means of UV resistance DC cable.
Tier-1 Quality, high efficiency>16%, and high wattage solar panels will be used in the
system. Panels are tested in accordance with IEC61215, IEC61730, TUV and UL1703
certified.
2. Grid Tie Inverters

The grid tie inverters in a solar PV power plant will converts the DC power generated by the
PV module in to suitable AC power. They have anti islanding protection thus will automates
the start-up and shut down functions as per the availability of the grid supply. By incorporating
advanced maximum power point tracking technology, it maximizes the energy harvested for
PV modules.
3. Module mounting structure

The ground mounted structure which will made up from hot dipped galvanized iron will be
used to support the Solar PV modules. The installation of structure will be done by digging the
holes in the ground and filling it by concrete of suitable grade. The Structure is designed to
withstand the wind speed as per IS875 Part 3 Code.
4. Injection of power in existing MV Panel

After analyzing an electrical Single line diagram received from the NWC Saudi, the solar
power injection will be in the existing LT panel in the substation building. The breaker at the
point of solar power injection will be provided by the NWC Saudi. The PV system will work

Page | 6
parallelly with the SEC supply and will cater to the load as per the generated power to reduce
overall SEC electricity consumption.

5. Monitoring system

A plant monitoring system will be installed which will enable permanent system monitoring
and performance evaluation. We will collect the electrical data on site via our PV monitoring
system. These data will be available for remote diagnosis. Also, we will make these data
available online to NWC Saudi.
6. PROJECT IMPLEMENTATION & SCHEDULE

Various activities under the project development and implementation are listed below (in
no particular order):
Detailed Site survey and detailed engineering design
Civil works and preliminary engineering construction (clearing, fencing, soil
exploration, ground improvement, foundations, surfacing, grading, etc.)
Rooftop PV support structure design, drawings, documentation
Safety signage
Installation, interconnection and commissioning of solar photovoltaic panels
Connection of PV array junction (combiner) box & main junction boxes
Installation and commissioning of grid-connected inverter
All DC cabling (conduits, fasteners etc.) up to inverters
AC cabling, switchgear, fuse boxes etc. from inverters to local PCC
Installation and commissioning of power evacuation system including
transmission of power from generation side to the point of connection
Installation of proper metering equipment in conformance with SEC codes
SCADA system installation and commissioning
All regulatory approvals for project and to connect to AC mains grid
Staff and client training
Operational & maintenance services

Page | 7
7. PROJECT TIMELINE
4 Weeks 7 Weeks 7 Weeks 1 Weeks

Finalization Engineering, Solar Plant Commissioning


of Design Procurement Installation and testing
and and Supply of
Drawings Material

8. SCOPE OF WORK
ANP’s Scope

Preparation of Engineering Drawing, Design for solar structure and solar power
plant as per relevant IS standard

Supply of Solar Modules, Inverters, Structures, Cables, and Balance of Plant

Installation of structure, solar modules, inverter, AC-DC cable, LT panel etc. for
solar power plant

Installation of monitoring and controlling system for solar power plant.

Commissioning of Solar Power Plant and supply of power to LT panel of NWC Saudi

NWC Saudi’s Scope



Providing safe storage place for material during installation & commissioning period.

Provide feeder with breaker of suitable capacity to evacuate the solar power

Providing water and temporary electricity connection during execution.

Periodic cleaning of solar modules as per schedule provided by ANP co.

Providing stable internet connection to take solar plant online

Lightening Arrestor at site.

Page | 8
9. OPERATION & MAINTENANCE OF THE PV PLANT

The Operations and Maintenance package offered by ANP company will include the following
services:
a) Performance monitoring of the PV plant
b) Remote diagnosis and failure response
c) Preventive maintenance
d) Corrective maintenance
The maintenance cost will be very small as compare to construction cost. The module cleaning
will be in the client scope and schedule for cleaning will be shared by ANP company.

