Engineering Department
Manual
Contents
INTRODUCTION.................................................................................................................................................................. 3
ORGANIZATION STRUCTURE AND JOB DESCRIPTIONS.......................................................................................................4
TRAINING AND DEVELOPMENT..........................................................................................................................................6
TOOLS MANAGEMENT.......................................................................................................................................................8
PURCHASING AND STOCK CONTROL..................................................................................................................................9
COMMUNICATIONS WITHIN THE DEPARTMENT..............................................................................................................11
ANNUAL PREVENTIVE MAINTENANCE PROCEDURE.........................................................................................................14
BUSINESS CONTINUITY PLAN...........................................................................................................................................18
CHECKING AND CHANGING LAMPS..................................................................................................................................34
CHILLER MAINTENANCE...................................................................................................................................................35
CONTRACTORS WORKS....................................................................................................................................................36
FIRE ALARM SYSTEM TESTING..........................................................................................................................................37
FIRE EXTINIGUISHERS.......................................................................................................................................................38
FIRE SPRINKLER SYSTEM TESTING....................................................................................................................................39
GENERATOR MAINTENANCE............................................................................................................................................40
HOW TO ENTER A GUEST ROOM.....................................................................................................................................41
KEN-FIX IT PROGRAM.......................................................................................................................................................42
LEGIONELLA DISEASE PREVENTION..................................................................................................................................43
LIFT MAINTENANCE.........................................................................................................................................................48
Master Filing System........................................................................................................................................................49
MAINTENANCE REQUEST SYSTEM...................................................................................................................................55
OCCUPATIONAL SAFETY AND HEALTH.............................................................................................................................57
OPEN FLAMES.................................................................................................................................................................. 59
SIGNAGES......................................................................................................................................................................... 60
TOUR OF THE HOTEL........................................................................................................................................................61
WATER TEST..................................................................................................................................................................... 63
2
INTRODUCTION
As part of the hotel entity, engineering department has specific roles/purpose why it is existing as one of the
operational departments. A hotel requires a huge amount of investment by the owner /owing company. This
investment as a facility needs to be kept in excellent condition at all times for the service life it is designed to
exist.
It is therefore the most important function of the department to maintain the looks, the services, furniture and
equipments of a hotel in an excellent condition.
All hotels provide guest services by consuming resources like electricity, water, gas, fuel, etc which we
collectively call Utility. It is also the responsibility of the department to make sure the consistent supply of
utilities and to monitor their consumption, to make sure that there is a minimized wastage and later minimize
the utility costs to a reasonable amount.
Finally it is safety. Safety to the guests we serve, safety to the employees who are working in the hotel and
safety to the environment we operate in at large which mainly concern the department.
The operating procedures are compiled together as a department manual together with the organization
structure and manning plan.
3
Chief Engineer
Asst Chief Engineer
Electrician- 5
4
Civil technician-3 G.Mechanic-
Chief Engineer 1
Asst Chief Engineer 1
Engineering Coordinator 1
Civil Technician 3
Handy Man 1
Total 17
Introduction
Purpose
5
To insure that there is a continual development process to all engineering staff members through
familiarization knowledge and skill trainings. Trainings also enable to set a bench mark for operating standards
and to make sure all are performing up to the set standards procedure.
Two types of trainings will be given to all staff within the department
Planned training
This training will be a scheduled training which will be divided into two.
The regular departmental training plan will be given to all as a briefing and orientation when new employees
join the department. In addition even Saturday morning is the date for departmental training from the basic
systems down to the individual equipments one by one throughout the year.
A preplanned schedule training mainly on skills covered under the OJS training. A training subject will be
developed based on the gap analysis observed during operation. Training sessions will be developed and
training will take 15-20mins per trainee. OJS training is a skill training which focuses on enabling trainees
achieve the skill to do one task to the standard via a structured training sessions in a very short time. It does not
include transferring knowledge, knowledge trainings should be given before hand on a specific subject before
conducting OJS training.
Giving an OJS or regular training does not make the trainee perfect by itself. During normal operations, there
are chances to observe performance gaps in trainees on subjects which trainings have been given. When such
gaps are observed an unplanned coaching and guidance on the spot will be conducted to all engineering staff. It
is this follow up and coaching which will enable the staff to meet the performance standards set.
Competence Chart
After the planned trainings, a competence chart will be filled to see in what areas one staff is competent and
which areas need to be covered for him/her to be efficient. In addition it will be used to assist the HOD to
determine to whom to assign a specific job based on their competency. The competence chart will also used as
guide line for performance evaluation.
6
TOOLS MANAGEMENT
Purpose: To set a clear procedure on how available engineering tools are utilized within the department to
provide consistent repair and maintenance service.
Procedure
7
All tools should only be issued by the engineering department. No personal tools should be used during
operation unless in special situations and approved by the HOD.
Any gift tools from suppliers or contractors should be reported to HOD and should be given to the engineering
department.
Everyone should carefully handle the tools provided to him with utmost care and proper usage.
Any tools lost should be reported immediately to HOD for further follow up and investigation.
Individual tools: to be kept in duty engineers and all other technicians individually and they will sign on the
tools receiving logbook for every tool that they receive with an individual responsibility.
Duty engineers - common tools: This common tool box will be managed in group by the duty engineers. The
key to the common duty tool box is to be transferred from one shift to the next during the duty briefing.
Mechanical common tools: This common tool box will be managed in group by the mechanics. The key to
the common mechanical tool box is to be transferred from one shift to the next during the duty briefing.
Civil Technicians common tools: This common tool box will be managed in group by the civil technicians.
The key to the common civil technician tool box is to be transferred from one shift to the next during the duty
briefing.
Work shop and Heavy tools: These tools will be managed by the engineering coordinator and will be kept in
engineering store. Tools which are taken from the store will be signed by the requesting technician and these
tools should not be kept personally, should be returned on the same date to the engineering coordinator.
Purpose: To insure that there is a smooth supply of spare, consumable and replacement items without
discontinuity of service to our internal and external customers.
Purchasing: The purchasing flow for procuring engineering consumables and spare parts will be mainly based
on the maintenance control system.(MC)
8
Regarding the request, the engineering coordinator will be mainly responsible and in his/her absence
ACE/supervisors will be in charge.
Moring briefing
Maintenance request
New projects
All supervisors and technicians are expected to report in writing the details of the requested item and the
expected delivery date.
The pending purchasing items will be updated on weekly basis and submitted to HOD for follow up with the
purchasing department. The supervisors and engineering coordinator will be following up regularly with the
purchasing and on critical and important items they can ask for assistance from the HOD.
When an item is purchased, the engineering coordinator is responsible for receiving and before signing off,
he/she has to liaise with the requester/ supervisor/Ass. CE/ HOD for confirmation that the item delivered is up
to the quality required.
Stock control
Stock control for the engineering store is a vital process which will enable the department activities of repair
and maintenance to proceed without any flows to meet the guest expectation.
Procedure
Stock control will mainly be the responsibility of the engineering coordinator and the following steps should be
followed.
Index the shelves into rows and columns and determine the location of the items.
Develop the bin-card and fill the above information including the existing quantity at the time of filling the
stock item information.
Whenever an item is received and/or issued the engineering coordinator will be in charge of balancing and if
the quantity of a given item reaches the minimum value to initiate the purchase request.
Chemical stores
9
The same procedure above applies to the chemical storing but chemicals used in engineering systems, should
be stored in a separate location which is ventilated and not in contact with other stock items. The chemicals
should be kept in a place where they are protected from spoilage, falling or moisture.
A manufacturer recommended, material safety data sheet (MSDS) should be listed for each chemical type
including the following information.
Name of chemical
Physical property
Chemical property
Health hazards
Fire hazards
Disposal
Purpose: As an operational department, communication plays a major role to provide a consistent service to
our internal and external customers. A lot of responsibility lies on the engineering department and
miscommunication can endanger the continuity of business.
1. Monthly Departmental meeting: this will be a scheduled monthly meeting with the presence of HR
manager mainly focusing on
10
Review of the department’s operation
Preventive maintenance
Ken-fix-it program
Duty roster
Attendance
Projects
Utility consumption
Open discussion
Morning briefing
Every morning at 8:00 AM there will be a morning briefing with normal shift and duty technicians, which will
take 15-20 mins.
Job assignment
A specific job will be assigned to each technician and supervisor. Each technician is expected to know what
job is assigned to him and the expected delivery date/time
The delayed job assignment will be made by the ACE or supervisors in his absence and will be read out loudly
to each technician.
Projects
General notices
Safety
Guest comment
Water
11
Electricity
Gas
Diesel
Temp
The daily utility consumption will be recorded in a utility consumption report logbook by the morning shift
duty technicians.
Afternoon and night briefings will be carried out between the shift and supervisors. The list of performed and
pending jobs will be communicated, including duty room cards, keys, duct phones etc.
Reports
A monthly compiled utility consumption report will be submitted to the finance department and a copy will be
kept in the engineering dept.
Diesel consumption
Water consumption
Gas consumption
Log Book
One of the main communication methods for the department is the logbook. The logbook is expected to be
filled by each engineering staff about every activity performed, remarks, observation, message etc. Each
engineering staff is expected to read and sign on the log book daily.
It is especially the duty engineer’s duty to read and also write their daily report about executed jobs, pending
jobs, special requests by other departments etc.
12
General log book – for all public area, back of house and all areas with the exception of guest rooms.
Guest room log book – will be used for activities performed in a guest room. The reason for separating this
logbook from the general one is that guest related jobs and urgency without any miscommunication.
Check lists
Check list will be developed to be used by the duty technicians while they are doing tour of the hotel. The
check lists have to be used on each duty shift and if there are irregularities observed, they have to be
communicated to the immediate supervisor/ACE/CE depending on the criticality of the situation. These
findings of irregularities have to be recorded and must be highlighted in the logbook.
Depending on the situation they are in a duty technician might need to change his shift duty. Since engineering
department is operational for 24 hrs 7 days a week, a strict policy is required to be set to maintain a consistent
service.
Any duty technician who wants to change his schedule has to come with a replacement request form filled and
signed. The shift change has to be checked by the ACE and only upon the approval from the HOD can the shift
change be allowed.
Shift change requests should be filled at least 3 days before the requested date of change.
Lieu days are days earned on which an employee has worked extra day like in holidays, weekly day offs and
collective extra hours. These extra days have to be compensated by taking leave which we call lieu day
clearing.
Lieu day clearing has to be requested by the requester at least 4 days before the actual date of leave to ensure a
smooth replacement.
Upon request, the ACE will check if the lieu day clearing is possible and will update the duty roster
accordingly. Finally upon approval by the HOD the lieu day clearing can be taken.
Introduction
Preventive maintenance is a schedule of planned maintenance actions aimed at the prevention of breakdowns
and failures and to keep the property and its contents in excellent condition at all times. This document is
intended as a guide line for setting up and running a hotel maintenance organization.
Purpose
13
The primary goal of preventive maintenance is to prevent the failure of equipment before it actually occurs and
to keep the product in good shape. It is designed to preserve and enhance equipment reliability by replacing
worn components before they actually fail. The ideal preventive maintenance program would prevent all
equipment failure before it occurs.
Procedure
The following procedures should be followed to develop a fully fledged preventive maintenance plan;
Technical fact sheet of the hotel: This sheet has to be prepared and contains the total built-in area, plot area
and area schedule of the hotel.
Technical Inventory: (Facility and Equipment register) a technical inventory of the whole plant and all
equipment installed must be prepared as per the submitted As-Built drawings, equipment schedules and
manuals. The inventory should contain the following information;
Equipment name
Location
Technical specifications
Serial No.
The program shall be a regular scheduled program to inspect, service and repair all facilities and equipment
A chart of the schedule of weekly , monthly, quarterly, Semi-annual and annual maintenance activities of all
the plant, laundry, kitchen, bar equipment should be prepared as per the manufacturer’s recommendations of
each equipment.
WEE
EQP K
T EQPT. NO.> 0 1
14
NO. NAME
HOT WATER
RECIRCULATIO
N PUMP – 1 A C
HOT WATER
RECIRCULATIO
N PUMP – 2 A C
STORM WATER
PUMP A D D C D
STORM WATER
PUMP A D D C D
STORM WATER
PUMP D A D D C D
STORM WATER
PUMP D A D D C D
STORM WATER
PUMP D A D D C
STORM WATER
PUMP D A D D C
Maintenance procedure
Maintenance procedures and a preventive maintenance plan as per the manufacturer’s recommendations must
be prepared for each piece of equipment. The maintenance manuals and catalogues will be used in preparing
the required plan. Please see the example below.
15
Equipment: Grease Interceptor Manufacturer: Model / Type:
Supplier :
S.No 1 7 15 1 2 3 4 6 1
Maintenance History Card: A maintenance history card for each piece of equipment will be prepared. The
history card will contain the following information;
Technical Details
Location
Equipment Number
Details of the maintenance works done( indicating any spare parts used)
The name and signature of the technician carrying out the work
After the execution of a maintenance and repair work, the history card must be filled and signed off by the
technician who has performed the work.
Effective work allocation to maintenance staff by the Engineering supervisor as per the preventive
maintenance plan and schedule though work order sheets
16
Name and location of equipment
Date
Date of Completion
Comments
Primary objective
Secondary Objectives
17
To analyze the emergency risks to the business
18
Business Impact Analysis
Affect on Service:
Mitigation in place
Check if power interruption is not due to own equipment-substation, cabling, panel board etc...
First 24 hours Contact EEPCO to get information on the fault and expected power outage duration
Verify that all equipment connected to Generator power supply is functional and disconnect all
non essential loads.
Consult the GM in relation to the ability of the generator sets to continue working
Shut down for 1 hour and check oil, temperature, noise etc.
Up to 1 week
Up to 1 week
19
Business Impact Analysis
Affect on Service:
Mitigation in place
Check the levels in the water tank and ensure the minimum required for
fire fighting purpose
Contact Utility company AAWSA( Addis Ababa Water and Sewer
Authority) and find out the expected time to recover from the interruption
First 24 hours
Inform the GM and all concerned parties
Consult with GM on closing high water consumption areas like Laundry,
Steam generator and Stewarding areas
Record on the log book activities carried out
Up to 1 week
Resources
Time No. of staff Relocation? Data required
required
Contact list
First 24 hours 1 No Manual for
Pumps
Up to 1 week
20
Business Impact Analysis
Affect on Service:
Mitigation in place
Up to 2 weeks
Contact list
Alternative
Up to 1 week 1 No
suppliers list
21
Business Impact Analysis
Time Effect on Service: Ranges from partial to complete hotel service interruption
Mitigation in place
Evaluate the cause and devise plan of action by consulting with the GM to reinstate the
service interrupted.
24 – 48 hours
Mobilize all available resources (including other hotels or similar entities) to resolve
the issue.
Up to 1 week
Resources
Time No. of staff Relocation? Data required
required
22
Spare parts, Contact list
Tel/ Internet
Up to 1 week
23
Business Impact Analysis
Affect on Service:
Mitigation in place
Assign a replacement
Resources
Time No. of staff Relocation? Data required
required
Contractors
24 – 48 hours 1 No and suppliers
list
Up to 1 week
24
Critical Function: Drainage / Sewer line blocked/flooding
Affect on Service:
Mitigation in place
Contact contractors or suppliers of the sewer system by consulting with the General
Manager
24 – 48 hours Come to a contractual agreement with selected sanitary service providers
At the end restore the sewer system, clean other systems damaged as a result of the
blockage and make sure they are in good condition.
Up to 1 week
Resources
Time No. of staff Relocation? Data required
required
Contact list
24 – 48 hours 1 No Contractors and suppliers
list
Up to 1 week
25
Critical Function: Close a floor/area for emergency reasons
Affect on Service:
Mitigation in place
Up to 1 week
Guarantee’s lis
Contact list
27
Risk Matrix Score
Risk Matrix
Hazard Impact
Score
28
Priority Critical Function
10
This list can be used during an emergency to assist your decision making when compiling an Action Plan as to
which function needs to be reinstated first.
29
Emergency Response Checklist
30
Arrange a Debrief:
31
Key Contact Sheet
Log Sheet
32
CHECKING AND CHANGING LAMPS
33
Purpose
To maintain all lamps in public area, guest floor and back areas, functional at all times of the hotel operation
Procedure
Areas to cover
Back office area, bar, restaurant, lobby, lifts, cafeteria, executive lounge, Staff canteen, Substation, MDB
room, Security room
Electricians in every shift will check the areas specified above and check and replace faulty lamps by
consulting the relevant department
A check list will be prepared and all finding shall be filled on it.
Missing lamp types should be immediately reported to the chief engineer for purchase processing
CHILLER MAINTENANCE
Purpose:
34
To keep the Chillers in our hotel free of trouble and keep them in an excellent condition to guarantee that they
are always operating at the peak efficiency.
Procedure
To have an AMC for the maintenance of the Chillers with an approved HVAC contractor.
Specialized trade should be carrying out the maintenances for continuously carrying preventive and service
maintenances
The chillers must be inspected by every shift person and to fill in the specified log sheets.
Any malfunction noted during the shift inspection must be logged in properly and to notify CE / ACE
immediately
CE/ ACE to liaise with the contractor for any breakdown of the chillers
In case of a complete chiller failure or temporary maintenance services a proper sign should be kept on the
chiller concerned stating “Do not operate, Equipment out of order"
Engineering department should coordinate with the service contracting company for the immediate trouble
shooting of the chillers.
All the service reports must be filed and available in the Eng. Office.
CONTRACTORS WORKS
PRIMARY OBJECTIVE:
35
To ensure all the contractors carries out their specified work in an orderly manner maintaining safety of the
guest and staff, causing minimum disturbance to the hotel operation.
PROCEDURE:
Ensure proper agreement between the contractor and the hotel exist
To brief the contractor of the timings of their work in relation to the area they are working
Ensure to assign a hotel staff accompany the contractor if the work involves a guest occupied area,
Engineering Dept. to notify the concerned Dept if the work involves a guest occupied area, like FO, F&B, Spa,
etc.
Contractors must be provided with an area for their lunch breaks if needed
Ensure to give standby services if the work affects the services to other areas of the hotel
Ensure that the contract staffs use all eqpts. safely and the eqpts are well protected
Primary objective:
To ensure the fire alarm system is thoroughly checked at specified intervals by an authorized service company.
36
Procedure:
To have an appropriate “Annual Maintenance Contract” for the periodic service of the fire alarm system, with
a competent and authorized service company
The service company to liaise with security control room for any testing or repair work.
Any detectors / MCP found defective during the inspection and service, must be rectified or replaced
immediately.
To ensure spares for the system is always available with the co. and must be available to replace any defective
spares at any time.
Any defective or damaged detectors / MCP units found at any time, the service company must be called in for
immediate rectification or replacement.
Any defects in the fire alarm system must be notified to the civil defence control room
FIRE EXTINIGUISHERS
Primary objective:
To ensure all the portable fire extinguishers are properly serviced at the specified intervals by an authorized
service company.
37
Procedure:
To have an appropriate “Annual Maintenance Contract” for the periodic service of all portable fire
extinguishers, with a competent and authorized service company
All the fire extinguishers to be serviced every six months and tagged by the service company
Any Extinguishers found defective during the inspection and service, must be rectified or replaced
immediately.
Spare fire extinguishers must be available to replace any defective extinguishers at any time.
All the extinguishers must be marked with the location, type and size of the extinguisher.
Any used or damaged extinguishers found at any time, must be sent to the service company for immediate
rectification or replacement.
The list of the fire extinguishers must be available in the Engineering and security office.
Primary objective:
To ensure the fire sprinkler system is thoroughly inspected and tested at specified intervals by an authorized
service company.
Procedure:
38
To have an appropriate “Annual Maintenance Contract” for the periodic service of the fire sprinkler system,
with a competent and authorized service company
The service company to liaise with security & Engineering Dept for any testing or repair work on the sprinkler
system.
Any spares found defective during the inspection and service, must be rectified or replaced immediately, as per
the service contract.
To ensure spares for the system is always available with the co. and must be available to replace any defective
spares at any time.
The sprinkler pumps – Electrical and Diesel pumps must be tested every month and the sprinkler head must be
tested annually.
Any defective or damaged components found at any time, the service company must be called in for immediate
rectification or replacement.
GENERATOR MAINTENANCE
Purpose:
To keep the Generators in our hotel free of trouble and keep them in an excellent condition to guarantee that
they are available for emergency power supply.
Procedure
39
To have an AMC for the maintenance of the Generators with an approved Electrical contractor.
Specialized trade should be carrying out the maintenances for continuously carrying preventive and service
maintenances
Generator problems are priority 1, and should be attended with utmost urgency
The Generator must be tested on a monthly basis and maintain athe test reports
In case of a complete Generator failure or temporary maintenance services a proper sign should be kept on near
to the generator concerned stating “Do not operate, Equipment under service"
Engineering department should coordinate with the service contracting company for the immediate trouble
shooting of the Generators.
All the service reports must be filed and available in the Eng. Office.
Objective:
To ensure that all guests in-house respect their privacy while staying in their room, all staff that needs to enter
the guestroom will follow the standard and procedure consistently. Always be aware that when the guest stays
in the hotel the room given is his/her home away from home.
Procedure
40
Try go get the name of the guest and make sure you pronounce it correctly.
Knock on door: Check the presence of DND "Do Not Disturb" sign, check if it is double lock, if no DND sign,
then proceed to your business. Knock the door 3 times with your knuckles and identify yourself "Engineering"
and your intention.
If no reply within 30 second, knock again and announce yourself the second time.
If no reply, knock again and open the door at the same time say "Good Morning, Good Afternoon or Good
Evening" and identify yourself.
If the guest presence in the room, explain what is your purpose of visit.
Always give the guest an option by offering him/her to comeback: Ask the guest what convenient time for the
service you offer.
When entering the guestroom always leave the door open by using door stopper. Never close the door while
you were inside the room.
At the end your shift such as DND rooms, Double locked, Refuse service etc. has to be reported to the
Housekeeping Supervisor along with the Room Attendant report accompany with all important information.
KEN-FIX IT PROGRAM
Introduction
The Ken-Fix-It (“KFI”) program is the Hotel’s guest room and public area maintenance program.
Guest satisfaction is directly tied to the quality of the Hotel’s physical appearance.
41
The Ken-Fix-it prorgram aims to keep the guest rooms,guest floors and all the public areas in excellent shape
at all times through routine and planned inspections,maitenance & repair works.
Procedures:
A Ken-Fix-Team will consist of multi-skilled technicians, typically a carpenter and an electrician, who are
trained to do minor repair and maintenance for all trades.
Usually, two Ken-Fix-It teams will be required, i.e. one in the guest areas and one in the back of house areas.
Each team will have a trolley containing several shelving to accommodate spare parts and engineering
consumables, such as lamps, screws, pipe fittings etc. The trolley will have rubber tires and swivel casters.
Uniforms worn by the team: The Ken-fix-it team technicians should wear a different uniform than the other
technical staff; more presentable, better in quality as they will be in front of the guest view at all times.
Programs for regular room and public area inspection &maintenance need to be prepared. These programs
should be prepared taking into consideration the size and type of the hotel.
The guest area inspections and maintenance other than the guest rooms should be completed in maximum four
to five days.
The back of house areas should be completed in maximum a week time. (Weekly turnover is one)
Daily house tours in the guest areas and back of house areas will be carried out by the Ken-Fix- It team to
instantly correct any noted deficiencies on the floors, walls, ceilings or furniture. A pre-determined amount of
guest rooms will be taken daily as “out of order” status –depending on the size and occupancy levels of the
hotel-to carry out deep maintenance.
Legionnaires' disease is a form of pneumonia that is caused by inhalation or aspiration of bacteria that belong
to the family Legionellaceae. Legionellosis is most commonly linked to exposure to Legionella pneumophila;
however, other species can cause the disease as well.
42
Legionella can be found in stagnant and unsanitised water sources. This could include decorative water
fountains, pools/ponds and standing water and in cooling towers. Legionella has also been found in improperly
maintained swimming pools and whirlpools.
Legionella and other bacteria can be controlled by maintaining sanitized water at all times. Water which is not
sanitized can become an attractive medium for growth. The appearance of algae or other growth should be a
warning sign for the potential presence of Legionella.
The illness can often be fatal and the publicity attracted by such cases is highly damaging to both the tour
operator and the hotel.
Signs of illness usually appear 3 to 6 days after infection but may take longer.
Risk vector:
generates Aerosols
C: a target: a person
DISTRIBUTION
A
ORIGIN TARGET
ا Inhalation
Legionella Prolifération ا
Symptoms:
The illness usually starts with a fever, chills, headache and muscle pain.
43
This is followed by a dry cough and breathing difficulties that in some persons will progress to a
severe pneumonia.
About a third of those infected will also have diarrhea or vomiting and about a half become confused or
delirious.
In order to make an accurate diagnosis specific medical laboratory tests must be undertaken and may need
repeating.
In most cases this Will not occur until after the guests have returned home
Water tanks
Cooling towers and evaporative condensers, even if situated on the roof or in the grounds
PURPOSE:
The preventive actions will ensure that the risk for Legionella disease is maintained at minimum at all times.
The risk of Legionnaires' disease can be minimized by implementing the Legionella prevention program.
PROCEDURES:
44
This program is controlled by the Engineering department and the Engineering department is fully responsible
for its implementation.
Prevention procedures: The prevention procedures that must be adapted are as follows;
Keeping hot water hot and circulating at all times: 50˚C - 60˚C. Keeping cold water: below 20˚C (although the
EC Directive on the quality of water intended for human consumption permits water to be supplied to premises
at temperatures up to 25°C).
Note: In practice, the water temperature is likely to be well below this maximum value (in the order of 5 -
10°C in winter and up to 20°C in summer). However, during a prolonged hot summer, the incoming water
temperature can become abnormally warm. If the incoming water is above 20°C, the incoming water should be
pre-cooled to 22 °C.
Running all taps and showers in unoccupied guest rooms for several minutes at least once a week and always
prior to occupation.
Keeping shower heads and taps clean and free from scale
Cleaning and disinfecting cooling towers and associated pipes used in air conditioning systems regularly - at
least twice a year
The AC filters and cooling coils of all AHUs and FCU should be disinfected on regular bases.
Cleaning and disinfecting all water filters regularly - every one to three months
Cleaning and disinfecting the shower heads in the guest room bathrooms on quarterly bases.
Inspecting the inside of cold water tanks at least once a year and disinfecting with 50mg/l chlorine and clean if
containing a deposit or otherwise dirty
Do not panic.
Do not disclose the contamination incident to anyone other than the GM. Instruct the local water treatment
consultant/lab to keep the results strictly confidential.
45
Do not shut down the water supply immediately. Remember that the bacteria exist since the day of the water
samples were taken. Non-essential equipment such as spa pools, fountains could be switched off.
Guests should be informed that a shock chlorination is to take place for "routine disinfection of the plumbing
networks" and that they should not drink, wash their teeth and take shower for the disclosed period of time
Circulate water containing 50-60 mg/l free available chlorine or another oxidizing biocide for 6 hours.
Maintain absolute minimum of 20 mg/l at any time during this period. Staff must wear full pressurized
respirators.
Refill with fresh water, circulate with 20-25 mg/l free available
De-chlorinate and drain, drain, refill and decommission the water treatment program.
Disinfect all shower heads/ hoses in the hotel. To be done manually with peroxide or other chlorine tablets.
Soak for 10-15 minutes, in a big recipient in a solution of water and peroxide or chlorine tablets. Buy 4 to 5
new shower heads and shower hoses to allow rotation with the disinfected ones.
After the problem has been solved (following results), regular analysis must be done at least 3 times a year.
When the results are clear for one year, go back to normal maintenance procedures.
Hot water pipes not insulated and close to cold water-pipes(T°C of cold water to room must be maintained to
+/-20°C),
If the hot water circulation loop is not well done ( Heat tracing system could be investigated to maintain min
hot water T°)
46
LIFT MAINTENANCE
Purpose:
To keep the lifts in our hotel free of trouble and keep them in an excellent condition to guarantee that they are
available for guest service
47
Procedure
Specialized trade should be carrying out the maintenances for continuously carrying preventive and service
maintenances
Lift problems are priority 1,( related to Guest) and should be attended with utmost urgency
When a lift fails to operate with a guest inside, immediate actions should be taken to get the guest out of the lift
safely.
i.e. either the service contracting company and/or the engineering department should work together to get the
guest out of the lift by using emergency procedures
In case of a complete lift failure or temporary maintenance services a proper sign should be kept on the lift
lobby near to the lift concerned stating " Do not operate, Equipment under service"
Engineering department should coordinate with the service contracting company for the immediate trouble
shooting of the lifts.
Primary objective
The purpose of this procedure is to establish the method how files in records are identified, collected, indexed,
accessed, filed, retained, protected, and stored properly.
