Daily Progress Report (DPR) From Proejct Engineer of PHC: S.E. (Mumbai / TNK/ Pune/ AN/ NAG Regional Office)
Daily Progress Report (DPR) From Proejct Engineer of PHC: S.E. (Mumbai / TNK/ Pune/ AN/ NAG Regional Office)
7 Structural Consultant As and When Required Water Supply and Drainage Engineer--B.E
Management Information System (MIS)/ Planning
8 Electrical Consultant As and When Required Engg. B.E
9 Water Supply and Drainage Consultant As and When Required Quantity Surveyor (QS) / Billing Engg., B.E
Safety Engineer, Advance Diploma in Induatrial
10 Geotechnical Consultant As and When Required Safety/ Certificate Course of NICMAR
11 Consultant for MOEF/CRZ As and When Required Supervisors, Safety Steward as per Requirement Mr. Mahesh T Bhave Supervisor
12 Consultant for Lft, Fire As and When Required Surveyor and Asst. Surveyor
Quality Assurance (QA) / Quality Control (QC) Lab
13 In Charge