'19 6 Oct '19 13 Oct '19 20 Oct '19 27 Oct '19 3 Nov '19 10 Nov '19 17 Nov '19 24 Nov '19 1 Dec '19 8 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 5 Jan '20 12 Jan '20 19 Jan '20 26 Jan '20
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 1 Project Planning 14 days Tue 1/10/19 Fri 18/10/19
2 1.1 Sketch & Design 3 days Tue 1/10/19 Thu 3/10/19
3 1.2 Electrical Design 1 day Fri 4/10/19 Fri 4/10/19
4 1.3 3D Drawing 3 days Mon 7/10/19 Wed 9/10/19
5 1.4 Cost Estimation 4 days Thu 10/10/19 Tue 15/10/19
6 1.5 JKKP Authorization 1 day Fri 18/10/19 Fri 18/10/19
7 2 Construction 35 days Mon 21/10/19Fri 6/12/19
8 2.1 Unnecessary 5 days Mon Fri 25/10/19
Materials & 21/10/19
Components
9 2.2 Platform Construction
4 days Mon 28/10/19Thu 31/10/19
10 2.3 Shaft's Supporting 7 days Fri 1/11/19 Mon 11/11/19
wall construction
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: EPM gantt chart
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 27/11/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress