Hand Book For Civil Engineer

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

Consumption of Materials

For Building Works As Per CPWD DSR


Brick Aggregate (Cum)
Cement (Nos)/ Sand
Item For
(Bag) Stone (Cum) 40mm 20mm 10mm
(Cum)
RCC M-30 1Cum 6.80 0.425 0.57 0.28
RCC M-25 1Cum 6.60 0.425 0.57 0.28
PCC (1:1½:3) 1Cum 8.00 0.425 0.57 0.28
PCC (1:2:4) 1Cum 6.40 0.445 0.67 0.22
PCC (1:3:6) 1Cum 4.40 0.47 0.70 0.24
PCC (1:4:8) 1Cum 3.40 0.47 0.65 0.24
PCC (1:5:10) 1Cum 2.60 0.47 0.65 0.24
Cement Mortar 1:1 20.40 0.72
Cement Mortar 1:2 13.60 0.95
Cement Mortar 1:3 10.20 1.07
Cement Mortar 1:4 7.60 1.07
Cement Mortar 1:5 6.20 1.07
Cement Mortar 1:6 5.00 1.07
Brick Work in 1:4 1Cum 1.90 494 0.268
Brick Work in 1:6 1Cum 1.25 494 0.268
Half brick masonry 1:3 10Sqm 2.856 565 0.30
Half brick masonry 1:4 10Sqm 2.128 565 0.30
CR (Ist Short) in 1:6 1Cum 1.50 1.21 0.321
CR (2nd Short) in 1:6 1Cum 1.50 1.10 0.321
RR in 1:6 1Cum 1.65 1.00 0.353
CC1:2:4 Flooring 40mm th 10Sqm 3.40 0.178 0.267 0.089
--Do-- 52 mm th 10Sqm 4.62 0.178 0.267 0.204
--Do-- 62 mm th 10Sqm 4.90 0.222 0.334 0.226
12mm Plaster 1:4 10Sqm 1.09 0.15
12mm Plaster 1:6 10Sqm 0.72 0.15
15mm Plaster 1:4 10Sqm 1.31 0.18
15mm Plaster 1:6 10Sqm 0.86 0.18
20mm Plaster 1:4 10Sqm 1.70 0.24
20mm Plaster 1:6 10Sqm 1.12 0.24
Provision for Formwork in Concrete Items-
As Per MORD Data Book
in Foundation (Chapter 11) - 4% already included in Rate Analysis
in Substructure (Chapter 12) - 10% already included in Rate Analysis
in Superstructure (Chapter 13) - For Height up to 5m 20% already included
- For Height 5 to10m 25%
- For Height above 10m 30%
Consumption of Materials
For Road Work as Per MORD Data Book

For Brick Aggregate (Cum)


Cement (Nos)/ Sand
Item
(Bag) Stone (Cum) 40mm 20mm 10mm
(cum)
PCC M-10 (1:3:6) 1Cum 5.00 0.48 0.576 0.288 0.096
PCC M-15 (1:2½:5) 1Cum 5.50 0.48 0.48 0.24 0.08
PCC M-20 (1:2:4) 1Cum 6.60 0.45 0.36 0.36 0.18
RCC M-20 1Cum 7.00 0.45 0.54 0.36
RCC M-25 1Cum 8.08 0.45 0.54 0.36
RCC M-30 1Cum 8.60 0.45 0.54 0.36
Brick Work in 1:3 1Cum 2.448 500 0.252
Brick Work in 1:4 1Cum 1.824 500 0.252
Brick Work in 1:5 1Cum 1.488 500 0.252
CR (Ist Short) in 1:3 1Cum 3.06 1.10 0.315
CR (Ist Short) in 1:4 1Cum 2.28 1.10 0.315
CR (Ist Short) in 1:5 1Cum 1.86 1.10 0.315
CR (2nd Short) in 1:3 1Cum 3.366 1.10 0.315
CR (2nd Short) in 1:4 1Cum 2.508 1.10 0.315
CR (2nd Short) in 1:5 1Cum 2.046 1.10 0.315
RR in 1:3 1Cum 3.366 1.00 0.315
RR in 1:4 1Cum 2.508 1.00 0.315
RR in 1:5 1Cum 2.046 1.00 0.315
Pointing 1:3 10Sqm 0.306 0.032
15mm Plaster 1:4 10Sqm 1.824 0.252
WATER BOUND MACADAM SUB-BASE/BASE/SURFACING
Compacted Loose Per cent by
Classificati Size IS Sieve
Thickness in Quantity weight
on Range Designation
mm Cum passing
125 mm 100
1.21 90 mm 90-100
90 mm to
Grading 1 100 mm to 63 mm 25-60
45 mm
1.43 45 mm 0-15
22.4 mm 0-5
90 mm 100
0.91 63 mm 90-100
63 mm to
Grading 2 75 mm to 53 mm 25-75
45 mm
1.07 45 mm 0-15
22.4 mm 0-5
63 mm 100
0.91 53 mm 95-100
53 mm to
Grading 3 75 mm to 45 mm 65-90
22.4 mm
1.07 22.4 mm 0-10
11.2 mm 0-5
RATE OF APPLICATION OF BINDER FOR TACK COAT
Type of Surface Quantity of emulsion ( per Sqm Area)
Normal Bituminous surfaces 0.20 to 0.25 Kg
Dry and hungry bituminous surfaces 0.25 to 0.30 Kg
Granular (primed) 0.25 to 0.30 Kg
Cement Concrete Pavement 0.30 to 0.35 Kg

