Professional Documents
Culture Documents
Owner-S: Permanent Lining and Support in Fault Zones
Owner-S: Permanent Lining and Support in Fault Zones
Owner-S: Permanent Lining and Support in Fault Zones
ne
Site Investigation, Design & Construction
tiv nd
ow
ec rla
of Hydro & Transport Tunnels
e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013
ir w
he - S
Permanent Lining
ft n
O tio
and support in fault zones
© a
n nd
tio ou
ra F
tiv nd
ow
ec rla
e
sp e
re itz
Basis for implementation of sprayed concrete based
ir w
tunnelling
he - S
Active design, a concept of hard rock tunnelling
ft n
O tio
Sprayed concrete linings in adverse rock mass
conditions © a
n nd
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Basis for implementation of sprayed concrete
r-s
based tunnelling
ne
tiv nd
ow
Some specific principles that we take into
ec rla
e
sp e
account in Hard Rock tunnelling and unlined
re itz
tunnelling
ir w
he - S
Self supporting capacity of the rock mass
ft n
O tio
The thermal capacity of the rock mass
© a
n nd
The impermeable capacity of the rock mass
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
• Basis for implementation of sprayed concrete
r-s
based tunnelling
ne
tiv nd
ow
Fundamentals of tunnelling
ec rla
e
sp e
The construction is a reversed process
re itz
ir w
The remaining from the construction process is the
he - S
constructive element that takes loads, absorbs stresses and
ft n
O tio
is tight
© a
n nd
Challenges:
tio ou
/construction?
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Basis for implementation of sprayed concrete
r-s
based tunnelling
ne
tiv nd
ow
In this context sprayed concrete is an ideal material:
ec rla
Sprayed concrete offers a variety of properties!!
e
sp e
re itz
Identify project needs/site conditions, specify requirements
ir w
he - S
accordingly;
ft n
O tio
Geological conditions are given; sprayed concrete capabilities can be
© a
n nd
designed
tio ou
ra F
Observe the variety in stiffness for steel bolts, rock mass and
sprayed concrete
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
Postulate: “Sprayed concrete is basically water, cement and
e
sp e
re itz
aggregate. Start from this basis, identify required properties and
ir w
use additives and fibres where required to obtain them”
he - S
Materials properties
ft n
O tio
Bond, strength, stiffness, ductility, permeabilitet
© a
n nd
Product properties
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Basis for implementation of
r-s
ne
sprayed concrete based
tiv nd
ow
tunnelling
ec rla
e
sp e
Clarification of a term
re itz
ir w
he - S
”Unlined” Tunnelling!
Permanent rock support consists of rock
ft n
O tio
bolts and sprayed concrete
© a
n nd
Primary support is approved as permanent
tio ou
on the condition that it meets the material
standard
ra F
st T
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Basis for implementation of sprayed
r-s
ne
concrete based tunnelling
tiv nd
ow
ec rla
e
sp e
re itz
Some call it;
ir w
he - S
Sprayed concrete based tunnelling
ft n
Single shell sprayed concrete lining
O tio
SCL – Spray concrete lining © a
n nd
tio ou
r-s
1. It’s selfstanding capacity, i.e. the ability of the rock mass to
ne
tiv nd
maintain stability even after being subject to cavities being
ow
ec rla
made, man made or natural.
e
sp e
re itz
•“Stand-up” time implies that the rock mass is not a dead load.
ir w
he - S
Engineering approach to take this capacity into account.
•Rock strengthening may be needed to secure specified
ft n
O tio
capacities
© a
n nd
The mining industry learned
tio ou
span:
llu E
lI C
* Were Stable
©
ne
tiv nd
ow
2. It’s impermeable nature, i.e. the actual permeability of the rock
ec rla
mass and associated discontinuities: vary 10-5m/sec to 10-
e
sp e
re itz
12m/sec.
•A typical jointed aquifer, water
ir w
he - S
occurs on the most permeable
ft n
discontinuities.
O tio
•The permeability of rock mass
© a
n nd
may be in the range of 10-8 m/sec.
tio ou
r-s
3. It’s stress induced confinement, the in-situ stress situation
ne
tiv nd
may vary from stress released rock bodies through a pure
ow
ec rla
gravitational stress situation to stresses resulting from long
e
sp e
re itz
tectonic history of the rock mass.
ir w
he - S
What made the Gjøvik hall
ft n
feasible??
O tio
Sufficient high horizontal
© a
n nd
stress!!
tio ou
gravity approach
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
What characterises a hard rock regime?
ne
tiv nd
4. It’s thermal capacity, i.e. the capacity to store energy
ow
ec rla
over significant amount of time.
e
sp e
re itz
An useful and important
ir w
he - S
property for:
ft n
•Cold storage eg. food
O tio
•Cooled/chilled gas storage
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
What characterises a hard rock regime?
r-s
ne
The Scandinavian host rock: poor
tiv nd
ow
ec rla
to extremely good rock.
e
sp e
Folding, faulting and high tectonic
re itz
ir w
stresses influence the quality of
he - S
the rock
ft n
Weakness zones can exhibit
O tio
© a great variation in quality, Q-
n nd
values; extremely poor to good
tio ou
ra F
r-s
ne
tiv nd
The rapid (???) technological development of
ow
ec rla
e
sprayed concrete enforces the users to specify its
sp e
re itz
correct applications
ir w
he - S
Incorrect specification and application may cause
ft n
O tio
more harm than good, particularly as far as
© a
n nd
maintaining a positive reputation of the method
tio ou
required, indeed
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Sprayed concrete is basically water, cement &
aggregates. Start here, identify relevant
r-s
ne
properties and add fibre, additives as required!
tiv nd
ow
Typical specifications:
ec rla
e
sp e
40 MPa final strength
re itz
ir w
he - S
45 MPa final strength in e.g. sub-sea part
ft n
Min. thickness of 80 mm (Norw. Road Authorities .spec)
O tio
© a
n nd
MA-very aggressive, W/C ratio < 0,45
tio ou
r-s
ne
'Fast’; very high early strength; high cement
tiv nd
ow
ec rla
content and accelerator
e
sp e
re itz
‘Stiff’; high early & final strength; high cement
ir w
he - S
content and microsilica
ft n
‘Ductile’; high ductility & low stiffness; low/
O tio
© a
moderate cement content, high fibre, microsilica
n nd
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Overview of properties of sprayed
ne
concrete in various geological conditions
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Typical mix design
ne
tiv nd
ow
Improvements open new possibilities! Are we able to
ec rla
utilise these opportunities or do we specify yesterdays
e
sp e
re itz
products
ir w
Challenge of the
he - S
designer/owner to
ft n
O tio
choose mix design and
© a
n nd
product behaviour based
tio ou
on project needs
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Sprayed concrete properties should be selected
r-s
after an evaluation of whether one or several
ne
tiv nd
ow
mix designs will best fit the project conditions
ec rla
e
sp e
A typical example would be a traffic tunnel, requiring
re itz
ir w
Allow no rock fall to the carriageway
he - S
ft n
Allow exposed rock surface where rock mass quality is OK
O tio
© a
Durability to ensure service life of 50 years, or more
n nd
tio ou
Solutions
lI C
Al ITA
ne
tiv nd
constitute a tunnelling method ”Single shell shotcrete lining”
ow
ec rla
e
sp e
Active design
CROSS SECTION LONGITUDINAL SECTION
re itz
Previous holes New holes
ir w ~3m
1 Ground water control
he - S
TUNNEL
ft n
~3m
O tio
~20 m Overlap
Alternativ
Pre-grouting
Alternativ
with 2 holes with 3 holes min. 6 m
© a
n nd
Impervious zone, reduce water gradient
tio ou
2 Cautious blasting
llu E
lI C
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Active design
ne
tiv nd
ow
3 Empirical guidelines and analytical/numerical modelling
ec rla
e
Several empirical methods at hand, Q, RMR etc
sp e
re itz
Numerical modelling is a powerful tool
ir w
Design verification and assessment and follow-up
he - S
4 Observations and monitoring
ft n
O tio
Visual observation of rock/shotcrete surfaces is first step
© a
n nd
Convergence pins, extensometers etc are second step
tio ou
5 Working procedures
st T
llu E
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Active design
r-s
ne
6 Drained structure
tiv nd
ow
Support measures not designed to take the hydrostatic load
ec rla
e
Excessive water is not allowed to build up behind support
sp e
re itz
Controlled handling and discharge of water
ir w
he - S
7 Primary support approved as permanent
ft n
Primary support is normally securing safe working conditions
O tio
Apply rock support that fulfils the specs for permanent work
© a
n nd
Do as much as possible close to the tunnel face
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Active design adaptability
r-s
ne
Establish geological model on information at hand prior to
tiv nd
ow
excavation works.
ec rla
e
sp e
A predefined set of rock support classes based on, for example,
re itz
empirical guidelines.
ir w
he - S
A sound verification of these support classes by utilisation of
analytical and/or numerical models.
ft n
O tio
A quantitative rock mass classification (e.g. the Q-system).
© a
n nd
A confirmed procedure for the application of support classes,
tio ou
modifications if needed.
©
r-s
ne
tiv nd
Today’s tunneling industry sets forth a
ow
ec rla
number of pre-requisites:
e
sp e
re itz
Flexibility, adaptability, experience, cost
ir w
he - S
efficiency and decision making at the tunnel
ft n
face.
O tio
© a
The tunnelling shall allow: reliability,
n nd
tio ou
It is typically Hard
llu E
lI C
r-s
ne
• Excessive water is not allowed
tiv nd
ow
ec rla
to build up behind support
e
sp e
re itz
• Support measures not designed
ir w
he - S
to take the hydrostatic load
ft n
• Controlled handling of water,
O tio
collection and discharge
© a
n nd
• Inner lining to prevent water
tio ou
ra F
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Reinforced ribs of sprayed concrete
r-s
Alkali-free accelerators
ne
tiv nd
ow
Alkali-aggregate reaction reduction; by removal of the alkali content.
ec rla
Work safety improvement; by reduced aggressiveness of accelerator
e
sp e
re itz
Environmental protection improvement; by reducing the amount of
ir w
aggressive and harmful components being released to the ground water.
he - S
Final strength compensation; by forming a homogenous and compact
ft n
concrete matrix.
O tio
Alkali-free accelerators provides:
© a
n nd
Early strength of 1 MPa after 1 hour.
tio ou
accelerator.
st T
Low rebound.
llu E
lI C
Low corrosiveness.
©
Reduced permeability.
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Reinforced ribs of sprayed concrete
r-s
Alkali-free accelerators
ne
tiv nd
ow
No difference in personal dust
ec rla
e
exposure between the alkali-free
sp e
re itz
and silicate based accelerators.
ir w
he - S
Improved early strength
development for the alkali-free
ft n
O tio
accelerators compared to water
© a
n nd
glass.
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Reinforced ribs of sprayed concrete
r-s
Sprayed concrete linings in adverse rock mass conditions
ne
tiv nd
ow
Q-value < 1, bolting as support
ec rla
e
sp e
measure may not be adequate on its
re itz
own.
ir w
he - S
Rock mass between the bolts must be
ft n
stabilized by sprayed concrete.
O tio
Increased number of tunnelling
© a
n nd
projects encounters adverse rock
tio ou
r-s
ne
Sprayed concrete linings in adverse rock mass conditions
tiv nd
ow
ec rla
e
The aim: to try and
sp e
re itz
extend the application
ir w
he - S
of permanent support
by means of sprayed
ft n
O tio
concrete and rock
© a
n nd
bolts
tio ou
ra F
as 1>Q>0.001, the
lI C
Al ITA
application involving
reinforced ribs was
©
r-s
Sprayed concrete linings in adverse rock mass conditions
ne
tiv nd
ow
Type of Sprayed Reinforced Cast-in-
ec rla
Support and concrete 250 ribs and place
The most favorable
e
results from mm, concrete sprayed concrete
sp e
UDEC invert, rock concrete, 2 m lining
re itz
combinations for support calculations bolts spacing (RRS) t=0,6m
ir w
invert,
he - S
in the Frøya-tunnel were 0,4m roof
& walls
ft n
(CCA)
found to be as shown in
O tio
Max. 14.4mm 17.1mm 17.3mm
the table: © a
n nd Displacement
after equlibr.
