ID WBS Task Task Name Duration Start Finish 29 Sep '19 6 Oct '19 13 Oct '19 20 Oct '19

'19 6 Oct '19 13 Oct '19 20 Oct '19 27 Oct '19 3 Nov '19 10 Nov '19 17 Nov '19 24 Nov '19 1 Dec '19 8 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 5 Jan '20 12 Jan '20 19 Jan '20 26 Jan '20
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 1 Project Planning 14 days Tue 1/10/19 Fri 18/10/19
2 1.1 Sketch & Design 3 days Tue 1/10/19 Thu 3/10/19
3 1.2 Electrical Design 1 day Fri 4/10/19 Fri 4/10/19
4 1.3 3D Drawing 3 days Mon 7/10/19 Wed 9/10/19
5 1.4 Cost Estimation 4 days Thu 10/10/19 Tue 15/10/19
6 1.5 JKKP Authorization 1 day Fri 18/10/19 Fri 18/10/19
7 2 Construction 35 days Mon 21/10/19Fri 6/12/19
8 2.1 Unnecessary 5 days Mon Fri 25/10/19
Materials & 21/10/19
Components
9 2.2 Platform Construction
4 days Mon 28/10/19Thu 31/10/19
10 2.3 Shaft's Supporting 7 days Fri 1/11/19 Mon 11/11/19
wall construction

11 2.4 Building conduits 4 days Tue 12/11/19 Fri 15/11/19


12 2.5 landing door 9 days Mon Thu 28/11/19
construction 18/11/19

13 2.6 Lift Machine room 3 days Fri 29/11/19 Tue 3/12/19


14 2.7 Lift Interior (wall 3 days Wed 4/12/19 Fri 6/12/19
panels, ceiling &
flooring)
15 3 Installation 24 days Mon 9/12/19 Thu 9/1/20
16 3.1 Electrical 9 days Mon 9/12/19 Thu 19/12/19
17 3.1.1 Wiring 3 days Mon 9/12/19 Wed 11/12/19
18 3.1.2 Ventilation 2 days Thu 12/12/19 Fri 13/12/19
19 3.1.3 Lift control System
2 days Mon 16/12/19Tue 17/12/19
20 3.1.4 Trunking installation
1 day Wed 18/12/19Wed 18/12/19
21 3.1.5 lighting and speakers
1 day Thu 19/12/19 Thu 19/12/19
22 3.2 Mechnical 9 days Fri 20/12/19 Wed 1/1/20
23 3.2.1 Buffer Spring 2 days Fri 20/12/19 Mon 23/12/19
24 3.2.2 Control Box 2 days Tue 24/12/19 Wed 25/12/19
25 3.2.3 Roof pulley system
2 days Thu 26/12/19 Fri 27/12/19
26 3.2.4 Traction system 2 days Mon Tue 31/12/19
& Counter 30/12/19
weight
27 3.2.5 lift door controllers
1 day Wed 1/1/20 Wed 1/1/20
28 3.3 Safety and security6 days Thu 2/1/20 Thu 9/1/20
29 3.3.1 Emergency alarm1 day Thu 2/1/20 Thu 2/1/20
30 3.3.2 CCTV 1 day Fri 3/1/20 Fri 3/1/20
31 3.3.3 Fire extinguishers1 day Mon 6/1/20 Mon 6/1/20
32 3.3.4 Intercom 1 day Tue 7/1/20 Tue 7/1/20
33 3.3.5 Weight 2 days Wed 8/1/20 Thu 9/1/20
measuring
system
34 4 Commisioning 15 days Fri 10/1/20 Thu 30/1/20
35 4.1 Pilot testing 13 days Fri 10/1/20 Tue 28/1/20
36 4.1.1 Site clean up 3 days Fri 10/1/20 Tue 14/1/20
37 4.1.2 Testing 3 days Wed 15/1/20 Fri 17/1/20
38 4.1.3 Feedback 2 days Mon 20/1/20 Tue 21/1/20
39 4.1.4 Pilot Run 5 days Wed 22/1/20 Tue 28/1/20
40 4.2 Review 2 days Wed 29/1/20 Thu 30/1/20
41 4.2.1 Close meeting 1 day Wed 29/1/20 Wed 29/1/20
42 4.2.2 Project handover1 day Thu 30/1/20 Thu 30/1/20

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: EPM gantt chart
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 27/11/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress