AB8-ELE 75 - JPO - Generator Dismentling For 5 Yearly Maintenance

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

PAR Record AB8-ELE-75 Aban Job Planning Outline (JPO)(Form 1 of 2 for Assessing Work Permit Type/ No.

# Risk)

Main Generator dismantling for 5 yearly maintenance Task Date Isolation Certificate #
Task/Activity Entry Certificate # NA

1. Complete this Form. Identify Task Steps/Equipment/Participants & *Any Rescue Plan will Department Head Approval
Instructions Responsibilities require its own PAR Name / Job Position
2. Transfer the Task Steps to the Hazard Management Form and complete same
TASK EQUIPMENT

Item No Certification Who Inspects? Dropped Objects Potential


Confirmed?
1 Lot Electrical Hand tools and cable markers N/A Elec.

2 Multi meter Yes Elec.

TASK PARTICIPANTS

Task Ref. Name Signature* Position Performed Before? Identify Task Supervisor and
No Banks man (where
applicable)
1, 6 Ch. Elec

2-5, 7-13 Elec.

TASK PROCEDURES /JOB PLAN (Include a Planned TOFS as a specific task step prior to conducting any critical parts of the operation)

Step No. Who Performs Who Supervises Dropped Objects Potential

1 NA
Review and update Risk Assessment & conduct a pre-task meeting.
2 NA
Obtain required initial Cold Work Permit, Electrical Isolation Permit
3 Switch off the generator circuit breaker and generator space heater in NA
electrical control room

*By signing your name you are confirming you understand the task, your duties and that you accept the obligation to stop the job (TOFS) for any real or perceived QHSEconcern
SAF-018, 11.April 2012, Reference SAF 330.00Page 1 of 2
4 NA
Lockout and Tag out the circuit breaker
5 Visual inspection of work site and tools
NA

6 NA
PLANNED TIME OUT for Safety
7 NA
Dismantle all cables by marking before removing the connections
8 YES
Secure main cables & gland with properly slings.
9 NA
Dismantle engine coupling and secure the coupling
10 NA
Remove main JB and Main cable bus bar mountings & secure

11 YES
Shift the generator by using H beam chain blocks up to the hatch area.

12 Close Cold Work Permit & make long term isolation. NA

ENVIRONMENTAL PRECAUTIONS
Step Ref. Task Step / Environmental Hazard / Prevention Control Required Who Performs Who Supervises Dropped Objects Potential

13 When finished ensure all tools and work material are removed
from work area. (Hazardous/Non Hazardous waste) &
housekeeping NA

*By signing your name you are confirming you understand the task, your duties and that you accept the obligation to stop the job (TOFS) for any real or perceived QHSEconcern
SAF-018, 11.April 2012, Reference SAF 330.00Page 2 of 2