Estimate 101
WALL FOOTING
T
L = LENGTH
W
FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length LT (M) 32.00 M
Enter Width W (M) 0.30 M
Enter Thickness T (M) 0.15 M
TOTAL VOLUME OF CONCRETE: 1.44 CU.M.
# OF CEMENT BAGS 13.00 BAGS
VOL. OF SAND CU.M. 0.80 CU.M.
LT = TOTAL LENGTH/PERIMETER VOL. OF 3/4" GRAVEL CU.M. 1.50 CU.M.
W2
FORMULA: VOLUME = H * W1 * W2
H CLASS A CONCRETE MIX
Enter Height L (M) 2.70 M
VOLUME OF CONCRETE FOR EACH COLUME: 0.16 CU.M.
Number of Columns Units 4.00 Units
TOTAL VOLUME OF CONCRETE: 0.65 CU.M.
# OF CEMENT BAGS 6.00 BAGS
VOL. OF SAND CU.M. 0.40 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 0.70 CU.M.
CONCRETE BEAMS
FORMULA: VOLUME = LT * W * D
CLASS A CONCRETE MIX
LT EnterTotal Length LT (M) 108.00 M
Enter Width W (M) 0.20 M
BEAM DIMENSIONS: Enter Depth D (M) 0.30 M
D TOTAL VOLUME OF CONCRETE: 6.48 CU.M.
# OF CEMENT BAGS 59.00 BAGS
VOL. OF SAND CU.M. 3.30 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 6.50 CU.M.
W
CONCRETE STAIRS
RIPRAPING WORKS L
W1
Enter Height H (M)
Stones 2.00 M
Enterranging
Width 1 W1 (M) 0.30 M
from 15 W2 (M)
EntertoWidth
25 kgs2 0.60 M
Length L (M)
Enter with 20.00 M
atleast
50% of
Using: stones
H weighing
more
than 20
kgs, &
TOTAL
Class A SIDE AREA: 0.90 SQ.M.
Mixture
TOTAL VOLUME: 18.00 CU.M.
VOL. OF BOULDERS CU.M. 18.00 CU.M.
# OF CEMENT BAGS 47.00 BAGS
VOL. OF SAND CU.M. 2.60 CU.M.
W2
spacing
80 1.6 4 Layers 1.720 layer
FOOTING MATTING
Enter Footing Length L (M) 0.60 M
Enter Footing Width W (M) 0.60 M
Enter # of Bars along L # 4.00 Pcs
Enter Number of Bars along W # 4.00 Pcs
L Enter Number of Footing # 10.00 Units
Enter Clear Cover Cc (M) 0.050 M
Note: Standard Clear Cover for footing =0.05m to 0.075m
# of Bars
per Side Net. Length along L 0.50 M
W Net. Length along W 0.50 M
# OF REIN. BARS USED: 8.00 LHS
#16 TIE WIRE USED: 1.30 Kgs
Clear
Cover
Tie Bars
Spacing
LT = TOTAL LENGTH/PERIMETER
D1
H
Clear Cover
for
D2 columns =
0.40m
0.5 0.2
Use End Hook: 0.200 M
Total length of each bars should be more than or equal to: 2.20 M
Total Number of Vertical Bars @ 6M: 30.00 LHS
3
Cut Length of each stirrups: 0.90 M
Number of Stirrups per Column: 19.00 PCS
Total Number of Bars used for stirrups @ 6M : 29.00 LHS
1 0.2
Use End Hook: 0.200 M
Total length of each bars should be more than or equal to: 4.20 M
Total Number of Vertical Bars @ 6M: 48.00 LHS
6 Circular Stirrups
Cut Length of each stirrups: 0.90 M
Number of Stirrups per Column: 28.50 M
Total Number of Bars required for stirrups @ 6M : 35.00 LHS
#16 TIE WIRE required: 7.80 Kgs
Spiral Stirrups
Cut Length of each stirrups: 0.70 M
Number of Stirrup Loops per Column: 28.50 M
Total Number of Bars required for stirrups @ 6M : 30.00 LHS
#16 TIE WIRE required: 7.80 Kgs
L = Span
L/4
0.15
L
Column
Width
TOP BARS
# of 6m Length Deformed Bars required as Continuous Bars - PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 2.00 PCS
WEB BARS
0.15 L
0.15 L
Column
Width
NUMBER
BAR OF STEEL
SPACING BARS PER TIES (KGS)
IN CM. SQUARE
METER
10.000 4.369 0.592
CONCRETE STAIRS
Enter Riser Height RH (M) 0.20 M
TR Enter Tread Run TR (M) 0.30 M
W Enter Stair Width W (M) 1.00 M
Enter # of Steps N 10.00 Steps
RHEnter Stringer Thickness TS (M) 0.15 M
0.30 0.36 0.66
Enter Spacing (M)
0.30
Enter Spacing (M) Enter Steps Lateral Bar diameter (mm)
0.30 12
Enter Stringer Lateral Bar diameter (mm)
16 TS
NOTES: DOWELS FOR LATERAL BARS ARE ALREADY INCLUDED IN THE ESTIMATES
FOR STAIRS LANDINGS YOU MAY USE THE SLAB REINFORCEMENT CALCULATOR
CONCRETE CANAL
REINFORCEMENTS
# of Horizontal Bars Used at CHB Wall 73.00 PCS @ 6M
# of Horizontal Bars Used at Flooring 55.00 PCS @ 6M
# U Bars 168.00 PCS
# Bars Used for U Bars 69.00 PCS @ 6M
W2
W1
W1
NUMBER OF BOARD FOOT OF STUDS & NAILING JOIST PER SQUARE METER
Lumber size
SPACING IN CENTIMETER (CENTER TO CENTER)
in inches
30 x 30 30 x 60 40 x 40 40 x 60 60 x 60
1x2 4.103 3.147 3.189 2.686 2.268
2x2 8.198 6.293 6.379 5.373 4.594
2x3 12.284 9.440 9.569 8.060 6.898
2x4 16.414 12.592 12.758 10.746 9.195
L
Enter Length of Wall/Ceilling/Flooring L (M) 9.00 M
Enter Height of Wall/Ceilling/Flooring H (M) 3.00 M
Enter Constant Factor C 6.898
# OF BD.FT OF STUDS & NAILING JOIST USED: BD.FT 186.25 BD.FT.
# OF 1" CWNails Used for Boards (ONE SIDE) KGS 0.6 KGS
# OF 1" CWNails Used for Boards (TWO SIDES) KGS 1.1 KGS
# OF 2 1/2" CWNails Used for Joining the Studs together KGS 1.4 KGS
End
Roof Sheet Length 2
lapping
H
Ls
Span
Projection
(Bulada)
Pitch
12
Note: Must multiply by two if the other side of the roof is similar
R
o
o
f
W
i
d
t
h
Roof Width
ROOF ACCESSORIES
Primer for
3. Red Oxide ferrous and Paint Thinner 35 to 40
3 Hours
Primer non-ferrous sq.m.
materials
Rust
4. Red Lead preventive 30 to 40
primer for Paint Thinner 3 Hours
Primer sq.m.
ferrous
surfaces
For Steel,
6 hrs, allow
5. Epoxy Aluminum, Epoxy 30 to 40
Primer Galvanized Reducer overnight b4 sq.m.
iron recoating
Exterior &
30 minutes
1. Acrylic Interior 1/2 lts/ 4 lts allow 30 to 40
6 hrs b4
Latex Paint masonry water recoat sq.m.
surfaces
Exterior &
3. Acrylic Interior 30 minutes 30 to 40
Water allow 6 hrs b4
Gloss Latex masonry recoat sq.m.
surfaces
For furniture,
cabinets,
doors,
4. Latex Hi- windows, 1 Hour. Allow 30 to 40
Gloss Enamel tools, toys, Usse as is 4 hrs before sq.m.
recoating
wrought iron,
& primed
metals
ROOF PAINT
KIND OF PAINT USES THINING DRYING TIMECOVERAGE/Gal
3 hrs. allow
3. Flat wall for interior overnight 40 to 50
Enamel wall & ceilings Paint Thinner before sq.m.
recoating
for exterrior
wood and 6 hrs. allow
4. Exterior 30 to 35
properly Paint Thinner 48 hrs. before
Gloss paint sq.m.
primed metal recoating
surfaces
VARNISHING
KIND OF PAINT USES THINING DRYING TIMECOVERAGE/Gal
for floors,
1. Valspar or sidings 40 to 50
Paint Thinner 24 hours
Spar Varnish furnitures, sq.m.
deck of boats
for interior
2. Hi-solid new wood 10 minutes.
sanding furnitures Lacquer Allow 30 40 to 50
sealer and fixtures, Thinner minutes sq.m.
cabinet, before recoat
doors, etc.
for interior
4. Hi-solid new wood Allow 30
Semi-gloss furnitures, Lacquer minutes 30 to 40
cabinets, Thinner sq.m.
Lacquer before recoat
doors,
shelves, etc
for interior
wood
5. Hi-solid furniture, Lacquer Allow 30 30 to 40
dead flat cabinets, Thinner minutes sq.m.
Lacquer door jambs, before recoat
trim
panelling, etc.
for furnitures,
6. Water cabinets, Allow 30
Lacquer 30 to 40
white gloss doors, panel minutes
Thinner sq.m.
Lacquer and interior before recoat
walls
DETERMINING THE TOTAL MATERIALS USED FOR BEAMS & GIRDER FORMS
B
SCAFFOLDINGS
PARTS OF SCAFFOLDINGS
1. Vertical Support
2. Base of Vertical Support
3. Horizontal Member
4. Diagonal Braces
5. Block and Wedges
6. Nails & Bolts
COLUMN BEAM
Enter Column Height M 3.00 Enter Beam Length M 3.50
Enter # of Columns Units 10.00 Enter # of Beams Units 6.00
Total Column Height: 30.00 M. Ht. Total Beam Length: 21.00 M. Ht.
FLOORING
Enter Floor Area SQ.M. 80.00