Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.

,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 DESIGN, SUPPLY, INSTALLATION & COMMISSIONING OF 132 kV GIS 675 days Sun 1/26/20 Tue 11/30/21
CHOVAR/MULPANI SUBSTATION

2 BASIC ENGINEERING 262 days Sun 1/26/20 Tue 10/13/20


3 SITE HANDOVER BY NEA 0 days Sun 1/26/20 Sun 1/26/20 1/26

4 CONTOUR SURVEY REPORT including Cable Route SUBMITTED 12 days Fri 8/14/20 Tue 8/25/20
5 CONTOUR SURVEY REPORT APPROVED 7 days Wed 8/26/20 Tue 9/1/20
6 SOIL INVESTIGATION (WORKS AND REPORT SUBMISSION) 30 days Mon 9/7/20 Tue 10/6/20
7 SOIL LAB TEST REPORT (APPROVAL) 7 days Wed 10/7/20 Tue 10/13/20
8 DETAIL ENGINEERING 150 days Thu 9/10/20 Sat 2/6/21
9 GENERAL ARRANGEMENT LAYOUT PLAN_SUBMISSION 21 days Thu 9/10/20 Wed 9/30/20
10 GENERAL ARRANGEMENT LAYOUT PLAN_APPROVAL 21 days Thu 10/1/20 Wed 10/21/20
11 SINGLE LINE DIAGRAM (SLD)_SUBMISSION 7 days Fri 10/30/20 Thu 11/5/20
12 SINGLE LINE DIAGRAM (SLD)_APPROVAL 15 days Thu 9/10/20 Thu 9/24/20
13 BOUNDARY WALL DESIGN N DRAWING_SUBMISSION 7 days Sun 11/8/20 Sat 11/14/20
14 BOUNDARY WALL DESIGN N DRAWING_APPROVAL 7 days Sun 11/15/20 Sat 11/21/20
15 CHAIN LINK FENCE DRAWING_SUBMISSION (If Required) 7 days Sun 11/15/20 Sat 11/21/20
16 CHAIN LINK FENCE DRAWING_APPROVAL 7 days Sun 11/22/20 Sat 11/28/20
17 SECURITY ROOM ARCHITECTURE DRAWING_SUBMISSION 7 days Sun 11/15/20 Sat 11/21/20
18 SECURITY ROOM ARCHITECTURE DRAWING_APPROVAL 7 days Sun 11/22/20 Sat 11/28/20
19 SECURITY ROOM STRUCTURE DES.N DRA._SUBMISSION 14 days Sun 11/29/20 Sat 12/12/20
20 SECURITY ROOM STRUCTURE DES.N DRA._APPROVAL 14 days Sun 12/13/20 Sat 12/26/20
21 CRB ARCHITECTURE DRAWING_SUBMISSION 7 days Mon 11/30/20 Sun 12/6/20
22 CRB ARCHITECTURE DRAWING_APPROVAL 14 days Mon 12/7/20 Sun 12/20/20
23 CRB STRUCTURE DES.N DRA._SUBMISSION 21 days Mon 12/21/20 Sun 1/10/21
24 CRB STRUCTURE DES.N DRA._APPROVAL 14 days Mon 1/11/21 Sun 1/24/21
25 FFPH ARCHITECTURE DRAWING_SUBMISSION 7 days Mon 12/7/20 Sun 12/13/20
26 FFPH ARCHITECTURE DRAWING_APPROVAL 7 days Mon 12/14/20 Sun 12/20/20
27 FFPH STRUCTURE DES.N DRA._SUBMISSION 14 days Mon 12/21/20 Sun 1/3/21
28 FFPH STRUCTURE DES.N DRA._APPROVAL 14 days Mon 1/4/21 Sun 1/17/21
29 ROAD LAYOUT_SUBMISSION 7 days Tue 11/10/20 Mon 11/16/20
30 ROAD LAYOUT_APPROVAL 7 days Tue 11/17/20 Mon 11/23/20
31 DRAINAGE LAYOUT_SUBMISSION 7 days Tue 11/24/20 Mon 11/30/20
32 DRAINAGE LAYOUT_APPROVAL 7 days Tue 12/1/20 Mon 12/7/20

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 1
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
33 EQUIPMENT STRUCTURE FOUNDATION DES N DRA_SUBMISSION 15 days Sat 1/2/21 Sat 1/16/21
34 EQUIPMENT STRUCTURE FOUNDATION DES N DRA_APPROVAL 21 days Sun 1/17/21 Sat 2/6/21
35 SUPPLY OF EQUIPMENT 786 days Mon 9/30/19 Tue 11/23/21
36 31.5/45 MVA,132/11 kV 3-PHASE POWER TRANSFORMER 660 days Sun 1/26/20 Mon 11/15/21

37 INSPECTION (COMPLETED ON NOV.'19) 7 days Sun 1/26/20 Sat 2/1/20


38 POWER TRF DISPATCH (READY FOR DISPATCH) 139 days Sun 2/2/20 Fri 6/19/20
39 DELIVERY AT SITE (REACHED AT KOLKOTA PORT) 85 days Sat 6/20/20 Sat 9/12/20
40 ERECTION & PRE-COMMISSIONING TEST 14 days Tue 11/2/21 Mon 11/15/21
41 11/0.4 kV 315 KVA LT TRANSFORMER 647 days Sun 2/2/20 Tue 11/9/21
42 STATION TRF DISPATCH (READY FOR DISPATCH) 139 days Sun 2/2/20 Fri 6/19/20
43 DELIVERY AT SITE (REACHED AT KOLKOTA PORT) 85 days Sat 6/20/20 Sat 9/12/20
44 ERECTION & PRE-COMMISSIONING TEST 5 days Fri 11/5/21 Tue 11/9/21
45 145 kV GIS EQUIPMENT 786 days Mon 9/30/19 Tue 11/23/21
46 MANUFACTURING (COMPLETED ON DEC.'19) 90 days Mon 9/30/19 Sat 12/28/19
47 INSPECTION (WAITING FOR INSPECTION SINCE JAN.'20) 7 days Thu 1/2/20 Wed 1/8/20
48 GIS DISPATCH 250 days Thu 1/9/20 Mon 9/14/20
49 DELIVERY AT SITE 50 days Tue 9/15/20 Tue 11/3/20
50 ERECTION & PRE-COMMISSIONING TEST 40 days Fri 10/15/21 Tue 11/23/21
51 120 kV SURGE ARRESTOR 640 days Sun 1/26/20 Tue 10/26/21
52 DRAWING HAS APPROVED ON JUL'19 0 days Sun 1/26/20 Sun 1/26/20 1/26

53 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Sun 11/1/20 Tue 12/15/20
54 DISPATCH 10 days Wed 12/16/20 Fri 12/25/20
55 DELIVERY AT SITE 21 days Sat 12/26/20 Fri 1/15/21
56 ERECTION & PRE-COMMISSIONING TEST 7 days Wed 10/20/21 Tue 10/26/21
57 145 kV BUS POST INSULATOR 648 days Sun 1/26/20 Wed 11/3/21
58 DRAWING HAS APPROVED ON JUNE'19 0 days Sun 1/26/20 Sun 1/26/20 1/26

59 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Sun 11/1/20 Tue 12/15/20
60 DISPATCH 10 days Wed 12/16/20 Fri 12/25/20
61 DELIVERY AT SITE 21 days Sat 12/26/20 Fri 1/15/21
62 ERECTION & PRE-COMMISSIONING TEST 7 days Thu 10/28/21 Wed 11/3/21
63 RELAY PANELS (WITH AUTOMATION) 355 days Wed 11/25/20 Sun 11/14/21
64 DESIGN N DRWING_SUBMISSION 30 days Wed 11/25/20 Thu 12/24/20

