Project : Zone C- Sport Field

Subject : Post Tender Queries and Clarification-1


Work : Pavilion Building-MEP Work
Contractor: Now Engineering Co.,Ltd
Date : 16 Sept, 2020

Important Note:
a. Tenderers shall answer the questions in full , not simply "yes" or "no".
In the event where there is cost implication in complying with the request stated in the questions, either for withdrawal of qualifications or for compliance with the specification /scope of work
b.
, you are to state clearly the amount involved, falling which , we shall regard it as no cost implication.
c. All post tender query replies via email to SPA on 17.9.2020 (Thursday).

Cost Impact (To make


Item Issue Tender Query Yes / No Contractor's Response
compliant)

I GENERAL

Is your quotation 100% compliant with the


1.1 Compliant Bid Drawing/Specification. Are there any deviation from the
Drawing/Specification ? If yes , please provide the list.

Confirm that you have read and understood the Drawings,


in terms of work scope and specification.

Confirm that all items indicated as "-


""NA","included","Nil","0" and left blank are considered to
be included if they are shown , described and/or implied in
the Tender Documents and Drawings, and are necessary for
the completion of the scope.

Please confirm that you are aware that this is a FIXED LUMP
SUM tender. The Tender Documents are to be taken
mutually explanatory and your offered Tender Sum shall be
deemed to have made all due allowances for works, as spelt
out or implied in the Tender Document and Drawings.

Please confirm that your Sum includes all preliminaries that


1.2 Preliminaries Cost are required offered for the proper completion of the whole
contract works.

Please confirm that , all the necessary temporary works such


as access equipment etc that are necessary to facilitate the
Contract works are included in the Contract Sum.

Please confirm that you have allowed for all associated cost
for providing offsite accommodation and fully aware that
workers quarters are prohibited on site.

Please confirm your acceptance that no increase/decrease in


Prelim cost is for any variation works to the Contract Works

Please note that Client will provide source for Water and
Electricity only, bill have to be paid by Contractor.

Please confirm contractor visited site before submission of


tender.

To confirm the scope inclusion for the mock up provision if


Mock Up
required.

Please provide details and brief explanation of your planned


1.3 Management Organization
Management Organization including the following:

a) Organization chart
b) CV's of key personal
c) Deployment / Planned time allocation (if any)

Please provide details and brief explanation of your planned


1.4 Planned Manpower
manpower including the following:
1) Total number and type of foreign workers
2) Total number and type of local workers
3) Manpower schedule
4) Explanation of planed number of teams, Foremen and so
on.

Please confirm that your acceptance on no claim for loss of


1.5 No Claim for Loss of profit
profit for any omission works from Your Contract

1/3
Project : Zone C- Sport Field
Subject : Post Tender Queries and Clarification-1
Work : Pavilion Building-MEP Work
Contractor: Now Engineering Co.,Ltd
Date : 16 Sept, 2020

Important Note:
a. Tenderers shall answer the questions in full , not simply "yes" or "no".
In the event where there is cost implication in complying with the request stated in the questions, either for withdrawal of qualifications or for compliance with the specification /scope of work
b.
, you are to state clearly the amount involved, falling which , we shall regard it as no cost implication.
c. All post tender query replies via email to SPA on 17.9.2020 (Thursday).

Cost Impact (To make


Item Issue Tender Query Yes / No Contractor's Response
compliant)

1.6 Insurance Please confirm you have allowed for any insurance.

Please confirm that you will take up all the necessary


insurances for your own plant and equipment brought into
the jobsite and provide a Public Liability insurance with
coverage of not less than US $ 1 million or could approve
and sign on "Letter of Undertaking of Insurance" refer to the
attachment.

The Contractors has effected a Contractor All Risk Insurance


and Workmen Compensation Insurance.

To confirm that you are aware that the following works


1.7 Warranty require the full list of warranty to be submitted to the
Employer.

Genearl Warranty Minium 2 years for materials, equipments and workmanship.

1.8 Technical data/Specification Please submit Technical Data and Specifciation.

Please confirm that you have reviewed as per attached


1.90 Responsibility Matrix
Responsibility Matrix.

Please advise the cost impact of including all taxes in your


1.10 Tax Exclusion
bid , ensure you define each type of tax

Submitted qotation included the commerical tax.

Please confirm that your submitted price are included for


any other work or equipment not mentioned in the Price
1.11 Scope of work Breakdown, but which are mentioned in the Drawings and
Specifications and are required to complete the works as
whole.

Please confirm that you have clearly understand attached


scope of work and cost impact are considered in the
submitted price.

Please note that Description in the Price Breakdown are


indicative only.You have the full responsibility to assure and
confirm the compliance.

Please confirm that you will comply with the following


1.12 Payment Terms
payment terms:

Proposed payment terms: 20% 1st payment, final payment


80% after 100% of progress,Retention Sum -10% of each
progress payment , capped at max 5% of contract sum
including Variation.

Holding Retention 5%, shall be released upon end of Period


for notifying defects (2 years) from overall project
completion.
2.5% after 12months from issurance of Taking Over
Certificate.
2.5% after 24months from issurance of Taking Over
Certificate.

Payment Duration: Payment claim shall be certified within


14 calendar days upon receipt of contractor's claim and
payment shall be made within 46 calendar days upon recipt
of Contractor's undissputed invoice.

Please confirm that you will provide cash flow forecast for
our review and approval prior to the submission of the 1st
payment claim.

Currency of payment: Myanmar Kyats

Not Applicable for rate of interest.

2/3
Project : Zone C- Sport Field
Subject : Post Tender Queries and Clarification-1
Work : Pavilion Building-MEP Work
Contractor: Now Engineering Co.,Ltd
Date : 16 Sept, 2020

Important Note:
a. Tenderers shall answer the questions in full , not simply "yes" or "no".
In the event where there is cost implication in complying with the request stated in the questions, either for withdrawal of qualifications or for compliance with the specification /scope of work
b.
, you are to state clearly the amount involved, falling which , we shall regard it as no cost implication.
c. All post tender query replies via email to SPA on 17.9.2020 (Thursday).

Cost Impact (To make


Item Issue Tender Query Yes / No Contractor's Response
compliant)

Please confirm you have allowed to prepare all


remaining/alternative detailing via the shop drawing review
1.13 Shop Drawings and approval process. Ie. Shop Drawings prepared by the
Tenderer for YDG PMS/Design review and approval, no
further drawing will be prepared by YDG PMS/Design.

Are you able to complete the works within the timeframe


1.14 Programme
(2nd week of October to 2nd week of November).
To confirm the inclusion of touch up or make good of any
1.15 Coordination work damage to the core & shell elements to handover
requirement.

To confirm the work scope inclusion of providing necessary


1.16 Protection work
protections to the existing core & shell work.

To confirm the work scope inclusion of providing as built


1.17 As built Drawing and O&M manuals drawings, O&M manuals according to this tender
requirement/ Catalogue.

2 SAFETY PROVISIONS

Please confirm that you have included the provision of


2.1 Safety officer , PPE
safety officer , coordinator & PPE in your Tender Price.

II COMMERCIAL

Please note that the proposal quotation shall be valid


1 Validy
minium period of 1month.

Total