tio ou
loading on bolts
st T
aperture
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Method advantages reinforced ribs
r-s
ne
tiv nd
ow
On-site materials
ec rla
e
sp e
On-site production
re itz
ir w
Convenient construction
he - S
ft n
Cost effective
O tio
© a
Ductile, allowing deformations without imposing
n nd
tio ou
load concentrations
ra F
st T
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Contractual matters
r-s
• The Owner carries the risk for the rock mass conditions
ne
tiv nd
ow
• The Contractor carries the risk for the appropriate and efficient handling of the
ec rla
works focusing to improve technical and organisational performance.
e
sp e
• The Owner is responsible for the collection of information on ground conditions.
re itz
ir w
All information is disclosed to the tendering contractors for their own
he - S
interpretation.
ft n
• The Owner presents their estimate on quantities on rock support, rock mass
O tio
grouting etc. all expected measures are quantified in the tenders/contracts.
© a
n nd
• The contracts include regulations for extension of construction time based on
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Construction
r-s
•High capacity equipment, multi-skilled workmen
ne
tiv nd
at the tunnelling face allowing high utilisation of
ow
ec rla
the equipment .
e
sp e
re itz
•Adaptability to the actual ground conditions,
ir w
careful following-up of the encountered rock mass
he - S
by mapping and classification for a best fit the of
ft n
O tio
rock support measures.
© a
n nd
•Observation of the ground behaviour by visual
tio ou
method.
lI C
Al ITA
r-s
In a broad perspective there are probably
ne
tiv nd
more common interests at the construction
ow
ec rla
site than interest of conflicts.
e
sp e
re itz
•Respect for the different roles and values
ir w
as tunnelling is a complex process and
he - S
various skills are needed at the
ft n
O tio
construction site.
© a
n nd
•Constructive co-operation between the
tio ou
been settled.
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Main principle: Apply rock support in accordance
ne
with the rock mass conditions encountered during
tiv nd
ow
ec rla
tunnelling
e
sp e
re itz
Support method can be quickly adjusted to meet
ir w
the continuously changing quality of rock mass
he - S
Experienced personnel are actively involved in
ft n
O tio
tunnelling process to make decisions on site
© a
n nd
Contract is flexible enough to allow revisions to be
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Extensive use of bolts and shotcrete, with
ne
tiv nd
ow
steel fibre reinforcement when required
ec rla
e
sp e
Cast-in-place concrete is only used in
re itz
ir w
adverse conditions
he - S
ft n
Spiling bolting and sprayed concrete arches
O tio
are used in connection with weakness© a
n nd
tio ou
zones
ra F
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Very good to extremely good rock mass:
ne
tiv nd
Only spot bolting
ow
ec rla
Poor to good rock mass:
e
sp e
Bolting with shotcrete
re itz
Length & pattern are decided by size of tunnel and the quality of
ir w
he - S
rock mass
Shotcrete with steel fibre up to 10mm thick, may increse to 20mm
ft n
O tio
for poorer rock mass
© a
Support is installed after each round of blasting
n nd
Adverse rock mass conditions:
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
CT-Bolt
st T
Spiling bolting
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Reinforced ribs of sprayed concrete
Alkali-free accelerators
r-s
ne
• Alkali-aggregate reaction reduction; by removal of
tiv nd
ow
the alkali content.
ec rla
• Work safety improvement; by reduced
e
sp e
aggressiveness of accelerator
re itz
• Environmental protection improvement; by
ir w
reducing the amount of aggressive and harmful • No difference in personal dust
he - S
components being released to the ground water. exposure between the alkali-free
ft n
• Final strength compensation; by forming a and silicate based accelerators.