Page | 9
10. PROJECT COST

Sr No Description Amount

338.1 kWp Grid-Tie Solar PV system


SUPPLY PRICE
1.Solar PV modules
SAR 1369305
2.Balance of system
(One million three sixty-
-Cabling
nine thousand three
-Structure
hundred and five Saudi
-Inverters
1 Riyals Only)
-LT panel
Balance of plant
SERVICE PRICE

SAR 152145
2.Installation and commissioning (One fifty-two thousand &
one hundred forty-five
Saudi Riyals only)

SAR 1521450
(one million five twenty-one
2
Total System Cost thousand & four hundred
fifty Saudi Riyals only)

11. PAYMENT TERMS

For Supply Part:


1. 30% of supply value as advance along with PO
2. 30% before placing order of modules
3. 30 % on delivery of inverter and related accessories
4. 10% on delivery of Structures, AC/DC Cables, LT Panel and Balance of
System

Page | 10
For Installation & Commissioning:

1. 30% of I & C value as advance along with Work Order


2. 50% of I & C value against successful commissioning*
3. 20% on SCADA, completion of any punch points
*Note: Commissioning is defined as the plant is generating power and injecting
power into client’s LT Panel
All Payments shall be made within 7 working days after submission of payment
request

12. WARRANTY

The Warranty of the Solar power plant provided is as below.


A) System Warranty 2 Years
The mechanical structures, electrical works including power conditioners/inverters/charge
controllers/maximum power point tracker units, etc. and overall workmanship of the Solar
power plants/ systems is warranted against any manufacturing/design/ installation defects for
a period of 2 years.
The equipment / material and the whole system should be operated and maintained by trained
personnel of the purchaser in accordance with our recommended operating instructions and
maintenance methods. Any repairs / replacements are to be carried out by party authorized by
us.

B) Solar Photo Voltaic Modules Output a. 10 years of product warranty


Warranty b. 90% power output for 10 years
c. 80% power output for 25 years

PV modules used in solar power plants/ systems are warranted for 10 years against any
manufacturing defect. Also, these modules are warranted for output peak watt capacity, which
will not be less than 90% at the end of 10 years and 80% at the end of 25 years from OEM.

Page | 11
OEM Warranty is applicable for workmanship against manufacturing defects, is subject to
equipment / material or part thereof not being subject to accident, alteration or improper use.

C) Solar Inverter Warranty 5 Years


The Solar inverters are warranted for 5 years from the OEM.

13. CONFIDENTIALITY

Except as may be required by Law, ANP and NWC Saudi will treat all information as strictly
confidential and will not disclose to any third party without prior written consent of the other,
any information which comes into their possession, the possession of their employees, agents
or others by virtue of this project

14. POINT OF CONTACT

1)Eng. Abdullah Harakati


Project Manager
+966- 556679811

Page | 12
ANNEXURE-I
BILL OF MATERIAL
Name of the client: NWC Saudi
Project details:338.1 kWp Roof top solar Power plant
Sr. Total
Description of items to be supplied UOM
No. Qty

Solar Modules –338.1 kWp, Module efficiency more


1 1 Lot
than 16%

Module mounting structure (HDG iron With excellent


2 1 Lot
corrosion resistant structure)

Grid tied string inverter of suitable capacity – 380 V


3 AC 60 Hz (Inverter configuration will be defined 1 Lot
during detailing)

Tinned copper DC cable (4 sq mm)


4 1 Lot
(Array to Inverter- suitable for outdoor duty)

XLPE CU Cable of suitable size


5 1 Lot
(Inverter to Injection point)
6 ACDB 1 Lot
7 Earthing kit (as per IS 3043 specs) 1 Lot
8 Necessary Cable Accessories 1 Lot
9 Online Monitoring System 1 Set

Page | 13
ANNEXURE-II
MAKE OF COMPONENTS

PV Modules Jinko/Risen/REC

Inverter Fronius / Huawei/ABB

Module mounting structure Standard Make

DC cable/ AC cables if any Rescab/ LAPP or Equivalent

Junction boxes Hensel Or Equivalent

Online Monitoring & Power Control Reputed Make

Electrical components Siemens/ ABB / Reputed make

Installation Accessories Customized by ANP

Page | 14
ANNEXURE-III
PROPOSED SOLAR PLANT LAYOUT

A.3D side View of Proposed Solar Plant

B.3D Top View of Proposed Solar Plant

Page | 15
ANNEXURE-IV

TYPICAL SYSTEM CONNECTION WITH EXISTING SYSTEM

Page | 16