48
Procedures
File categories
All files shall be organized into logical groups, separate color labels/binders will be used to differentiate
between each category, which relate to the functions and activities of the department. Records in a filing
system shall be categorized as follows
Also known as operation protocols. Documentation used on daily basis when operating hotels
Electrical(Yellow Labels/Binders)
Mechanical(Green Labels/Binders)
Each second level category of process has its own number sequence that ranges from 01 to 99.
49
Clearly identifying the year of creation.
Categorize the records based on the specific Department / Service / Sections and these are designated by two to
three uppercase English Alphabets as Follows.
Code Department
ENG Engineering
Two digit numerical codes starting from 01 to 99 shall be assigned to each process/activity identified in each
Second level category.
Table 1
008 Security
50
015
Every file shall be allocated a file number and year of creating clearly identifying the years the file
remained active.
Company Logo
AAA (ENGINEERING)
Additi
nal Identification
The Second Level Category
Assign a unique identification number for each activity/process
aA
001
File Serial Number
01
Unique Number for Each File within Each Third Category
Note:
The number of second level category files within one box shall not exceed three files.
Each file shall have its own File Content Summary registration Form.
All files accessed shall be controlled by recording their status on File/Record Movement Control Form, to
ensure an easy identification about who possess the file and /or whether a file is returned or not
Access control
All confidential records shall be handled and stored confidentially. The access to such records shall be
approved by the Chief Engineer.
52
A person who wants to have an access to confidential records shall raise a request clearly describing his/her
reasons on File/Movement Control Form and he/she may have an access to such records only when he/she has
adequate reasons and authorized person approves his/her request.
Access controlled records shall be stored in an area where their confidentiality is secured i.e. in locked filing
cabinets and/or in separate rooms where entry of unauthorized individuals is restricted.
S.N. Access Controlled Records Reasons for Access Location Authorized Persons
Controlled
Note:
Authorized persons have an access to confidential records without any prior approval of their access and they
have the responsibility to maintain the confidentiality of such records
File closing
Files are closed using File closing form when the file becomes full or when the process associated to the file
terminates.
Storage of files
All engineering records shall be filed and stored in an office environment unless specific media and/or special
environmental control are specified to prevent damage, deterioration, or loss and allow access control.
All records shall be physically or electronically filed by a method which enhances accessibility and retrieval by
a user. If electronic files are used a back-up system or other suitable measures shall be used to prevent records.
53
Photocopy the original ensuring enough copies for all subjects represented in the original.
Register each copy of the records to the file to which it has been attached, and note that it is a copy.
Related documents:
Primary objective
To have all “Furniture Fixtures & Equipment” and the structures always well maintained and to speed up
reinstate Broken, worn out or “Out of Order” items.
54
To ensure all the repairs carried out in the property is well monitored and recorded for proper maintenance
history.
Policy:
1 All Departments to enter their R&M related complaints in the MR system, in the shared drive.
2 Only “Repair & Maintenance” nature defects related to an existing structure, furniture, fixtures or
equipment only must be entered in the MR. System.
3 The Department responsible for the concerned area must originate the MR. All the repairs must be
carried out through the MR system only.
4 Any “Non-R&M” nature jobs, such as any new items, any modifications, new installations, re-
locations, etc and any damaged / broken items should not be entered in the MR. System.
4a Non-R&M Jobs: “Maintenance Request” forms, depending on the nature of the work, as attached, to
be filled by the concerned Department Head and must be approved by GM. Such work will not be treated as
top priority. Do not process MR for such cases.
5 All the Guest complaints must be received properly by the Front office / Housekeeping / F&B and to
notify Duty Engineer via Dect phones set for immediate rectification. Engineering Dept. treats this type of
defects as top priority. Such defects must be in 2 category.
5a Category 1: Engineering Department recommends to enter all R&M related jobs in the MR system, But
Guest complaints such as fused bulbs, drain blockage, TV. Channels, etc. may not be entered in the MR.
System. However the job
completion must be checked with the Duty engineer, by the originator. R&M Department won’t be responsible
for such calls, if the details given verbally is incomplete.
5b Category 2: Guest complaints such as A/C noisy, A/C not cooling, No hot water, etc must be entered in
the MR system, for easy follow ups and proper completion.
6 All R&M related complaints must be received through MR system and NO oral comments / complaints
to be accepted by Engineering, except for No. 5 category.
Procedure
An MR must be entered in the system immediately on noticing malfunction, faulty or wear and tear damage on
any existing FF&E or property structure by the operating department concerned.
55
“MR.” Must be entered in the shared drive, strictly following this procedure.
The “MR” must be completed fully, mentioning the location, equipment name / No., nature of breakdown, and
the name of the person entering the MR.
The Engineering Department will carry out the “MR” on “first come first serve basis” and level of priority.
“MR” for urgent matters must be notified by phone to Engineering supervisor or ACE.
One “MR” per job must be made. Will not accept “MR” with more than one job written in the same line.
R&M Dept. to check the incoming “MRs” every 4Hrs., during the Day shift and once in the evening shift.