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 2
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
65 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 45 days Fri 12/25/20 Sun 2/7/21
66 MANUFACTURING (* Manufacturing might be start before the scheduled time) 90 days Mon 2/8/21 Sat 5/8/21
67 INSPECTION 7 days Sun 5/9/21 Sat 5/15/21
68 DISPATCH 15 days Sun 5/16/21 Sun 5/30/21
69 DELIVERY AT SITE 30 days Mon 5/31/21 Tue 6/29/21
70 ERECTION & PRE-COMMISSIONING TEST 21 days Mon 10/25/21 Sun 11/14/21
71 MV SWITCHGEAR 345 days Wed 11/25/20 Thu 11/4/21
72 DESIGN N DRWING_SUBMISSION 7 days Wed 11/25/20 Tue 12/1/20
73 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Wed 12/2/20 Tue 1/12/21
74 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Wed 1/13/21 Fri 2/26/21
75 INSPECTION 7 days Sat 2/27/21 Fri 3/5/21
76 DISPATCH 10 days Sat 3/6/21 Mon 3/15/21
77 DELIVERY AT SITE 60 days Tue 3/16/21 Fri 5/14/21
78 ERECTION & PRE-COMMISSIONING TEST 2 days Wed 11/3/21 Thu 11/4/21
79 SUBSTATION AUTOMATION 364 days Wed 11/25/20 Tue 11/23/21
80 DESIGN N DRWING_SUBMISSION 30 days Wed 11/25/20 Thu 12/24/20
81 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 45 days Fri 12/25/20 Sun 2/7/21
82 MANUFACTURING (* Manufacturing might be start before the scheduled time) 90 days Mon 2/8/21 Sat 5/8/21
83 INSPECTION 7 days Sun 5/9/21 Sat 5/15/21
84 DISPATCH 15 days Sun 5/16/21 Sun 5/30/21
85 DELIVERY AT SITE 30 days Mon 5/31/21 Tue 6/29/21
86 ERECTION & PRE-COMMISSIONING TEST 30 days Mon 10/25/21 Tue 11/23/21
87 TELEPROTECTION & COMMUNICATION EQUIPMENT 328 days Mon 11/30/20 Sat 10/23/21
88 DESIGN N DRWING_SUBMISSION 7 days Mon 11/30/20 Sun 12/6/20
89 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Mon 12/7/20 Sun 1/17/21
90 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Mon 1/18/21 Wed 3/3/21
91 INSPECTION 7 days Thu 3/4/21 Wed 3/10/21
92 DISPATCH 10 days Thu 3/11/21 Sat 3/20/21
93 DELIVERY AT SITE 65 days Mon 6/7/21 Tue 8/10/21
94 ERECTION & PRE-COMMISSIONING TEST 3 days Thu 10/21/21 Sat 10/23/21
95 LT SWITCHGEAR (AS PER TS) 325 days Mon 12/7/20 Wed 10/27/21
96 DESIGN N DRWING_SUBMISSION 7 days Mon 12/7/20 Sun 12/13/20

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 3
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
97 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Mon 12/14/20 Sun 1/24/21
98 MANUFACTURING (* Manufacturing might be start before the scheduled time) 30 days Mon 1/25/21 Tue 2/23/21
99 DISPATCH 10 days Wed 2/24/21 Fri 3/5/21
100 DELIVERY AT SITE 65 days Sat 3/6/21 Sun 5/9/21
101 ERECTION & PRE-COMMISSIONING TEST 2 days Tue 10/26/21 Wed 10/27/21
102 BATTERIES & FLOAT CUM BOOST BATTERY CHARGER 311 days Fri 12/25/20 Sun 10/31/21
103 DESIGN N DRWING_SUBMISSION 7 days Fri 12/25/20 Thu 12/31/20
104 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Fri 1/1/21 Thu 2/11/21
105 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Fri 2/12/21 Sun 3/28/21
106 DISPATCH 10 days Mon 3/29/21 Wed 4/7/21
107 DELIVERY AT SITE 60 days Thu 4/8/21 Sun 6/6/21
108 ERECTION & PRE-COMMISSIONING TEST 3 days Fri 10/29/21 Sun 10/31/21
109 FIRE PROTECTION SYSTEM 315 days Mon 12/7/20 Sun 10/17/21
110 DESIGN N DRWING_SUBMISSION 7 days Mon 12/7/20 Sun 12/13/20
111 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 60 days Mon 12/14/20 Thu 2/11/21
112 MANUFACTURING (* Manufacturing might be start before the scheduled time) 30 days Fri 2/12/21 Sat 3/13/21
113 DISPATCH 10 days Sun 3/14/21 Tue 3/23/21
114 DELIVERY AT SITE 60 days Wed 3/24/21 Sat 5/22/21
115 ERECTION & PRE-COMMISSIONING TEST 3 days Fri 10/15/21 Sun 10/17/21
116 CABLES ALONG WITH CABLE CLAMPS,GLANDS,LUGS & STRAIGHT JOINTS,etc. 307 days Thu 1/7/21 Tue 11/9/21

