Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

7/18/2020 Quiz 002: Attempt review

Home / My courses / UGRD-CS6209-2013T / Week 4: Software Project Management / Quiz 002

Started on Saturday, 18 July 2020, 10:12 PM


State Finished
Completed on Saturday, 18 July 2020, 10:36 PM
Time taken 23 mins 11 secs
Grade 17.00 out of 20.00 (85%)

Question 1 Resources, such as people and equipment, need to do work.


Correct

Mark 1.00 out of Select one:


1.00
a. A project is an endeavor 

b. A project is temporary

c. A project is deliverable

d. None of the above

Your answer is correct.

Question 2 The process each manager follows during the life of a project is known as
Correct

Mark 1.00 out of Select one:


1.00
a. All of the mentioned

b. Project Management

c. Manager life cycle

d.  Project Management Life Cycle 

Your answer is correct.

Question 3 Which of the following is not considered as a risk in project management?


Correct

Mark 1.00 out of Select one:


1.00
a. Staff turnover

b. Product competition

c. Testing 

d. Specification delays

Your answer is correct.

https://trimestral.amaesonline.com/mod/quiz/review.php?attempt=42976&cmid=1245 1/5
7/18/2020 Quiz 002: Attempt review

Question 4 A 66.6% risk is considered as


Correct

Mark 1.00 out of Select one:


1.00
a. high 

b. low

c. very low

d. moderate

Your answer is correct.

Question 5 It refers to the budgeted amount available for the project.


Correct

Mark 1.00 out of Select one:


1.00
a. Cost constraints 

b. Money constraints

c. Budget constraints

d. Amount constraints

Your answer is correct.

Question 6 Identify the sub-process of process improvement


Incorrect

Mark 0.00 out of Select one:


1.00
a. Process distribution

b. Process analysis

c. De-processification

d. Process introduction 

Your answer is incorrect.

Question 7
Every project should have a well-defined objective. For example, many people hire firms to design and
Incorrect
build a new house, but each house, like each person, is unique.
Mark 0.00 out of
1.00

Select one:
a. A project is temporary 

b. A project has a unique purpose.

c. A project requires resources, often from various areas.

d. A project is developed using progressive elaboration or in an iterative fashion.

Your answer is incorrect.

Question 8 An independent relationship must exist between the attribute that can be measured and the external
Correct quality attribute.
Mark 1.00 out of
1.00 Select one:
True

https://trimestral.amaesonline.com/mod/quiz/review.php?attempt=42976&cmid=1245 2/5
7/18/2020 Quiz 002: Attempt review

False 

Question 9 A temporary endeavor undertaken to create a unique product, service, or result.


Correct

Mark 1.00 out of Select one:


1.00
a. Plan

b. Project 

c. System

d. Documentation

Your answer is correct.

Question 10 Projects are often defined broadly when they begin, and as time passes, the specific details of the
Correct project become clearer.
Mark 1.00 out of
1.00 Select one:
a. A project involves uncertainty

b. A project is developed using progressive elaboration or in an iterative fashion. 

c. A project requires resources, often from various areas

d. A project should have a primary customer or sponsor. 

Your answer is correct.

Question 11 Most projects have many interested parties or stakeholders, but someone must take the primary role of
Correct sponsorship.
Mark 1.00 out of
1.00 Select one:
a. A project is developed using progressive elaboration or in an iterative fashion.

b. A project has a unique purpose

c. A project should have a primary customer or sponsor 

d. A project involves uncertainty

Your answer is correct.

Question 12 Which of the following is/are main parameters that you should use when computing the costs of a
Correct software development project?
Mark 1.00 out of
1.00 Select one:
a. all of the mentioned 

b. travel and training costs

c. hardware and software costs

d. effort costs (the costs of paying software engineers and managers)

Your answer is correct.

https://trimestral.amaesonline.com/mod/quiz/review.php?attempt=42976&cmid=1245 3/5
7/18/2020 Quiz 002: Attempt review

Question 13 A project’s duration might be just one week or it might go on for years, but every project has an end
Correct date.
Mark 1.00 out of
1.00 Select one:
a. A project is deliverable 

b. A project is temporary 

c. A project is an endeavor

d. All of the above

Your answer is correct.

Question 14 Which of the following is incorrect activity for the configuration management of a software system?
Correct

Mark 1.00 out of Select one:


1.00
a. Internship management 

b. Version management

c. System management

d. Change management

Your answer is correct.

Question 15 Project managers have to assess the risks that may affect a project.
Correct

Mark 1.00 out of Select one:


1.00
True

False 

Question 16 Quality planning is the process of developing a quality plan for


Correct

Mark 1.00 out of Select one:


1.00
a. team

b. project manager

c. customers

d. project 

Your answer is correct.

Question 17 It refers to what must be done to produce the project's end result
Incorrect

Mark 0.00 out of Select one:


1.00
a. Limit constraints

b. Deliverable  constraints

c. Scope constraints

d. Output constraints 

Your answer is incorrect.

https://trimestral.amaesonline.com/mod/quiz/review.php?attempt=42976&cmid=1245 4/5
7/18/2020 Quiz 002: Attempt review

Question 18
Resources include people, hardware, software, or other assets. Many different types of people, skill sets,
Correct
and resources are needed to build a home.
Mark 1.00 out of
1.00

Select one:
a. A project should have a primary customer or sponsor

b. A project involves uncertainty

c. A project requires resources, often from various areas 

d. A project has a unique purpose

Your answer is correct.

Question 19 It refers to the amount of time available to complete a project


Correct

Mark 1.00 out of Select one:


1.00
a. Time constraints 

b. Cost constraints

c. Budget constraints

d. Duration constraints

Your answer is correct.

Question 20 Which of the following is not project management goal?


Correct

Mark 1.00 out of Select one:


1.00
a. Keeping overall costs within budget

b. Avoiding customer complaints 

c. Delivering the software to the customer at the agreed time

d. Maintaining a happy and well-functioning development team

Your answer is correct.

◄ WEEK4 - Software Project WEEK6 - Software Quality Management


Jump to...
Management - PPT ►

https://trimestral.amaesonline.com/mod/quiz/review.php?attempt=42976&cmid=1245 5/5

You might also like