Eng. Sups / Eng. Co-ordinator to assign the Jobs to Technicians, marking the priority, 1, 2 & 3.
Technician will carry out the Job and mark completed in the status column.
If the Jobs cannot be carried out due to unavailability of spares, right manpower, no access, etc, the status of
the same must be marked in the status column.
Eng. Sup / Shift leader to discuss the status of all “MR”, with CE. On a daily basis..
Due to Busy period or major breakdowns there will be situations when R&M Dept. cannot handle all in-
coming “MRs”. and there will be pending “MRs”. Therefore a follow up system must be maintained by all
departments to be always aware of the status of the item given for repair.
It is recommended that one senior supervisory staff from each department is made responsible for following up
“MR” on a weekly basis, to avoid everybody approaching Engineering Department.
The follow up must be on a regular basis, and the HOD concerned to meet CE on long pending items, for
discussion and necessary actions.
Purpose
The purpose of this procedure is to set the guide lines for creating a working environment free from accident
and injuries.
Procedure
56
All employees will be provided with Protective equipment and other safety materials and will be required to
use it properly at all times.
An Occupational Safety and Health Committee shall be formulated as per the directive laid by the Ministry of
Labor and social affairs within 6 months of the opening of the hotel.
Annually prepare plan and budget for Occupational Safety and Health activities
Identify areas where a continuous follow up is required and carry out close follow up and report to the
employer.
Ensure all information is gathered on near miss, near hit, accident and diseases observed in the hotel and plan
and act on the prevention of such.
Assess complaints raised by the employees in various areas regarding safety and health in relation to their job
and advise the employer together with the solutions.
Organize, conduct and evaluate training programs with each department on Occupational safety and Health
procedures.
Arrange a media for the management and employees to discuss on Occupational safety and health within the
hotel
Evaluate the Occupational Health and safety policy of the hotel and advise for improvement.
Make sure posters for the prevention of occupational accidents and injuries are posted in all areas required.
To facilitate and work together with safety inspectors coming from the appropriate authority
All employment accidents and occupational diseases will be recorded and will be reported to the ministry/
regional bureau.
Continuous trainings will be given on Occupational Safety and Health directive issued by the Ministry of
Labor and Social affairs, once in two weeks to the whole staff together with the Occupational safety and health
committee.
Reference:
Occupational Safety and Health Directive, by Ministry of Labor and Social Affairs.
57
Labor Proclamation No. 377/2003
OPEN FLAMES
Primary objective:
To ensure safety when open flames are used for any engineering works.
Procedure:
Any jobs involved with open flames, must have prior approval of the Chief Engineer.
58
The eqpt. / Torch must be checked for proper operation prior to commencing the job.
Make sure to use minimum amount of fuel for the job, store away the balance fuel if any.
To ensure there are minimum 2 people available for such hazardous jobs.
Appropriate fire extinguishers must be brought to the work area, before starting the work.
On completion of such work, ensure to keep the eqpts, fuel, etc at the designated area.
All the Ashes or any other disposals of the flame / fire must be disposed properly as necessary
SIGNAGES
Purpose
To maintain all hotel signage, exterior and interior to ensure they are properly placed, well lit and they are
always in good condition to ease the guest movement and contribute the overall Guest perception of the hotel.
Procedure
All Signs will be inspected by the night shift technicians and routine maintenance carried out
59
Signage to check are, all hotel areas, Fire escape signs, Directional signs, Safety signs, etc.
A full report on the maintenance carried out shall be filled in a log sheet.
All service reports must be filed at Eng. and made available at all times.
Primary objective:
The primary objective of this document is to set the guide line on the continuous daily tour of the hotel by the
Engineering department
Procedure:
The tour of the hotel will be carried out by the engineering department three times a day by each shift
personnel i.e. Morning, Afternoon and Night.
60
The following areas of focus shall be considered while carrying the tour of the hotel
Safe and proper operation of critical equipments like substation, transformer, MDB, Plant room and Chillers
and AHU
The tour of the hotel will be carried by the engineering department staff as assigned by the CE during day time
(Morning and afternoon) and by the duty technician during night time
Generator area
Substation
MDB
M&E area
Lobby area
Plant room
Roof and
Every time a tour is made a log sheet to be filled in inclusive but not limited to the time started and finished,
areas covered and observations collected including the name and signature of the person who carried out the
tour shall be included.
61
WATER TEST
Primary objective:
The domestic water is regularly tested to ensure the water is safe for utilization for our Guest, maintaining the
required standards.
Procedure:
Ensure to have a contract with an approved Laboratory to carry out the tests.
62
The Mechanical sup. to lease with the company to take water samples at the set times.
The samples to be taken from Kitchen, Guest rooms, Spa, water tanks, etc.
Based on the test results and advice, necessary action to be taken on improving the quality of water.
The Laboratory responsible must certify that the water concerned is suitable for utility or not.
All the original test results must be filed in the Eng. Office.