117 DESIGN N DRWING_SUBMISSION 7 days Thu 1/7/21 Wed 1/13/21


118 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 21 days Thu 1/14/21 Wed 2/3/21
119 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Thu 2/4/21 Sat 3/20/21
120 DISPATCH 7 days Sun 3/21/21 Sat 3/27/21
121 DELIVERY AT SITE 60 days Sun 3/28/21 Wed 5/26/21
122 ERECTION & PRE-COMMISSIONING TEST 40 days Fri 10/1/21 Tue 11/9/21
123 AIR CONDITIONING SYSTEM FOR CRB 259 days Mon 1/25/21 Sun 10/10/21
124 SUBMISSION OF DRWING FOR APPROVAL 7 days Mon 1/25/21 Sun 1/31/21
125 APPROVAL OF DRAWING 15 days Mon 2/1/21 Mon 2/15/21
126 MANUFACTURING (* Manufacturing might be start before the scheduled time) 21 days Thu 6/10/21 Wed 6/30/21
127 DISPATCH 7 days Thu 7/1/21 Wed 7/7/21
128 DELIVERY AT SITE 10 days Mon 8/16/21 Wed 8/25/21

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 4
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
129 ERECTION & PRE-COMMISSIONING TEST 7 days Mon 10/4/21 Sun 10/10/21
130 STEEL STRUCTURES INCLUDING TOWER STRUCTURES 240 days Thu 1/7/21 Fri 9/3/21
131 DESIGN N DRWING_SUBMISSION 7 days Thu 1/7/21 Wed 1/13/21
132 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Thu 1/14/21 Wed 2/24/21
133 MANUFACTURING (* Manufacturing might be start before the scheduled time) 42 days Tue 6/22/21 Mon 8/2/21
134 INSPECTION 7 days Tue 8/3/21 Mon 8/9/21
135 DISPATCH 10 days Tue 8/10/21 Thu 8/19/21
136 DELIVERY AT SITE 15 days Fri 8/20/21 Fri 9/3/21
137 COMMUNICATION EQUIPMENTS 342 days Mon 12/7/20 Sat 11/13/21
138 DESIGN N DRWING_SUBMISSION 7 days Mon 12/7/20 Sun 12/13/20
139 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Mon 12/14/20 Sun 1/24/21
140 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Mon 1/25/21 Wed 3/10/21
141 INSPECTION 7 days Thu 3/11/21 Wed 3/17/21
142 DISPATCH 10 days Thu 3/18/21 Sat 3/27/21
143 DELIVERY AT SITE 60 days Sun 3/28/21 Wed 5/26/21
144 ERECTION & PRE-COMMISSIONING TEST 7 days Sun 11/7/21 Sat 11/13/21
145 ERECTION HARDWARE 290 days Tue 2/2/21 Thu 11/18/21
146 DESIGN N DRWING_SUBMISSION 14 days Tue 2/2/21 Mon 2/15/21
147 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 45 days Tue 2/16/21 Thu 4/1/21
148 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Mon 6/7/21 Wed 7/21/21
149 DISPATCH 10 days Thu 7/22/21 Sat 7/31/21
150 DELIVERY AT SITE 21 days Sun 8/1/21 Sat 8/21/21
151 ERECTION 40 days Sun 10/10/21 Thu 11/18/21
152 EARTHING & LIGHTNING PROTECTION SYSTEM 295 days Mon 1/4/21 Mon 10/25/21
153 DESIGN N DRWING_SUBMISSION 10 days Mon 1/4/21 Wed 1/13/21
154 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 35 days Thu 1/14/21 Wed 2/17/21
155 MANUFACTURING (* Manufacturing might be start before the scheduled time) 30 days Thu 5/20/21 Fri 6/18/21
156 DISPATCH 10 days Sat 6/19/21 Mon 6/28/21
157 DELIVERY AT SITE 15 days Tue 6/29/21 Tue 7/13/21
158 ERECTION 50 days Mon 9/6/21 Mon 10/25/21
159 FIRE PROTECTION SYSTEM FOR TRANSFORMER 281 days Mon 1/11/21 Mon 10/18/21
160 DESIGN N DRWING_SUBMISSION 10 days Mon 1/11/21 Wed 1/20/21

