Professional Documents
Culture Documents
Failure of Titanium Lined Vessel
Failure of Titanium Lined Vessel
I
ncitec Pivot Limited (IPL) is the largest man-
ufacturer and distributor of nitrogen products well as changes to the format and structure of op-
and fertilizers on the East coast of Australia. erating procedures.
At the Gibson Island site in Brisbane, Queen-
sland, IPL operates a Vulcan urea plant, of na- Some important lessons were learned regarding
meplate capacity 640 MTPD, which has been de- operations culture and “blind spots” in relation to
bottlenecked to about 900 MTPD. equipment reliability risk assessment.
NH3 Reflux
Lean MEA
PRIMARY PRIMARY
DECOMPOSER ABSORBER
UREA
REACTOR
Urea Solution
to Evaporation
Unconverted ammonia and carbon dioxide are When the system was repressurized on startup,
treated in an anhydrous MEA (monoethanola- gas was seen coming from the telltales on T-745.
mine) separation system where they are separated
and recovered. On inspection, the titanium internal liner of T-745
was found severely damaged: bulged and buckled,
After letdown, reactor contents flow through the with a number of creases, folds and tears.
steam-heated Primary Decomposer, where uncon-
verted ammonium carbamate is decomposed, and
into the Separator T-745. Here urea solution is se-
parated from the excess ammonia and uncon-
verted carbon dioxide, which are sent to the Pri-
mary Absorber of the MEA system. T-745
normally operates at about 265 psig (1830 kPag)
and 310 oF (154 C).
The Incident
The plant had been shut down three days pre-
viously to replace a rupture disc at the inlet of the
Primary Decomposer that had failed prematurely.
This required the entire synthesis section, includ- Figure 2: Bulges and creases in bottom head.
ing T-745, to be drained and depressured.
The immediate challenge was to repair the vessel Figure 4: T-745 through-wall section
as quickly as possible, however it was essential
that we also identify the root cause and implement Internals consist of an entry pipe that provides a
preventive measures. tangential flow below a baffle and skirt, which fa-
cilitate disengagement of the urea solution from
Repairs the vapors. Apart from a cone at the vapor outlet,
there is no demister or other secondary liquid se-
paration device. The urea solution flows through a
Vessel and Liner Details
heated falling-film stripping section at the bottom.
T745 is a vertical cylindrical pressure vessel de-
signed to ASME VIII, originally fabricated by The two basic options open to us were to repair it
Wyatt Industries of Houston, Texas. It has a di- in situ or to remove the vessel to an external
ameter of 10’0” (3.05 m) with 7’7” (2.31 m) tan- workshop. In either case removal of the damaged
to-tan length, semi-elliptical ends, with a design areas was required and this commenced imme-
pressure of 300 psig (2070 kPag). The vessel has a diately.
steam jacket and a loose titanium liner to protect
the carbon steel shell from the highly corrosive
urea solution.
Protective Systems
Our initial focus was on a vacuum breaker, how-
ever we soon realized that letting air into a system
that might contain hot (and flammable) MEA was
We finally opted for an instrumented protective (A slightly different mental leap is the considera-
system, which, in summary, achieves the follow- tion of applied external pressure to vessel liners
ing: e.g. applying air pressure to a vessel’s telltale to
1. To prevent rapid vacuum formation: find an internal liner leak.)
• Shuts off the MEA flow if pressure
falls below a preset minimum (80 psig Training, Procedures and Operating Culture
or 550 kPag);
2. To prevent slow vacuum formation: Until fairly recently, our operating workforce had
• If pressure is low (< 5 psig or 35 been quite stable, with average length of service
kPag) AND the vent valve is shut, of 18-20 years, and had considerable experience.
starts a steam flow to the Primary Ab-
sorber. These older operators were predominantly trained
on the job by their predecessors and therefore
• If pressure goes negative, starts a
many had learned to complete tasks in different
steam flow to the Primary Absorber
ways.
(irrespective of vent valve position).
About 10 years ago, we set up our own internal
These responses are activated by a 2 out of 3 vot-
Training Group, and developed Training Guides
ing system in a high integrity PLC, in a system
and Competency Testing, which were applied to
with an overall SIL rating (Safety Integrity Level)
new hires and anyone learning a new plant area.
of 1.
There was also a greater focus on written proce-
General Lessons dures, and we had gone through various formats.
Our original procedures had evolved from the
Clearly, failure to adhere to our startup procedures Vulcan operating manuals, however many were
was the root cause of the vacuum event; however used as guidelines to achieve an outcome in the
there are some important lessons here that are plant, i.e. plant startup, but weren’t necessarily
broadly applicable. prescriptive on the actions to take. Consequently,
different shifts, for example, would start the plant
Risk Assessment in slightly different ways.
IPL has a strong focus on equipment risk assess-
(The smaller percentage of newer employees that
ment as a means of minimizing safety hazard and
had trained on the new system were generally
maximizing plant reliability. Nevertheless, the
more consistent in following procedures.)
possibility of vacuum occurring and causing a ma-
jor vessel failure had never occurred to anyone.
It is also probably fair to say that some of our key
Rule-of-thumb is that a vessel designed for 300
procedures were generally wordy, with a lot of
psig (2 MPag) will withstand full vacuum. T-745
specific cautions and detail about hazards to
had been designed for 300 psig (2 MPag) (and our
avoid.
Reactor for 6600 psig or 45.5 MPag). How could
such vessels fail under vacuum?
We believe that the combination of the culture of
operator discretion and the absence of a clear “DO
THIS; THEN DO THAT” message contributed to
Conclusions
1. Vessel liners may not have the same struc-
tural integrity as the vessel they form part
of, and need to be considered separately
and carefully in any risk assessment. In
particular, vacuum rating needs to be tak-
en into account, as well as applied exter-
nal pressure.