20 mm THICK PREMIX CARPET (Qty for 10 Sqm)


Qty. of By
By Bitumen
Aggregate Emulsion
Nominal size 13.2 mm 0.18 Cum 9.50 Kg 14.0 Kg
(passing 22.4 mm sieve and retained on 11.2 mm sieve)
Nominal size 11.2 mm 0.09 Cum 5.10 kg 7.5 Kg
(passing 13.2 mm sieve and retained on 5.6 mm sieve)
Total 0.27 Cum 14.60 Kg. 21.50 Kg

SEAL COAT (Qty for 10 Sqm)


Quantity of Graduation requirement Bitumen in Emulsion in
Type
aggregate Passing sieve Retained sieve kg kg
Type A 0.09 Cum 11.2mm 2.36mm 9.8 12-14
Type B 0.06 Cum 2.36mm 180micron 6.8 10-12
Type C 0.09 Cum 9.5mm 2.36mm @ 4.5% 9-11

Roller Output
GSB & G1 10 Cum per Hr.
G2 & G3 08 Cum per Hr.
PC 250 Sqm per Hr.

Removal of Form work (Stripping Time)


Equivalent Plain Areas of Uneven Surface
(for measuring painting, varnishing, oiling etc. of joinery and steel work etc.)

Please Refer CPWD Specification for Detail Explanatory Notes


Explanatory Notes:-
(1) Measurements for doors windows etc., shall be taken flat (and not girthed) over all
including chowkhuts or frames, where provided. Where Chowkhuts or frames are not
provided, the shutter measurements shall be taken.
(2) Where doors, windows etc., are of composite types other than those included in Table
the different portion shall be measured separately with their appropriate coefficients,
the center line of the common rail being taken as the dividing line between the two
portions.
(3) The coefficients for door and windows shall apply irrespective of the size of frames and
shutter members.
(4) In case steel frames are used the area of doors, windows shutters shall be measured
flat excluding frames.
(5) When the two faces of a door, window etc. are to be treated with different specified
finishes, measurable under separate items, the edges of frames and shutters shall
be treated with the one or the other type of finish as ordered by the Engineer-in-
Charge and measurement of this will be deemed to be included in the measurement
of the face treated with that finish.
(6) In the case where shutters are fixed on both faces of the frames, the measurement for
the door frame and shutter on one face shall be taken in the manner already
described, while the additional shutter on the other face will be measured for the
shutter only excluding the frame.
(7) Where shutters are provided with clearance at top or/and bottom each exceeding 15
cm height, such openings shall be deducted from the overall measurements and
relevant coefficient shall be applied to obtain the area payable.
(8) Collapsible gates shall be measured for width from outside to outside of gate in its
expanded position and for height from bottom to top of channel verticals. No
separate measurements shall be taken for the top and bottom guide rails rollers,
fittings etc.
(9) Coefficients for sliding doors shall be the same as for normal types of doors in the
table. Measurements shall be taken outside to outside of shutters, and no separate
measurements shall be taken for the painting guide rails, rollers, fittings etc.
(10) Measurements of painting as above shall be deemed to include painting all iron
fittings in the same or different shade for which no extra will be paid.
(11) The measurements of guard bars, expanded metal, hard drawn steel wire fabric of
approved quality, grill work and gratings, when fixed in frame work, painting of which
is once measured elsewhere shall be taken exclusive of the frames. In other cases
the measurements shall be taken inclusive of the frames.
(12) For painting open palisade fencing and gates etc., the height shall be measured from
the bottom of the lowest rail, if the palisades do not go below it, (or from the lower
end of the palisades, if they project below the lowest rail), up to the top of rails or
palisades whichever are higher, but not up to the top of standards when the latter
are higher than the top rails or the palisades.
Deductions in measurements for opening etc.-
(a) No deduction will be made for openings or ends of joists, beams, posts, girders, steps etc. upto
0.5 sqm in area and no additions shall be made either, for the jambs, soffits and sills of such
openings. The above procedure will apply to both faces of wall.
(b) Deduction for opening exceeding 0.5 sqm but not exceeding 3 sqm each shall be made for
reveals, jambs, soffits sills, sills, etc. of these openings.
(i) When both faces of walls are plastered with same plaster, deductions shall be made
for one face only.
(ii) When two faces of walls are plastered with different types of plaster or if one face is
plastered and other is pointed or one face is plastered and other is un-plastered,
deduction shall be made from the plaster or pointing on the side of the frame for the
doors, windows etc. on which width of reveals is less than that on the other side but
no deduction shall be made on the other side.
Where width of reveals on both faces of wall are equal, deduction of 50% of area of
opening on each face shall be made from area of plaster and/or pointing as the case
may be.
(iii) For opening having door frame equal to or projecting beyond thickness of wall, full
deduction for opening shall be made from each plastered face of wall.
(c) For opening exceeding 3 sqm in area, deduction will be made in the measurements for the full
opening of the wall treatment on both faces, while at the same time, jambs, sills and soffits will
be measured for payment.
In measuring jambs, sills and soffits, deduction shall not be made for the area in contact
with the frame of doors, windows etc.

You might also like