20200617-KCC Container Work Plan
20200617-KCC Container Work Plan
20200617-KCC Container Work Plan
3 Condensate Export
4 KSOC Abhilash to take care of
5 KCC Containers Electrical Cabling works (See next tab)
6 OPS PA Interviews
6.01 Raghunath In-Progress 50% 3/1/2020 3/7/2020 [03/03] Interview on Wednesday- 4th March, post-lunch. Contact Mr. Ahmed.
6.02 Shijil Mohan In-Progress 20% 3/5/2020 3/15/2020 Nomination Completed
6.03 Raid Al Shukeili In-Progress 20% 3/14/2020 3/24/2020 Nomination Completed
7 DMR at CBN-9
7.01 DMR works Completions at CBN-9 Completed
7.02 DMR Firmware Compatibility Issues Completed
7.03 SAT Completed [07/03] completed on 7th March
11 GAS Export
11.01 Work Schedule Open
[03/03] Nasmatel Staff (Ted and Al Wardi) already stayed at STS Accommodation in Fahoud
11.02 Confirmation of Bed space In-Progress 50% during one of the site surveys. Names and Schedule have been given to GPS for
Accommodation booking.
11.03 Construction Activities Open
11.04 Commissioning Activities Open
Open 13
In-Progress 15
Completed 21
SUMMARY
1.07 Updates as required to documents and drawings/Uploading documents and drawings into JPI In Progress 25-Jun To be checked
3 HSE
3.01 Job Hazard Analysis (JHA) In Progress 3-Jul
3.02 Emergency/Incident Reporting Procedures Open 3-Jul
3.03 First Aiders and First Aid Box Open 3-Jul
3.04 List of PA assigned for the project (L&I) Open 3-Jul Issam/Wilson
4 Permits
4.01 L&I OPS Permit Open 26-Jun
4.02 Isolation Authority (IA) Open 12-Jul
4.03 Work Completions Open 13-Jul
6 Completions
6.01 LOSH Open To be confirmed if required or not.
6.02 Tags Validation Open To be confirmed if required or not.
6.03 ITRs Validation Open To be confirmed if required or not.
6.04 QDAC Folder Open To be confirmed if required or not.
6.05 MC Pack Folder Open To be confirmed if required or not.
6.06 SH Pack Open To be confirmed if required or not.
7 Reports
7.01 Schedule In Progress
7.02 Daily/Weekly work planning Open
7.03 Progress Update Open
SUMMARY
In Progress
Open 25
4 Completed 9
11%
In Progress 4
Completed
9
24%
Open
25
66%