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 5
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
161 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 30 days Thu 1/21/21 Fri 2/19/21
162 MANUFACTURING (* Manufacturing might be start before the scheduled time) 45 days Thu 5/20/21 Sat 7/3/21
163 DISPATCH 7 days Sun 7/4/21 Sat 7/10/21
164 DELIVERY AT SITE 15 days Sun 7/11/21 Sun 7/25/21
165 ERECTION & PRE-TESTING 15 days Mon 10/4/21 Mon 10/18/21
166 ILLUMINATION SYSTEM 303 days Fri 1/15/21 Sat 11/13/21
167 DESIGN N DRWING_SUBMISSION 15 days Fri 1/15/21 Fri 1/29/21
168 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 42 days Sat 1/30/21 Fri 3/12/21
169 MANUFACTURING (* Manufacturing might be start before the scheduled time) 15 days Tue 6/15/21 Tue 6/29/21
170 DISPATCH 4 days Wed 6/30/21 Sat 7/3/21
171 DELIVERY AT SITE 7 days Sun 7/4/21 Sat 7/10/21
172 ERECTION & PRE-TESTING 15 days Sat 10/30/21 Sat 11/13/21
173 AIR CONDITIONING & VENTILATION SYSTEM 283 days Mon 1/25/21 Wed 11/3/21
174 DESIGN N DRWING_SUBMISSION 15 days Mon 1/25/21 Mon 2/8/21
175 DESIGN N DRAWING_APPROVAL (Including Resubmission & Approval) 21 days Tue 2/9/21 Mon 3/1/21
176 MANUFACTURING (* Manufacturing might be start before the scheduled time) 30 days Thu 6/10/21 Fri 7/9/21
177 DISPATCH 4 days Sat 7/10/21 Tue 7/13/21
178 DELIVERY AT SITE 10 days Wed 7/14/21 Fri 7/23/21
179 ERECTION & PRE-TESTING 14 days Thu 10/21/21 Wed 11/3/21
180 POWER & CONTROL CABLES 250 days Sun 2/7/21 Thu 10/14/21
181 VENDOR APPROVAL 7 days Sun 2/7/21 Sat 2/13/21
182 MANUFACTURING 30 days Tue 6/15/21 Wed 7/14/21
183 DISPATCH 15 days Thu 7/15/21 Thu 7/29/21
184 DELIVERY AT SITE 7 days Fri 7/30/21 Thu 8/5/21
185 ERECTION 60 days Mon 8/16/21 Thu 10/14/21
186 CIVIL WORKS (AS PER TS) 329 days Mon 12/7/20 Sun 10/31/21
187 EARTHWORK IN CUTTING, FILLING, COMPACTION & LEVELLING 5 days Mon 12/7/20 Fri 12/11/20
188 UNDERGROUND CABLE WORKS (Including Dry Test) 60 days Wed 9/1/21 Sat 10/30/21
189 BOUNDARY WALL & MAIN GATE 50 days Sun 1/10/21 Sun 2/28/21
190 SECURITY ROOM 90 days Fri 1/15/21 Wed 4/14/21
191 CONTROL ROOM BUILDING including GIS FOUNDATION 280 days Mon 1/25/21 Sun 10/31/21
192 EQUIPMENT STRUCTURE FOUNDATION (Including TRF Foundation) 60 days Thu 2/25/21 Sun 4/25/21

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only

Page 6
Contract No.:PMD/PTDEEP/KVTCEP:073/74-01 Design,Supply, Installation and Commissioning of 132 kV GIS Substation Pinggao Group Co. Ltd.,
Drawing No.: PGG/NEA/KVTCRP_L2_CS_R01 No.22, Nanhuandong Road, Pigdishan City
Henan Province, P.R. China

ID Task Name Duration Start Finish artend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartest Quartend Quarterd Quarteth Quartes
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
193 FIRE PUMP HOUSE 90 days Sun 2/21/21 Fri 5/21/21
194 WATER STORAGE TANK 42 days Sat 5/22/21 Fri 7/2/21
195 STELL STRUCTURE ERECTION OF TOWER, AIR BUSHING, etc. 30 days Wed 9/15/21 Thu 10/14/21
196 TESTING & COMMISSIONING 4 days Thu 11/25/21 Sun 11/28/21
197 COMMISSIONING OF TRANSFORMER 1 day Thu 11/25/21 Thu 11/25/21
198 COMMISSIONING OF GIS 1 day Fri 11/26/21 Fri 11/26/21
199 COMMISSIONING OF UNDERGROUND CABLE CONNECTION 1 day Sat 11/27/21 Sat 11/27/21
200 ENERGIZATION OF SUBSTATION 1 day Sun 11/28/21 Sun 11/28/21
201 HANDOVER 2 days Mon 11/29/21 Tue 11/30/21
202 MANPOWER & EQUIPMENT DEMOBILIZATION 1 day Mon 11/29/21 Mon 11/29/21
203 REQUEST FOR ISSUE WORK COMPLETION CERTIFICATE 1 day Tue 11/30/21 Tue 11/30/21

Task External Tasks Duration-only External Tasks


Split External Milestone Manual Summary Rollup External Milestone
Milestone Inactive Milestone Manual Summary Progress
Schedule might be delayed due to impact of COVID-19.
Summary Inactive Summary Start-only Deadline
Project Summary Manual Task Finish-only