O tio
homogenous and compact concrete matrix. • Improved early strength
© a
n nd development for the alkali-free
•Alkali-free accelerators provides:
tio ou
- Early strength of 1 MPa after 1 hour. accelerators compared to water
ra F
r-s
ne
Q-value < 1, bolting as support measure
tiv nd
ow
may not be adequate on its own.
ec rla
e
sp e
Rock mass between the bolts must be
re itz
stabilized by sprayed concrete.
ir w
he - S
Increased number of tunnelling projects
ft n
encounters adverse rock mass
O tio
conditions, thus alternative solutions © a
n nd
have been considered.
tio ou
ra F
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Reinforced ribs of sprayed concrete
r-s
ne
Sprayed concrete linings in adverse rock mass conditions
tiv nd
ow
ec rla
e
The aim: to try and
sp e
re itz
extend the application
ir w
he - S
of permanent support
by means of sprayed
ft n
O tio
concrete and rock
© a
n nd
bolts
tio ou
ra F
as 1>Q>0.001, the
lI C
Al ITA
application involving
reinforced ribs was
©
r-s
Sprayed concrete linings in adverse rock mass conditions
ne
tiv nd
ow
Type of Sprayed Reinforced Cast-in-
ec rla
Support and concrete 250 ribs and place
The most favorable
e
results from mm, concrete sprayed concrete
sp e
UDEC invert, rock concrete, 2 m lining
re itz
combinations for support calculations bolts spacing (RRS) t=0,6m
ir w
invert,
he - S
in the Frøya-tunnel were 0,4m roof
& walls
ft n
(CCA)
found to be as shown in
O tio
Max. 14.4mm 17.1mm 17.3mm
the table: © a
n nd Displacement
after equlibr.
tio ou
loading on bolts
st T
aperture
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Method advantages reinforced ribs
r-s
ne
tiv nd
ow
On-site materials
ec rla
e
sp e
On-site production
re itz
ir w
Convenient construction
he - S
ft n
Cost effective
O tio
© a
Ductile, allowing deformations without imposing
n nd
tio ou
load concentrations
ra F
st T
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Cave-in at Buon Kuop HPP - 5 km of headrace tunnel:
600
r -s
500
ne
tiv nd
450
ow
ec rla
400
e
sp e
350
re itz
300
ir w
250
he - S
200
ft n
52
311
570
870
1152
1434
1717
1999
2281
2563
2845
3127
3409
3691
3973
4265
O tio
© a
Two parallel tunnels with D = 9 m
n nd
tio ou
ra F
st T
llu E
=9m
AC
=9m
IT
©
22 m
lI
Al
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
60m
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
- No probe drilling
ra F
20 m wide
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Support measures in the first tunnel
• Concrete re-filling
• Spiling bolts (L=6 m, f=50 mm, d1=30 cm, d2=2 m)
r-s
• Half face and 1 m of manually excavation
ne
• Shotcrete, and
tiv nd
ow
• Steel ribs
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Support measures in the second tunnel
r-s
• Shotcrete, and
ne
• Steel ribs
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Numerical modelling Excavation with only spiling bolts: To study the support
efficiency of the spiling bolts;
● No support: >1500 mm
r-s
● Spiling bolts: 75 mm
ne
● Spiling bolts + bolt fixed: 20 mm
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Numerical modelleing - Excavation with spiling bolts and steel ribs, shotcrete:
To check the tunnel stability with the designed support measure.
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
All in all, the method
provides:
● With a proper tool and
r-s
input, complicated
ne
tiv nd
excavation and rock
ow
ec rla
support in an extremely
e
sp e
re itz
poor ground condition
ir w
can be modelled;
he - S
● Such complicated
ft n
O tio
support measure as
© a
n nd
spiling bolts can be
tio ou
convincingly
ra F
demonstrated;
st T
llu E
tools is considered to be
very useful tool in such
©
situations.
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
Conclusions
ne
tiv nd
ow
ec rla
Permanent sprayed concrete lining in active
e
sp e
re itz
design together with other tunnelling techniques;
ir w
he - S
is a cost effective and flexible tunnelling method,
ft n
O tio
which is utilising;
© a
n nd
the versatility of sprayed concrete,
tio ou
and fulfils;
ra F
st T
llu E
documentation
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
r-s
ne
Site Investigation, Design & Construction
tiv nd
ow
ec rla
of Hydro & Transport Tunnels
e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013
ir w
he - S
ft n
O tio
Disclaimer
© a
n nd
A. The speakers are presenting their own personal views and are not expressing the
tio ou
B. Papers and documents displayed or handed out during the Event are copyrighted.
llu E
lI C
The participants must observe and comply with all applicable law regulations
Al ITA